Vinh Long freshwater reservoir infrastructure project reaches over 30% of volume, exceeding progress by nearly 10%

HOÀNG LỘC |

Vinh Long - Freshwater reservoir infrastructure project reached more than 30% of volume, exceeding nearly 10% of the plan, units are accelerating construction, shortening progress.

Workers unanimously stick to the project ahead of schedule

The freshwater reservoir infrastructure project in Vinh Long is a key project, of great significance in ensuring water sources for production and daily life for people, especially in the context of increasingly complex climate change. Right from the time of implementation, the project has received consensus and positive response from engineers, workers and laborers at the construction site.

Mr. Bui Xuan Thao - a project construction worker said that he clearly recognizes the practical significance of the project for the lives of local people. When completed, the reservoir will not only contribute to regulating water sources but also create a spacious landscape with a wide and synchronous embankment system.

Công nhân thi công trên công trường dự án hồ chứa nước ngọt tại Vĩnh Long, nỗ lực tăng ca đảm bảo tiến độ công trình. Ảnh: Hoàng Lộc
Workers constructing on the freshwater reservoir project site in Vinh Long, striving to work overtime to ensure project progress. Photo: Hoang Loc

According to Mr. Thao, that meaning helps each worker have more motivation and consciously improve their sense of responsibility in construction. "We are always aware that this is a long-term project, serving the community, so we try to work carefully, ensuring proper techniques so that the project achieves quality and progress," Mr. Thao shared.

Working directly at the construction site, Mr. Phan Thanh Trung said that the prolonged hot weather has caused many difficulties for workers. However, none of the workers have given up but still maintain continuous construction.

There are sunny days, but the brothers still work all day, overtime at night to keep up with the schedule. During the day, they use windbreakers and wide-brimmed hats to reduce heat and ensure health," Mr. Trung said.

Flexible construction, proactively overcoming material difficulties

Mr. Hoang Huan - Commander of the construction site of the freshwater reservoir infrastructure project in Vinh Long province said that the project implementation process encountered some difficulties in terms of weather and supply of construction materials, including a period of stone shortage lasting about 10 days.

During this time, the unit proactively adjusted the plan, switching to constructing items that are not dependent on rock such as excavating soil, making iron, digging pits to drive piles and other foundation work. This flexible approach helps the project not to be interrupted, still maintaining a stable construction pace.

After the material source was supplied again, the unit quickly increased equipment and manpower and organized overtime construction to compensate for the affected progress. Thanks to that, many important items still ensured the overall progress, even exceeding the set plan.

According to Mr. Huan, proactively managing and flexible construction plans is a key factor to help the project overcome difficulties and maintain progress in unfavorable construction conditions.

Chủ đầu tư dự án hồ chứa nước ngọt tại Vĩnh Long cùng đơn vị thi công kiểm tra, giám sát hiện trường, bảo đảm chất lượng và tiến độ công trình. Ảnh: Hoàng Lộc
The investor of the freshwater reservoir project in Vinh Long and the construction unit inspect and supervise the site, ensuring the quality and progress of the project. Photo: Hoang Loc

Mr. Lam Hoang Vu - Vinh Long Provincial Agricultural Project Management Board, the project investor, said that the freshwater reservoir infrastructure package has a total investment of 860 billion VND. Up to now, the disbursement progress has reached about 30%, while the actual construction volume has reached more than 30% compared to the plan.

Notably, compared to the initial plan, the current construction progress is exceeding by about 8-10%. According to the plan, the project is expected to be completed and put into use in the fourth quarter of 2027, but the construction unit is making efforts to shorten the time, striving to complete it in the first quarter of 2027.

Mr. Vu assessed that this result shows the great efforts of the units participating in the project in the context of many difficulties in weather and construction materials.

HOÀNG LỘC
RELATED NEWS

Tran Huynh Park Project: Golden land divided

|

Ca Mau - Many prolonged projects, causing public outrage such as Tran Huynh Park, Bac Lieu LNG, Khai Long Wind Power... will be inspected.

Workers constructing the largest freshwater reservoir in the West

|

With a capacity of about 1.3 million m3, Lac Dia Lake (Phu Le Commune, Ba Tri District, Ben Tre Province) is considered the largest artificial freshwater reservoir in the West under construction.

Spreading feedback that the competency assessment exam of Vietnam National University Ho Chi Minh City has errors

|

Social networks spread reflections that the second phase of the capacity assessment exam of Vietnam National University, Ho Chi Minh City appeared with blurred printing errors and missing data in one question.

Notes when moving, parking cars for long periods under intense heat

|

The following technical recommendations will help car drivers proactively protect their cars and move safely on hot sunny days.

Behind the million-view videos of Hanoi Traffic Police

|

Hanoi - Few people know that traffic propaganda videos that are attracting millions of views are all conceived and produced by Hanoi traffic police officers and soldiers themselves.

Leaked 10th grade exam questions in Nghe An are false information

|

Nghe An - The Provincial Department of Education and Training denies information about the leaked 10th grade entrance exam questions spreading on social networks.

Tran Huynh Park Project: Golden land divided

NHẬT HỒ |

Ca Mau - Many prolonged projects, causing public outrage such as Tran Huynh Park, Bac Lieu LNG, Khai Long Wind Power... will be inspected.

Hạ tầng hồ chứa nước ngọt tại Vĩnh Long hoàn thành vượt tiến độ 14 tháng

HOÀNG LỘC |

Vĩnh Long - Công trình hạ tầng hồ chứa nước ngọt sông Láng Thé khánh thành vượt tiến độ 14 tháng, là dự án trọng điểm chào mừng Đại hội Đảng bộ tỉnh lần thứ I.

Workers constructing the largest freshwater reservoir in the West

Thành Nhân |

With a capacity of about 1.3 million m3, Lac Dia Lake (Phu Le Commune, Ba Tri District, Ben Tre Province) is considered the largest artificial freshwater reservoir in the West under construction.