Tran Huynh Park Project: Golden land divided

NHẬT HỒ |

Ca Mau - Many prolonged projects, causing public outrage such as Tran Huynh Park, Bac Lieu LNG, Khai Long Wind Power... will be inspected.

Tran Huynh Park - a project with many public opinions

Among the projects inspected, Tran Huynh Park in Bac Lieu ward, Ca Mau province is a project that has caused much controversy and is of particular interest to people.

This park was planned by the People's Committee of Bac Lieu province (old) from 1997 with an area of more than 22 hectares, oriented to become a central park and a large public living space of the locality.

However, according to the 2016 inspection conclusion of the Bac Lieu Provincial Inspectorate (old), through many planning adjustments, the park area has continuously been narrowed.

Dự án Công viên Trần Huỳnh một thời được người dân Bạc Liêu - Cà Mau kỳ vọng, nay chỉ còn là dấu tích xưa (ảnh chụp năm 2018). Ảnh: Nhật Hồ.
Tran Huynh Park project once expected by the people of Bac Lieu, now only an old trace (photo taken in 2018). Photo: Nhat Ho

By 2012, the remaining area was about 146,695 m2 and was assigned to many organizations and businesses for management, exploitation and use.

According to the inspection conclusion, Quoc Lam Trading - Service Co., Ltd. was leased more than 41,000 m2 of land in the park area. Of which more than 6,700 m2 of commercial service land is leased by the State with annual payment; the rest is traffic land, green trees and lawns.

During the land use process, this enterprise was identified as carrying out many unlicensed construction items that were not in accordance with the plan. The enterprise also leased land to many individuals to open restaurants, cafes, game shops and other business activities in violation of regulations.

After the inspection conclusion, on October 15, 2018, the People's Committee of Bac Lieu province (old) issued a decision to recover more than 41,000 m2 of land from this enterprise to hand over to the Housing and Land Fund Development Center for management. Currently, this area has formed a commercial center and shophouse housing area.

Cam Quyen Trading - Service and Tourism Co., Ltd. was leased more than 13,000 m2 of land to invest in entertainment areas, restaurants, and hotels. To date, the business is still exploiting many service items such as wedding parties, restaurants and eateries.

Meanwhile, the Bac Lieu Provincial Youth Union (old) was allocated nearly 40,000 m2 of land to build the Youth Activity Center and Phung Ngoc Liem Children's Cultural House. However, many items here have been under construction for many years and show signs of degradation.

Many projects such as swimming pools, gymnasiums, and children's playgrounds have not been effective, overgrown with weeds, and facilities have deteriorated over time. The headquarters of the Youth Activities Center also showed signs of damage after a long period of ineffective use.

Another part of the area that was once assigned to Bac Lieu Electricity (old) as a temporary headquarters has now been handed over. However, many public land areas in the area are still unclear about the specific management unit.

Notably, some land plots that were previously concluded by the Bac Lieu Provincial Inspectorate (old) to be leased and used improperly, but so far the purchase and sale and exploitation still take place.

From the planned public park land of more than 22 hectares in 1997, after nearly 30 years, this place no longer has the appearance of a true central park. Many land areas have been converted into functions, and many public works are unfinished.

Review of a series of slow-progress projects

According to Decision No. 235/QD-TT dated April 29, 2026 of the Chief Inspector of Ca Mau province, the specialized inspection of projects with difficulties, obstacles, and prolonged backlogs is carried out according to Plan No. 1158/KH-TTCP dated April 22, 2026 of the Government Inspectorate.

The inspection period is determined from the project implementation time to March 31, 2026. In necessary cases, the inspection team will consider additional related contents before or after this period.

Một phần của dự án Nhà thiếu nhi Phùng Ngọc Liêm trong khu quy hoạch Công viên Trần Huỳnh, Cà Mau còn dở dang sau 10 năm xây dụng. Ảnh: Nhật Hồ
Part of the Phung Ngoc Liem Children's House project in the Tran Huynh Park planning area is still unfinished after 10 years of construction. Photo: Nhat Ho

According to the decision, there are 46 projects and works subject to inspection this time. These are all projects that have experienced difficulties, slow progress, prolonged backlogs or caused many opinions in local public opinion.

Some notable projects include the Bac Lieu LNG Liquefied Natural Gas Power Plant Project at Bac Lieu LNG Thermal Power Center; Project to upgrade and renovate Tran Huynh Park; Project to invest in the construction of technical infrastructure of the Administrative and Public Works Area at the Northeast gateway of Ca Mau City; Bac Lieu Trade Center Area Project; Project to invest in the construction of the Wind Power Plant in Khai Long - Ca Mau Tourist Area phase 1.

Khu đất vườn cao đến nay không biết đơn vị nào quản lý. Ảnh: Nhật Hồ.
The areca garden land area is currently unknown which unit manages it. Photo: Nhat Ho.

According to the plan, the inspection team will review the management and use of land; construction investment order; public asset management; and clarify the reasons why many projects have been prolonged for many years but have not been completely resolved.

This is considered a large-scale inspection of backlog projects in Ca Mau and Bac Lieu (old), especially in the context that many projects related to public land, urban planning and the use of public assets have caused public outrage for a long time.

Local people expect this inspection to clarify the responsibilities of related organizations and individuals; and at the same time remove long-standing backlogs in the management and use of public land to avoid generating bad public opinion that has lasted for many years.

NHẬT HỒ
RELATED NEWS

Ca Mau removes obstacles, accelerates key projects

|

Ca Mau - Many key projects are behind schedule due to lack of construction materials and site clearance problems.

Proposal for Ho Chi Minh City to restrict private cars from entering the center, applying fees to reduce congestion

|

Ho Chi Minh City is proposed to be granted the right to restrict private cars from entering the center, applying congestion reduction fees to reduce traffic jams and reduce emissions.

Iran accuses the US of violating the ceasefire agreement

|

Middle East tensions continue to escalate as new US airstrikes target Iran threaten the fragile negotiation process.

Series of "furnaces" for fasting and drinking alkaline ionized water to treat patients in Hanoi

|

Not a medical facility, without a team of doctors, but around Hanoi, a series of models are appearing of receiving patients to stay, fasting, and drinking alkaline ionized water to treat diseases.

Consolidating the Central Steering Committee for Anti-Corruption, Wastefulness, and Negative Phenomena

|

The Politburo has just issued a Decision to consolidate the Central Steering Committee for Anti-Corruption, Wastefulness, and Negative Phenomena.

Ca Mau removes obstacles, accelerates key projects

NHẬT HỒ |

Ca Mau - Many key projects are behind schedule due to lack of construction materials and site clearance problems.

Bạc Liêu khởi tố vụ án liên quan đến thu hồi Công viên văn hóa Trần Huỳnh

NHẬT HỒ |

Ngày 22.3, Cơ quan Cảnh sát điều tra Công an tỉnh Bạc Liêu cho biết, đã quyết định khởi tố vụ án hình sự “Vi phạm quy định về quản lý, sử dụng tài sản Nhà nước gây thất thoát, lãng phí và vi phạm quy định về bồi thường, hỗ trợ, tái định cư khi Nhà nước thu hồi đất” xảy ra trong quá trình thu hồi đất để thực hiện tại Dự án khu Trung tâm thương mại và nhà ở thương mại (Phường 7, thành phố Bạc Liêu, tỉnh Bạc Liêu).

Hàng loạt dự án "bất động" trên đất vàng ở Bạc Liêu

NHẬT HỒ |

Có những dự án đã hơn 20 năm, nhưng chưa bàn giao cho địa phương, chủ đầu tư vẫn sửa đường, trồng cây. Có dự án làm nửa chừng rồi thôi mặc cho người dân tranh chấp. Điều đáng nói, đây là những dự án nằm ngay trung tâm thành phố Bạc Liêu, tỉnh Bạc Liêu.