Road expansion project in Hanoi to be completed after 15 years of construction

SÓNG HỮU |

Hanoi - The National Highway 1A expansion project, Ngoc Hoi - Van Dien section, has completed more than 90% of the volume, of which the asphalt concrete item has been paved on the entire route.

According to the Hanoi Traffic Construction Investment Project Management Board, the Project to renovate and upgrade National Highway 1A, Van Dien - Ngoc Hoi section (Km185 - Km189) is a group B project, level I project.

The total length of the project is 3.8km, cross-section from 46 - 53m, including items: renovation, upgrading of foundation, road surface, drainage, technical trenches, lighting, sidewalks, green trees, traffic organization.

The total investment of the project is 887.735 billion VND (construction cost is 297.614 billion VND).

Project implementation time: 2011 - Q1/2026.

Regarding the capital plan, the Hanoi Traffic Construction Investment Project Management Board said that the accumulated disbursement to date is 774.074 billion VND. The 2026 plan has not been allocated.

To date, the entire project has completed site clearance work.

Regarding the construction situation, more than 90% of the total project volume has been completed (3.8km/3.8km of asphalt concrete paving has been completed), technical traffic was opened on December 31, 2025.

The investor is continuing to urge construction to complete the remaining items and complete the entire project in the first quarter of 2026 in accordance with the direction of the Hanoi Party Secretary in Notice No. 144-TB/TU dated December 22, 2025.

SÓNG HỮU
RELATED NEWS

A section of Ring Road 2.5 is both under construction and site clearance

|

Hanoi - The Ring Road 2.5 project section passing through Xuan Dinh ward has just organized construction, and has also carried out land acquisition and site clearance.

Completement milestone of the entire underpass project under the railway in Hanoi

|

Hanoi - The Ring Road 2.5 - Giai Phong underpass project, with a total investment of nearly 780 billion VND, will be fully completed in March 2026.

Women bring smiles and hope to patients

|

8. March is an occasion to honor women, and also a time to mention women who are working day and night in hospitals.

Import and export of 450 tons of goods on the first day of weekend customs clearance in Bac Luan II

|

Quang Ninh - Morning of March 7, the first day of week-end customs clearance pilot in the Bac Luan II bridge area, about 450 tons of goods were imported and exported.

Hoa Minzy publicly expresses her feelings for Captain Thang Van Cuong

|

Hoa Minzy has officially confirmed her relationship and introduced her military boyfriend to the audience.

US gasoline prices increase by 15% due to Middle East conflict

|

The disruption of the global energy supply chain caused gasoline and oil prices in the US to escalate rapidly, creating new pressure on consumers.

3 out of 4 Tet movies have surpassed hundreds of billions of VND in revenue

|

The 2026 Tet movie season recorded a rare achievement when up to three Vietnamese films released from the 1st day of Tet all achieved hundreds of billions of VND in revenue.

Live Vietnam Women's Team vs Taiwan (China) at Asian Cup 2026

|

Live football match Vietnam - Taiwan (China) women's team at Asian Cup 2026, taking place at 12:00 PM on March 7.

Hà Nội: Hoàn trả mặt đường tạm bợ sau thi công, tiềm ẩn nguy cơ mất an toàn

Minh Hạnh |

Hà Nội – Nhiều đoạn trên đường Đào Tấn được hoàn trả tạm bợ, mặt đường gồ ghề, gây khó khăn cho phương tiện, tiềm ẩn nguy cơ mất an toàn.

A section of Ring Road 2.5 is both under construction and site clearance

VIÊN NGUYỄN - SÓNG HỮU |

Hanoi - The Ring Road 2.5 project section passing through Xuan Dinh ward has just organized construction, and has also carried out land acquisition and site clearance.

Completement milestone of the entire underpass project under the railway in Hanoi

SÓNG HỮU |

Hanoi - The Ring Road 2.5 - Giai Phong underpass project, with a total investment of nearly 780 billion VND, will be fully completed in March 2026.