The Hanoi Traffic Construction Investment Project Management Board has provided information on the progress of the Ring Road 2.5 construction investment project (Dich Vong - Duong Dinh Nghe new urban area section; Vu Pham Ham - Tran Duy Hung section; Nguy Nhu Kon Tum - Nguyen Trai section).
Section 1: Dich Vong - Duong Dinh Nghe new urban area, about 0.71km long, 50m cross-section in Cau Giay ward, Yen Hoa ward (starting point at Dich Vong new urban area; ending point on Duong Dinh Nghe street).
Section 2: Vu Pham Ham - Tran Duy Hung, about 0.6km long, cross-section 40m in Yen Hoa ward (starting point at the Mac Thai Tong - Vu Pham Ham intersection; ending point at the Tran Duy Hung - Hoang Dao Thuy intersection).
Section 3: Nguy Nhu Kon Tum - Nguyen Trai, about 0.95km long, 40m cross-section in Thanh Xuan ward (starting point at the intersection of Hoang Dao Thuy - Nguy Nhu Kon Tum streets; ending point at Nguyen Trai street).
The project includes 4 component projects, including 3 component projects for site clearance (GPMB); 1 component project 2 (construction investment).
The total investment of the project is 432.261 billion VND (of which construction costs are 303.281 billion VND).
Implementation time (expected): 2025-2026.
Regarding site clearance work
Component project 1.1 in Cau Giay ward (Dich Vong - Duong Dinh Nghe new urban area section). The total area to be recovered is about 30,520m2.
359/359 graves have been relocated, reaching 100%; 24,656m2/30,520m2 of site clearance has been recovered, reaching 81%.
Component project 1. 2 in Yen Hoa ward: The total area to be recovered is about 30,614m2. The project has been approved in decision No. 129/QD-UBND dated February 5, 2026.
Moving 83/83 graves has been completed, reaching 100%; 366/366 land recovery plans have been issued. Survey and inventory of 168/366 plans have been completed; dossiers confirming the origin of land for 82/366 plans are being completed.
Component project 1. 3 in Thanh Xuan ward. The total area to be recovered is about 39,053.9m2, with about 5,000 people residing within the project area.
475/475 plans have been issued; 431/475 plans have been investigated, inventoried and confirmed the origin of land; 14/475 plans have been approved. 98/475 plans are currently being drafted. 10,000m2/39,053m2 has been recovered, reaching 25.6%.
Compared to the previous report period: Thanh Xuan Ward has approved 14 plans, land recovery reached about 25.6%; other wards are continuing to promote site clearance.
About construction work
On February 11, 2026, Hanoi City People's Committee approved the project in decision No. 674/QD-UBND. Hanoi Traffic Construction Investment Project Management Board is completing procedures to start the project: approved contractor selection plan for project implementation phase No. 189/QD-BQLCTGT dated February 13, 2026; approved task and cost estimate for construction drawing design No. 192/QD-BQLCTGT dated February 13, 2026.
The Project Management Board is also coordinating with the Department of Agriculture and Environment to inspect and organize additional landmark positioning on the map and on the ground.