National Highway 14B expansion project to be completed in 2025

Nguyễn Linh |

According to the Department of Transport of Da Nang City, the National Highway 14B expansion project is expected to be completed in 2025.

The project to renovate and upgrade National Highway 14B through Da Nang was started in November 2023 and was approved by the Ministry of Transport with a total investment of more than 788 billion VND. The project starts at Hoa Nhon commune and ends at Hoa Khuong commune (Hoa Vang district) with a total route length of 7.58 km. This project is currently being implemented on the scale of an urban main road, including 4 lanes for motor vehicles and 2 lanes for rudimentary vehicles.

To date, site clearance work has been completed with nearly 80% of compensation documents approved. Regarding construction, bridge, culvert, and road surface items are being implemented synchronously, although construction progress is slow in some sections due to lack of personnel and equipment. The project is expected to be completed in 2025, and efforts are being made to accelerate disbursement and strengthen construction work to ensure progress.

Previously, last August, Deputy Director of the Department of Natural Resources and Environment of Da Nang City, Vo Nguyen Chuong, said that the project to renovate and upgrade National Highway 14B, Da Nang City, due to historical reasons, this National Highway had no sidewalks, at the time of construction and completion of the road in 2005.

"Households living on both sides of the road have a difference in elevation of 0.5 - 4.0m. Therefore, to access the road, the household owner must fill the ground with soil to raise the ground. Furthermore, most households living on both sides of the road do business.

Therefore, households built expansions on the recovered and compensated area of ​​old 14B and on the area of ​​traffic safety corridor to do business" - Vo Nguyen Chuong said.

The Department of Natural Resources and Environment of Da Nang City has reported to the City People's Committee and proposed that the City People's Committee agree on the policy of supporting dismantling and relocation equivalent to 20% of the value of compensated assets.

Nguyễn Linh
RELATED NEWS

7 consecutive earthquakes border Da Nang and Quang Ngai

|

Quang Ngai - In two days, there have been at least 7 consecutive earthquakes in the mountainous area.

U17 Laos vs U17 Malaysia live in the semi-finals of the 2026 Southeast Asia tournament

|

Live football match U17 Laos vs U17 Malaysia in the semi-finals of the 2026 U17 Southeast Asian Championship at 3:30 PM today (April 22).

President Trump warns of the possibility of the US continuing airstrikes on Iran

|

President Donald Trump said that the US does not want to extend the ceasefire with Iran and can still continue airstrikes.

Dong Nai fireworks display in 12 wards on the occasion of April 30th

|

Dong Nai fireworks display on April 30th holiday in Tran Bien ward, Binh Phuoc ward and 10 new wards.

The Inspection Committee of the Journalists Association highly appreciates the operating results of the Journalists Association of Lao Dong Newspaper

|

According to the annual inspection and supervision plan for 2026, on April 22, the Inspection Board of the Vietnam Journalists Association had a working session with the Journalists Association of Lao Dong Newspaper.

Many Meritorious Artists and People's Artists have quit their profession and become freelancers due to injuries

|

National Assembly Deputy Trinh Thuy Mui shared that many artists who are proficient in their profession, meritorious artists, and people's artists have quit their profession and gone to other freelance jobs.

Long Thanh Airport recruits 400 personnel for commercial operation at the end of 2026

|

Dong Nai - Airports Corporation of Vietnam (ACV) is recruiting 400 personnel to work at Long Thanh airport when this project goes into commercial operation at the end of 2026.

Increase the base salary, reform salaries worthy of the position of commune-level civil servant

|

In addition to increasing the base salary, National Assembly deputies proposed salary reform commensurate with the job position of commune-level cadres and civil servants.

Đề xuất hỗ trợ di dời các hộ dân sống ven Quốc lộ 14B

Mai Hương |

Sở Tài nguyên và Môi trường TP Đà Nẵng đã đề nghị UBND thành phố thống nhất chủ trương hỗ trợ di dời các hộ dân sống hai bên Quốc lộ 14B.

Đà Nẵng khởi công Dự án cải tạo, nâng cấp Quốc lộ 14B hơn 788 tỉ đồng

Văn Trực |

UBND TP Đà Nẵng vừa khởi công Dự án cải tạo, nâng cấp Quốc lộ 14B đoạn đi qua TP Đà Nẵng với tổng chiều dài tuyến là 7,58km, mức đầu tư hơn 788 tỉ đồng.

Đà Nẵng chi gần 400 tỉ đồng để cải tạo, nâng cấp Quốc lộ 14B

An Thượng |

Đà Nẵng - Hội đồng Nhân dân thành phố Đà Nẵng đã thông qua Nghị quyết bố trí hơn 358 tỉ đồng vốn ngân sách địa phương để thực hiện Dự án cải tạo, nâng cấp Quốc lộ 14B - đoạn qua địa phận thành phố.