National Highway 14B expansion project to be completed in 2025

Nguyễn Linh |

According to the Department of Transport of Da Nang City, the National Highway 14B expansion project is expected to be completed in 2025.

The project to renovate and upgrade National Highway 14B through Da Nang was started in November 2023 and was approved by the Ministry of Transport with a total investment of more than 788 billion VND. The project starts at Hoa Nhon commune and ends at Hoa Khuong commune (Hoa Vang district) with a total route length of 7.58 km. This project is currently being implemented on the scale of an urban main road, including 4 lanes for motor vehicles and 2 lanes for rudimentary vehicles.

To date, site clearance work has been completed with nearly 80% of compensation documents approved. Regarding construction, bridge, culvert, and road surface items are being implemented synchronously, although construction progress is slow in some sections due to lack of personnel and equipment. The project is expected to be completed in 2025, and efforts are being made to accelerate disbursement and strengthen construction work to ensure progress.

Previously, last August, Deputy Director of the Department of Natural Resources and Environment of Da Nang City, Vo Nguyen Chuong, said that the project to renovate and upgrade National Highway 14B, Da Nang City, due to historical reasons, this National Highway had no sidewalks, at the time of construction and completion of the road in 2005.

"Households living on both sides of the road have a difference in elevation of 0.5 - 4.0m. Therefore, to access the road, the household owner must fill the ground with soil to raise the ground. Furthermore, most households living on both sides of the road do business.

Therefore, households built expansions on the recovered and compensated area of ​​old 14B and on the area of ​​traffic safety corridor to do business" - Vo Nguyen Chuong said.

The Department of Natural Resources and Environment of Da Nang City has reported to the City People's Committee and proposed that the City People's Committee agree on the policy of supporting dismantling and relocation equivalent to 20% of the value of compensated assets.

Nguyễn Linh
RELATED NEWS

Mr. Trump confirms the time of phone call with Mr. Xi Jinping

|

The phone call between US President Donald Trump and General Secretary and President of China Xi Jinping is scheduled to take place on September 19.

Low pressure surrounds the East Sea, rapidly strengthening, affecting Vietnam

|

According to the latest storm/low pressure information, there are currently 3 low pressure areas, disturbances in the East Sea and Northwest Pacific, with the risk of affecting Vietnam.

Gold price increases, be careful when trading or you will lose money or suffer from fraud

|

In the context of rising gold prices and high demand for buying, many subjects have impersonated reputable businesses to commit fraud and appropriate property.

The United States is about to stop importing many types of seafood from Vietnam from January 1, 2026

|

Minister Nguyen Hong Dien has just suggested that the US Department of Commerce reconsider the decision to refuse to recognize the equivalent of 12 Vietnamese seafood exploitation occupations.

Đề xuất hỗ trợ di dời các hộ dân sống ven Quốc lộ 14B

Mai Hương |

Sở Tài nguyên và Môi trường TP Đà Nẵng đã đề nghị UBND thành phố thống nhất chủ trương hỗ trợ di dời các hộ dân sống hai bên Quốc lộ 14B.

Đà Nẵng khởi công Dự án cải tạo, nâng cấp Quốc lộ 14B hơn 788 tỉ đồng

Văn Trực |

UBND TP Đà Nẵng vừa khởi công Dự án cải tạo, nâng cấp Quốc lộ 14B đoạn đi qua TP Đà Nẵng với tổng chiều dài tuyến là 7,58km, mức đầu tư hơn 788 tỉ đồng.

Đà Nẵng chi gần 400 tỉ đồng để cải tạo, nâng cấp Quốc lộ 14B

An Thượng |

Đà Nẵng - Hội đồng Nhân dân thành phố Đà Nẵng đã thông qua Nghị quyết bố trí hơn 358 tỉ đồng vốn ngân sách địa phương để thực hiện Dự án cải tạo, nâng cấp Quốc lộ 14B - đoạn qua địa phận thành phố.