400 billion VND school project in Quang Ngai abandoned

VIÊN NGUYỄN |

After 13 years of construction, the Dung Quat College of Economics and Technology project in Quang Ngai City is being abandoned , causing a waste of land.

The Dung Quat Vocational College of Economics and Technology project in Chanh Lo Ward, Quang Ngai City was granted an Investment Certificate in September 2011, with Dung Quat Vocational College of Economics and Technology (now Dung Quat Vocational College of Economics and Technology) as the investor. The project has an investment capital of 400 billion VND, with a usable area of ​​over 37,000m2.

The project campus is overgrown with grass. Photo: Vien Nguyen
The project campus is overgrown with grass. Photo: Vien Nguyen

The project is divided into 2 construction phases. According to the initial commitment, phase 1 was completed in 2012 and phase 2 in 2015. However, during the implementation process, the project was behind schedule, so after considering the difficulties and obstacles, the Provincial People's Committee allowed the investor to adjust the project implementation progress, phase 1 was completed in 2016 and phase 2 in 2017.

However, more than ten years after the start of construction, the project has not yet been completed. According to the reporter of Lao Dong Newspaper, the project is located in a prime location but is currently overgrown with grass. Many items are unfinished and then stopped, the steel is rusty, the concrete blocks are crumbling. The 3-storey building alone has been completed but is still abandoned.

The project's three-story building is basically complete, but has been abandoned for many years. Photo: Vien Nguyen
The project's three-story building is basically complete, but has been abandoned for many years. Photo: Vien Nguyen

On October 22, 2019, the Provincial People's Committee issued Decision No. 809 on extending the land use progress by 24 months for Dung Quat Vocational College of Economics and Technology to implement the project.

Up to now, the School has leveled over 95% of the area; completed and put into use a number of construction items and is completing a number of other items. However, due to the outbreak and prolongation of the Covid-19 pandemic at the end of 2019, experts, investors and contractors have not had the conditions to access the project, affecting the progress of the project.

Speaking to Lao Dong Newspaper reporter, Mr. Nguyen Duc Trung - Acting Director of the Department of Natural Resources and Environment of Quang Ngai province said that the Dung Quat College of Economics and Technology project was extended by the province for another 24 months. It is still within the deadline.

VIÊN NGUYỄN
TIN LIÊN QUAN

Nguyên giám đốc ở Quảng Ngãi nói không tư lợi khi làm dự án

VIÊN NGUYỄN |

Bị tố kê khai khống trong dự án dồn điền đổi thửa, ông N.K - nguyên Giám đốc Văn phòng đăng ký đất đai Quảng Ngãi khẳng định không chia chác, tư lợi.

Dự án bệnh viện tư nhân lớn nhất Quảng Ngãi làm xong phần móng rồi dừng

VIÊN NGUYỄN |

Dự án Khu dịch vụ chất lượng cao - Bệnh viện Đa khoa tỉnh Quảng Ngãi có tổng vốn đầu tư 1.100 tỉ đồng, nhưng làm xong phần móng rồi dừng.

Sau thanh tra, bệnh viện nghìn tỉ ở Quảng Ngãi vẫn là bãi cỏ hoang

VIÊN NGUYỄN |

Năm 2023, tỉnh Quảng Ngãi quyết định thu hồi khu đất dự án bệnh viện 1.100 tỉ đồng xây dựng dang dở rồi bỏ hoang để tổ chức đấu giá. Tuy nhiên đến nay bệnh viện vẫn đang trong tình trạng dang dở sau 7 năm triển khai thi công, gây lãng phí quỹ đất vàng, khiến người dân bức xúc.

Sập giàn giáo thi công hầm chui cao tốc Tuyên Quang-Hà Giang

Lam Thanh |

Giàn giáo thi công hầm chui tuyến cao tốc Tuyên Quang - Hà Giang đoạn qua địa phận xã Tứ Quận (huyện Yên Sơn, Tuyên Quang) vừa bị sập.

Lô đất trúng đấu giá hơn 100 triệu đồng/m2 ở Hà Nội bị bỏ cọc

CAO NGUYÊN |

Dù đã hết thời gian nộp tiền nhưng đến nay lô đất có giá trúng đấu giá hơn 100 triệu đồng/m2 ở huyện Thanh Oai (Hà Nội) vẫn chưa đóng tiền.

Hà Nội tắc đường cả cây số, người dân ì ạch di chuyển

Nhóm PV |

Tối 16.9, nhiều tuyến đường tại Hà Nội tắc cứng do giờ tan tầm và lượng người đổ ra đường đi chơi Trung thu.

Nga dồn ép quân Ukraina khỏi Kursk theo nhiều hướng

Song Minh |

Lực lượng Ukraina ngày càng bị đẩy lùi khỏi nhiều khu định cư ở tỉnh Kursk của Nga.

Cho thôi việc Bí thư huyện Vĩnh Cửu theo nguyện vọng

MINH CHÂU |

Ông Nguyễn Văn Thuộc - Bí thư Huyện ủy Vĩnh Cửu được Ban Thường vụ Tỉnh ủy Đồng Nai chấp thuận cho thôi việc theo nguyện vọng.