Deep under the mountain, workers work overnight to extend the Noi Bai - Lao Cai expressway

Bảo Nguyên - Duy Dũng |

In the midst of the cold mountains, workers take turns working on mountain drilling machines to dig tunnels determined to bring the Noi Bai - Lao Cai expressway expansion project to completion by the end of 2026.

The project to expand the Yen Bai - Lao Cai section of the Noi Bai - Lao Cai expressway has a total length of 121km, with a total investment of nearly 7,700 billion VND invested by Vietnam Expressway Corporation (VEC).

According to the design, the route will be expanded from 2 to 4 lanes, with a roadbed width of 24m. On the route, there is a 530m long Dai Viet tunnel, with a scale of 3 lanes, constructed by Song Da 10 MTV Co., Ltd.

Dự án có tổng chiều dài 121km, tổng mức đầu tư gần 7.700 tỉ đồng
The project has a total length of 121km, total investment of nearly 7,700 billion VND. Photo: Ha Thang

In the heart of the mountain, where the humidity is high and the temperature is always lower than outside, each drill bit still steadily goes deep into the rock.

Mr. Phung Duc Tue - Construction site commander of Song Da Company 10.1 - said that the unit organized continuous construction, without days off.

Each meter of tunnel being dug is the result of a tightly coordinated production line: drilling, blasting, excavating, spraying concrete, reinforcing tunnel arches. Just one step slow down, the entire progress will be affected," Mr. Tue said.

Hầm Đại Việt dài 530m, quy mô 3 làn xe đang được triển khai
Dai Viet tunnel is 530m long, with a scale of 3 lanes, which is being deployed. Photo: Ha Thang

To ensure safety and progress, more than 70 engineers and workers divided up to stick to the machine day and night. According to worker Ngo Duy Ngoc, they have been used to working overnight for more than two months now.

The night shift is the hardest when it's near dawn, cold and humid, people are easily tired. But brothers encourage each other to try harder, because the faster we work, the more convenient people travel," Mr. Ngoc shared.

In the same team as Mr. Ngoc, Mr. Nguyen Viet Vinh is in charge of checking and reinforcing the iron welds of the vault.

Building tunnels does not allow errors. Each weld must be carefully checked, ensuring technical correctness before confidently moving to the next stage. Tired is tiring, but looking at the rock gradually receding, seeing the tunnel getting longer day by day gives the brothers more motivation," Mr. Vinh said.

Mid-shift meals are carefully prepared by the unit right at the construction site, ensuring sufficient nutrition for workers working at high intensity. Temporary houses and mid-shift rest areas are arranged closedly, keeping warm, helping workers recover their health before starting a new shift.

Trong điều kiện thời tiết lạnh, độ ẩm cao, đơn vị vẫn tổ chức thi công liên tục “3 ca, 4 kíp”, hoàn toàn không có ngày nghỉ. Ảnh: Hà Thắng
In cold weather conditions, high humidity, the unit still organized continuous construction "3 shifts, 4 crews", completely without days off. Photo: Ha Thang

According to Mr. Nguyen Duc Thanh - official of the Northern Expressway Project Management Board (VEC), to date, the unit has drilled about 150m on the total length of 530m of Dai Viet tunnel.

In which, the tunnel entrance towards Lao Cai has been excavated and reinforced to reach 86m, exceeding the plan by 26m; the tunnel entrance towards Hanoi reached 74m, exceeding 27m. Overall, the tunnel construction progress is exceeding the plan by nearly 30 days.

Leaders of the Northern Expressway Project Management Board emphasized that accelerating the progress of Dai Viet tunnel is identified as one of the "key points" of the entire expansion project.

When completed, the expressway will increase traffic capacity, reduce congestion, and shorten travel time between the northern midlands and mountainous provinces and Hanoi Capital.

Bảo Nguyên - Duy Dũng
RELATED NEWS

Continuous accidents in the area of Noi Bai - Lao Cai expressway expansion construction

|

In just one day, March 3rd, two consecutive accidents occurred in the construction area of the Noi Bai - Lao Cai expressway expansion.

Acceleration at the Noi Bai - Lao Cai expressway construction site after the Tet holiday

|

After the Lunar New Year holiday, engineers and workers returned to the Noi Bai - Lao Cai expressway expansion site to work to bring the project to completion by the end of 2026.

Noi Bai - Lao Cai expressway "races" progress before the rainy and flood season

|

Lao Cai - The project to upgrade the Noi Bai - Lao Cai expressway in the last days of the year is still taking place urgently and vibrantly.

Experts talk about the operating efficiency of E10 gasoline

|

E10 gasoline contains 10% ethanol with oxygen content, which helps the burning process in the engine to be more complete and cleaner.

Truck loses control and plunges into abyss on National Highway 37, one person dies

|

Son La - While moving on National Highway 37, a truck suddenly plunged into a ravine, killing one person on the spot and seriously damaging the vehicle.

Launching Workers' Month in the Textile and Garment industry

|

Ho Chi Minh City - Vietnam National Textile and Garment Union launches Workers' Month and Action Month on Occupational Safety and Health in 2026.

Ho Chi Minh City Aquatic Sports Center denies reports of encroachment on Da Bang Lake while preparing for boat racing

|

According to the Ho Chi Minh City Aquatic Sports Center, the preparation for the boat race at Da Bang Lake to serve the Games is not against regulations.

A young person who has worked hard for 30 years cannot afford to buy a house

|

House prices in Hanoi and Ho Chi Minh City are 25-30 times higher than the average annual income, causing young people who have worked hard for 30 years to not be able to buy a house.

Continuous accidents in the area of Noi Bai - Lao Cai expressway expansion construction

Duy Dũng |

In just one day, March 3rd, two consecutive accidents occurred in the construction area of the Noi Bai - Lao Cai expressway expansion.

Acceleration at the Noi Bai - Lao Cai expressway construction site after the Tet holiday

Duy Dũng - Văn Đức |

After the Lunar New Year holiday, engineers and workers returned to the Noi Bai - Lao Cai expressway expansion site to work to bring the project to completion by the end of 2026.

Noi Bai - Lao Cai expressway "races" progress before the rainy and flood season

Văn Đức |

Lao Cai - The project to upgrade the Noi Bai - Lao Cai expressway in the last days of the year is still taking place urgently and vibrantly.