Deep under the mountain, workers work overnight to extend the Noi Bai - Lao Cai expressway

Bảo Nguyên - Duy Dũng |

In the midst of the cold mountains, workers take turns working on mountain drilling machines to dig tunnels determined to bring the Noi Bai - Lao Cai expressway expansion project to completion by the end of 2026.

The project to expand the Yen Bai - Lao Cai section of the Noi Bai - Lao Cai expressway has a total length of 121km, with a total investment of nearly 7,700 billion VND invested by Vietnam Expressway Corporation (VEC).

According to the design, the route will be expanded from 2 to 4 lanes, with a roadbed width of 24m. On the route, there is a 530m long Dai Viet tunnel, with a scale of 3 lanes, constructed by Song Da 10 MTV Co., Ltd.

Dự án có tổng chiều dài 121km, tổng mức đầu tư gần 7.700 tỉ đồng
The project has a total length of 121km, total investment of nearly 7,700 billion VND. Photo: Ha Thang

In the heart of the mountain, where the humidity is high and the temperature is always lower than outside, each drill bit still steadily goes deep into the rock.

Mr. Phung Duc Tue - Construction site commander of Song Da Company 10.1 - said that the unit organized continuous construction, without days off.

Each meter of tunnel being dug is the result of a tightly coordinated production line: drilling, blasting, excavating, spraying concrete, reinforcing tunnel arches. Just one step slow down, the entire progress will be affected," Mr. Tue said.

Hầm Đại Việt dài 530m, quy mô 3 làn xe đang được triển khai
Dai Viet tunnel is 530m long, with a scale of 3 lanes, which is being deployed. Photo: Ha Thang

To ensure safety and progress, more than 70 engineers and workers divided up to stick to the machine day and night. According to worker Ngo Duy Ngoc, they have been used to working overnight for more than two months now.

The night shift is the hardest when it's near dawn, cold and humid, people are easily tired. But brothers encourage each other to try harder, because the faster we work, the more convenient people travel," Mr. Ngoc shared.

In the same team as Mr. Ngoc, Mr. Nguyen Viet Vinh is in charge of checking and reinforcing the iron welds of the vault.

Building tunnels does not allow errors. Each weld must be carefully checked, ensuring technical correctness before confidently moving to the next stage. Tired is tiring, but looking at the rock gradually receding, seeing the tunnel getting longer day by day gives the brothers more motivation," Mr. Vinh said.

Mid-shift meals are carefully prepared by the unit right at the construction site, ensuring sufficient nutrition for workers working at high intensity. Temporary houses and mid-shift rest areas are arranged closedly, keeping warm, helping workers recover their health before starting a new shift.

Trong điều kiện thời tiết lạnh, độ ẩm cao, đơn vị vẫn tổ chức thi công liên tục “3 ca, 4 kíp”, hoàn toàn không có ngày nghỉ. Ảnh: Hà Thắng
In cold weather conditions, high humidity, the unit still organized continuous construction "3 shifts, 4 crews", completely without days off. Photo: Ha Thang

According to Mr. Nguyen Duc Thanh - official of the Northern Expressway Project Management Board (VEC), to date, the unit has drilled about 150m on the total length of 530m of Dai Viet tunnel.

In which, the tunnel entrance towards Lao Cai has been excavated and reinforced to reach 86m, exceeding the plan by 26m; the tunnel entrance towards Hanoi reached 74m, exceeding 27m. Overall, the tunnel construction progress is exceeding the plan by nearly 30 days.

Leaders of the Northern Expressway Project Management Board emphasized that accelerating the progress of Dai Viet tunnel is identified as one of the "key points" of the entire expansion project.

When completed, the expressway will increase traffic capacity, reduce congestion, and shorten travel time between the northern midlands and mountainous provinces and Hanoi Capital.

Bảo Nguyên - Duy Dũng
RELATED NEWS

Continuous accidents in the area of Noi Bai - Lao Cai expressway expansion construction

|

In just one day, March 3rd, two consecutive accidents occurred in the construction area of the Noi Bai - Lao Cai expressway expansion.

Acceleration at the Noi Bai - Lao Cai expressway construction site after the Tet holiday

|

After the Lunar New Year holiday, engineers and workers returned to the Noi Bai - Lao Cai expressway expansion site to work to bring the project to completion by the end of 2026.

Noi Bai - Lao Cai expressway "races" progress before the rainy and flood season

|

Lao Cai - The project to upgrade the Noi Bai - Lao Cai expressway in the last days of the year is still taking place urgently and vibrantly.

Rose in the middle of summer" and the reason why short films force viewers to spend money

|

From a few-minute clip on social networks, many viewers are gradually drawn into the world of mini-dramas and short films like "Roses in the middle of summer".

Spain denies US cooperation claim

|

Spain denies US concession information after trade warning.

Deep under the mountain, workers work overnight to extend the Noi Bai - Lao Cai expressway

|

In the midst of the cold mountains, workers take turns working on mountain drilling machines to dig tunnels determined to bring the Noi Bai - Lao Cai expressway expansion project to completion by the end of 2026.

Trade union news: Appropriate pension increase for retirees before 1995

|

Trade union news bulletin includes: Increasing pensions for retirees before 1995; Requesting businesses not to work overtime on March 15 for workers to vote...

Singer Kasim Hoang Vu passed away at the age of 46

|

Singer Kasim Hoang Vu - a rock voice familiar to Vietnamese audiences has passed away in the US after a long time fighting illness.

Continuous accidents in the area of Noi Bai - Lao Cai expressway expansion construction

Duy Dũng |

In just one day, March 3rd, two consecutive accidents occurred in the construction area of the Noi Bai - Lao Cai expressway expansion.

Acceleration at the Noi Bai - Lao Cai expressway construction site after the Tet holiday

Duy Dũng - Văn Đức |

After the Lunar New Year holiday, engineers and workers returned to the Noi Bai - Lao Cai expressway expansion site to work to bring the project to completion by the end of 2026.

Noi Bai - Lao Cai expressway "races" progress before the rainy and flood season

Văn Đức |

Lao Cai - The project to upgrade the Noi Bai - Lao Cai expressway in the last days of the year is still taking place urgently and vibrantly.