Ring Road 2 in Lao Cai has not yet reached the finish line after 6 years of construction

Đinh Đại |

Lao Cai - Due to problems in land acquisition, the Ring Road 2 project has not yet been completed.

Unable to remove obstacles

In mid-May, Lao Dong recorded that at the Ring Road 2 project, running along Na Hoi - Ta Chai commune of Bac Ha district with an investment capital of 300 billion VND, after many years of construction, this road is still not completed.

The main reason for the road's inability to be completed is due to problems with site clearance.

Con duong vanh dai 2 chua the hoan thien sau nhieu nam thi cong. Anh: Dinh Dai
Ring Road 2 has not been completed after many years of construction. Photo: Dinh Dai

Ms. Sung Thi Xuong (Na Hoi commune, Bac Ha district) said: "For the past 5 years, we have had to live in these temporary tents. People always support the state in building roads to promote economic development. But the government has confiscated all agricultural land not within the road boundary".

According to Ms. Xuong, her family's house is located outside the land for road construction but has been reclaimed for a subdivision and resettlement project.

"If the road construction area is close to the house, we are ready to donate land for expansion. But the road to the house is still far away and the government collects all of it, I disagree," Ms. Xuong explained.

Ms. Sung Thi Yen also shared: All households affected by the Ring Road 2 project agree with the policy of building a traffic road. However, the reclamation of too much agricultural land on both sides of the road is unreasonable".

Ms. Yen said that the width of the road and sidewalk is about 20.5m, so the land recovery outside the above area is not correct.

Due to the inability to resolve the problem in land recovery, 8 households are continuing to file complaints to the Central Government.

Nhieu dien tich dat 2 ben duong da duong quay kin ton. Anh: Dinh Dai
Many areas of land on both sides of the road have been surrounded by corrugated iron. Photo: Dinh Dai

Continue to extend the progress

According to the investigation, the construction unit of the Ring Road 2 project is a joint venture of Anh Nguyen Company Limited - Vu Thanh Company Limited. The project started in 2019, expected to be completed in 1,000 days.

According to statistics, there are a total of 420 households in the area affected by the project. The area of compensation and site clearance land is 36.9 hectares, of which the area for traffic works is 25.9 hectares, the area for residential areas is 11 hectares.

Due to waiting for the site for too long, one of the two units, Vu Thanh Company Limited, has withdrawn from the project since mid-2024.

Currently, only Anh Nguyen Company Limited is building branch routes. The areas where land was recovered along both sides of the road have been surrounded by corrugated iron.

On May 18, speaking with Lao Dong, the leader of the Bac Ha District Construction Investment Project Management Board - said that due to land clearance problems, the Ring Road 2 project has been extended and the completion time has been postponed to May 2025. However, this route has not been able to reach the finish line as planned and is being extended to December 31, 2025.

In addition, after Vu Thanh Company Limited withdraws, a subcontractor will be added to work with Anh Nguyen Company Limited to construct the project.

Trong khi cho giai quyet don tu, nhieu ho dan phai song tam trong leu bat. Anh: Dinh Dai
While waiting for the settlement, many households have to temporarily live in tents. Photo: Dinh Dai

Mr. Nguyen Ngoc Hai - Chairman of Na Hoi Commune People's Committee informed: "The Ring Road 2 project through the new commune has only been constructed for about 1.2/4.3 km, partly due to land clearance problems".

Secretary of the Bac Ha District Party Committee Nguyen Duy Hoa also said: "The district has also tried very hard to listen, but after the dialogues, households have made recommendations and the government has not yet reached a common voice on any solution. This is a very difficult story, so in the coming time, the locality will continue to propagate and mobilize people".

Previously, Lao Dong Newspaper published a series of articles "People living miserably on the 300 billion VND road project in Lao Cai" and "The Chairman of Bac Ha District talks about the 300 billion VND road behind schedule" reflecting on the Ring Road 2 project in Bac Ha District.

Up to now, despite many dialogues, there is still no specific solution and people are continuing to send petitions to the Central level to claim their rights.

Đinh Đại
TIN LIÊN QUAN

Lao Cai to open International Tourism Fair with 130 booths

|

Lao Cai - Lao Cai International Tourism Fair 2025 is an opportunity for domestic and international tourism service businesses to introduce their products.

Many problems in the prolonged complaint on Lao Cai Ring Road 2

|

Lao Cai - After many meetings, the difficulties and problems at the Ring Road 2 project in Bac Ha district have not been completely resolved.

People live miserably next to the 300 billion VND road project in Lao Cai

|

For the past four years, many households in Na Hoi Commune, Bac Ha District, Lao Cai Province have been living in makeshift huts after their homes were confiscated to make way for the beltway project. Meanwhile, the completion date of this VND300 billion transport project remains unclear.

European weapons continue to flow into Ukraine despite strong warnings from Russia

|

Several European countries continue to provide military aid to Ukraine, despite Russia's warnings that the move would prolong the conflict.

HCMC is about to build 4 more bridges in Nha Be district, with a total capital of VND 12,500 billion

|

Ho Chi Minh City is about to deploy the construction of 4 large bridges in Nha Be district including Can Gio, Phu Xuan 2B, Rach Tom and Rach Doi bridges, with a total investment of about VND 12,500 billion.

Nam Dinh Club won big against Hoang Anh Gia Lai at Thien Truong

|

On the evening of May 18, Nam Dinh club won 6-1 against Hoang Anh Gia Lai in round 23 of V.League 2024-2025.

Ring Road 2 in Lao Cai has not yet reached the finish line after 6 years of construction

|

Lao Cai - Due to problems in land acquisition, the Ring Road 2 project has not yet been completed.

Rescuing a 19-year-old girl who panicked because she was trapped in an elevator in Ho Chi Minh City

|

HCMC - A 19-year-old girl panicked because of an elevator stuck in District 1, and was quickly rescued safely by the Fire Prevention and Rescue Police - HCMC Police.

Lao Cai to open International Tourism Fair with 130 booths

Bảo Nguyên |

Lao Cai - Lao Cai International Tourism Fair 2025 is an opportunity for domestic and international tourism service businesses to introduce their products.

Many problems in the prolonged complaint on Lao Cai Ring Road 2

Đinh Đại |

Lao Cai - After many meetings, the difficulties and problems at the Ring Road 2 project in Bac Ha district have not been completely resolved.

People live miserably next to the 300 billion VND road project in Lao Cai

Đinh Đại |

For the past four years, many households in Na Hoi Commune, Bac Ha District, Lao Cai Province have been living in makeshift huts after their homes were confiscated to make way for the beltway project. Meanwhile, the completion date of this VND300 billion transport project remains unclear.