Monitor progress of key projects in Quang Tri

HƯNG THƠ |

After starting key projects with large total investment capital, leaders of Quang Tri province regularly inspect and monitor progress and remove problems.

At the end of 2023 and in 2024, in Quang Tri province, construction will begin and deploy 3 key projects, with a total investment of trillions of VND.

For example, the My Thuy Port Area project (Hai An commune, Hai Lang district, Quang Tri province) was approved by the Government for investment policy in 2019, with a scale of 685 hectares, by My International Port Joint Venture Joint Stock Company. Thuy (MTIP) is the investor with a total investment capital of 14,234 billion VND. 5 years ago, this project had a groundbreaking ceremony, but for many reasons it was delayed, until the end of March 2024 it was officially completed.

Most recently, in early July 2024, the Quang Tri Airport project (Quang Tri Airport) started construction. This project has a total investment of more than 5,800 billion VND implemented in Gio Linh district (Quang Tri province) with a scale of more than 265 hectares. It is expected that by July 2026, Quang Tri airport will be put into operation and use.

Previously, at the end of December 2023, the Quang Tri Industrial Park Project with a total investment capital of 2,074 billion VND deployed in Hai Lang district officially started construction. This project has an area of ​​481 hectares, developed in 12 years. When put into operation, the project is expected to create jobs for 30,000 to 40,000 workers.

Leaders of Quang Tri province inspected the construction site of the Quang Tri Airport project and gave gifts to encourage the construction unit. Photo: H.Nguyen.
Leaders of Quang Tri province inspected the construction site of the Quang Tri Airport project and gave gifts to encourage the construction unit. Photo: H.Nguyen.

The above 3 projects are key projects in Quang Tri province. Once completed and put into operation, they will bring many meanings and create motivation to promote the local socio-economic development.

Mr. Vo Van Hung - Chairman of Quang Tri Provincial People's Committee said that the process of implementing the above three key projects encountered many difficulties, especially site clearance, but the locality has mobilized units to participate. disassemble.

To support the project and grasp difficulties and problems, leaders of Quang Tri province regularly conduct field inspections. If the construction does not take place according to the committed schedule, corrective measures will be taken. If there are any problems, they will be resolved immediately.

Most recently, on August 6, Mr. Vo Van Hung and representatives of departments, branches and localities went to inspect the implementation of the Quang Tri airport project. After 1 month of starting the project, the investor has deployed mine clearance and is constructing public service roads. The current problem is that the People's Committee of Gio Linh district has just completed site clearance of an area of ​​148.1 hectares/265.3 hectares.

Chairman of Quang Tri Provincial People's Committee emphasized that the project has been implementing basic construction to ensure on schedule and quality. Regarding policies to support site clearance, Mr. Vo Van Hung suggested some solutions and proposed to complete and hand over clean site to investors to implement the project on schedule.

"With key projects, after starting construction, provincial leaders regularly check the progress and, if they have not met the target, request corrections. In addition, the locality always accompanies and removes difficulties and obstacles during the project implementation process. The local wish is for the projects to be deployed smoothly and on schedule to soon come into operation. local economic and social development" - Mr. Vo Van Hung said.

HƯNG THƠ
TIN LIÊN QUAN

Đẩy mạnh đầu tư công, không để dự án trọng điểm chờ mặt bằng

Phạm Đông |

Ủy viên Bộ Chính trị, Thủ tướng Chính phủ Phạm Minh Chính chỉ đạo không để tình trạng dự án chờ mặt bằng, đặc biệt là các dự án quan trọng quốc gia, dự án cao tốc, trọng điểm, đường liên vùng, đường ven biển.

Quảng Trị thúc các đơn vị đẩy nhanh tiến độ các dự án trọng điểm

HƯNG THƠ |

Trong 9 dự án trọng điểm với tổng vốn đầu tư hàng chục nghìn tỉ đồng ở tỉnh Quảng Trị, không ít dự án đang gặp các vướng mắc dẫn đến chậm tiến độ đề ra. Vì vậy, tỉnh Quảng Trị phát động đợt cao điểm đẩy nhanh tiến độ thực hiện các dự án trọng điểm.

Các dự án trọng điểm ở Quảng Trị đều gặp vướng mắc về giải phóng mặt bằng

HƯNG THƠ |

Các dự án trọng điểm của tỉnh Quảng Trị, gồm Khu công nghiệp Quảng Trị, Khu bến cảng Mỹ Thủy và Đường ven biển kết nối Hành lang kinh tế Đông Tây tỉnh Quảng Trị đều gặp khó khăn liên quan đến giải phóng mặt bằng.

Nguyện vọng của trái chủ trong vụ Vạn Thịnh Phát giai đoạn 2

NHÓM PV |

TPHCM - Nhiều bị hại liên quan đến sai phạm xảy ra ở Tập đoàn Vạn Thịnh Phát, Ngân hàng TMCP Sài Gòn đã có mặt tại TAND TPHCM để theo dõi phiên xét xử.

Mưa ngập, hơn 11.000 học sinh vùng trũng ở Hà Tĩnh nghỉ học

TRẦN TUẤN |

Sáng 20.9, tại huyện Hương Khê và Hương Sơn (Hà Tĩnh) xảy ra mưa lớn, ngập cục bộ nên hơn 11.000 học sinh ở khu vực trũng thấp được cho nghỉ học.

So sánh hình ảnh TP Yên Bái hiện tại và thời điểm bão lũ lịch sử

Trần Bùi - Vũ Bảo |

Trận đại hồng thủy đã đi qua TP Yên Bái gần 10 ngày, hiện nước đã rút, đường đã khô, cuộc sống người dân đã dần ổn định trở lại.

Giá vàng hôm nay 20.9: Vàng nhẫn tăng sốc

Khương Duy |

Giá vàng hôm nay 20.9 tăng mạnh ở thị trường trong nước và thế giới. Giá vàng nhẫn tròn trơn 9999 sáng nay sắp bằng giá vàng miếng SJC.

Giám đốc công ty làm máy nhắn tin cho Hezbollah bị điều tra

Anh Vũ |

Công ty Gold Apollo, có trụ sở tại Đài Loan (Trung Quốc), đang bị điều tra liên quan đến vụ nổ hàng nghìn máy nhắn tin của lực lượng Hezbollah.