On August 23, Chairman of the People's Committee of Thai Binh province Nguyen Khac Than and Vice Chairman of the People's Committee of Hai Phong City Nguyen Duc Tho jointly inspected the progress of the investment project to build a bridge over the Hoa River and the section through Hai Phong of the road route. From Thai Binh city go to Thousand bridge.
The investment project to build a bridge over Hoa River has a length of 411.2, a retaining wall of 140m long; bridge width 22.5m; Clearance for navigation BxH=30mx6m; Build a connecting road according to the scale of a level II plain road, with a cross-section of 22.5m wide and a length of 1,882m. The project belongs to group B traffic works, with a total investment of more than 760 billion VND.
When the project is completed, it will shorten travel time between Thai Binh and Nam Dinh provinces with Hai Phong city and Quang Ninh province, reduce the load on current National Highway 10, and reduce traffic accidents in the area; create favorable conditions to attract investment, contributing to promoting socio-economic development between Thai Binh province and Hai Phong city.
According to the Hai Phong Transport Construction Investment Project Management Board, to serve the project, the total land recovery area in Hai Phong is 7.43 hectares, involving 222 households, of which residential land ( 0.56ha), agricultural land (6.08ha), traffic corridor land). Up to this point, the authorities have inventoried the land of 222 households and handed over the premises of 211 households; The remaining 11 households have not yet handed over their land. The total area of land that Thai Binh has to recover is 1.62 hectares. Currently, Quynh Phu District People's Committee has handed over 1.62 hectares of land.
Currently, contractors are focusing on implementing the construction of bored piles, pedestals, bodies, beams and caps of the pillars; box retaining wall; Soil piles reinforce roadbed cement; Super T beam, the completed volume value is about 23.3% of the contract value.
After directly inspecting the construction site and listening to representatives of the departments and branches of the two localities reporting on the progress of project implementation, Chairman of Thai Binh Provincial People's Committee Nguyen Khac Than requested Hai Phong City People's Committee to be drastic. Direct and urge the People's Committee of Vinh Bao district to urgently complete project site clearance; Accelerate the construction progress of related items to ensure the required progress.
Vice Chairman Nguyen Duc Tho requested Vinh Bao district to focus heavily on propaganda and mobilization of households with land recovered for the project to soon hand over the site and complete it before September 15. For the construction unit, it is necessary to organize a series of construction steps to complete the bridge on December 23 and open to traffic on the 70th Anniversary of Hai Phong Liberation Day (May 13, 1955 - May 13, 2025). .
Vice Chairman of Hai Phong City People's Committee also wants Thai Binh province to urgently invest in completing the route connecting Hoa River bridge to the road from Thai Binh city to Nghin bridge to promote investment efficiency.
Hoa River Bridge is the 6th connection - the last connection between Hai Phong city and Thai Binh province.