An Phu underpass flooded many times, Ho Chi Minh City requests definitive handling

MINH QUÂN |

Ho Chi Minh City - After many times the HC1-02 underpass at An Phu intersection was flooded, the Ho Chi Minh City Department of Construction requested to clarify the cause and handle it thoroughly, not to let it happen again.

The Ho Chi Minh City Department of Construction has just sent a document to the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) - the investor of the An Phu traffic intersection construction project, requesting to handle the flooding situation at the HC1-02 underpass.

According to the Department of Construction, the flooding situation at An Phu underpass has occurred many times, greatly affecting people's travel. The Department has repeatedly requested the Traffic Board to inspect, review and handle it thoroughly.

However, on the evening of September 10, the HC1-02 underpass continued to be flooded after heavy rain and has not been thoroughly repaired to date.

The Department of Construction requests the Traffic Management Board to urgently overcome the flooding situation, ensure traffic safety, exploitation safety and prevent recurrence in the near future.

At the same time, the investor must inspect and clarify objective and subjective causes; assess the drainage capacity of the tunnel, the condition of the drainage system and related equipment.

The Department of Construction also requested to accelerate the construction progress of the remaining items of the project, strengthen inspection and supervision of construction quality, and ensure that the items are implemented in accordance with the approved design documents, technical instructions and requirements on quality and project safety.

Ôtô chết máy trong hầm chui An Phú (TPHCM) tối 10.9. Ảnh: Minh Quân
Cars stalled in An Phu underpass (HCMC) on the evening of the 10th. 9. Photo: Minh Quan

On the evening of September 10, underpass HC1-02 at An Phu intersection, Binh Trung ward, was flooded about 1m after a heavy rain. Water flooded into the tunnel, causing the project to be temporarily closed to ensure safety. Fire and rescue forces and Ho Chi Minh City Urban Drainage One Member Limited Company were mobilized to pump water out. By 1:45 pm on September 11, the water in the tunnel was pumped out and the project was treated to serve traffic.

Toàn cảnh dự án nút giao An Phú chụp đầu tháng 9.2026. Ảnh: Anh Tú
Overview of the An Phu intersection project taken in early September 2026. Photo: Anh Tu

According to the Traffic Board, the HC1-02 underpass has completed the tunnel section and was opened to traffic from February 2026. However, the entire package currently only reaches more than 90% of its value.

Because the items of the project have not been synchronously completed, the drainage system in the tunnel is still operating with temporary pumps. The capacity of this pump only meets about 70% of the designed capacity of the main pumping system.

Currently, the construction and installation of the pumping station has been about 80% completed. The Traffic Management Board requests the contractor to focus on construction, strive to complete and put the main pumping system into operation from September 22, 2026.

An Phu intersection was started at the end of 2022 with a total investment of more than 3,400 billion VND, built on a three-story scale including an underpass and an overpass system.

The project connects Mai Chi Tho, Luong Dinh Cua, Dong Van Cong routes with the Ho Chi Minh City - Long Thanh - Dau Giay expressway, and is expected to reduce traffic pressure at the eastern gateway of Ho Chi Minh City.

This is also an important traffic hub connecting the eastern area of Ho Chi Minh City with Cat Lai port, Dong Nai and Long Thanh airport.

The project has been postponed twice. Initially, the project was expected to be completed by the end of 2025, then postponed to the second quarter of 2026. Currently, the progress has continued to be adjusted to the second quarter of 2027 and is expected to be handed over in the third quarter of 2027.

MINH QUÂN
RELATED NEWS

Ho Chi Minh City raises road surface 70 - 80cm to prevent flooding of An Phu intersection underpass

|

Ho Chi Minh City - The road surface elevation in the An Phu intersection area will be raised by 70 - 80cm, creating a suitable drainage direction, limiting surface water flowing into the tunnel causing flooding.

An Phu tunnel in Ho Chi Minh City closed in both directions, mobilizing large capacity pumps to pump water

|

Ho Chi Minh City - After about 15 hours of deep flooding due to heavy rain, the An Phu intersection tunnel is still closed in both directions. Many large capacity pumps are mobilized to pump water out.

Quang Tri Department of Education and Training determines errors in the case of officials studying in 10th grade before graduating from secondary school

|

Quang Tri - Verification results show that the enrollment of 10th grade high school continuing education for Mr. Vo Danh Thuan when he had not graduated from secondary school had errors.

Trinh My Anh and the story of exchanging international crowns to find opportunities at Miss Universe Vietnam

|

Currently Miss Earth Water 2025, Trinh My Anh unexpectedly registered for Miss Universe Vietnam 2026. This decision opens up opportunities but also poses challenges for her.

Network operators turn off 2G, people can switch to popular 4G phones

|

The 2G network has officially stopped operating, people who are using feature phones need to switch to suitable devices.

Vietnamese sports delegation officially departs for ASIAD 20

|

Some teams of the Vietnamese Sports Delegation officially departed to attend ASIAD 20 in Japan.

Từ vụ ngập Hầm chui An Phú, nghĩ đến việc khai thác sân bay Long Thành

Lê Thanh Phong |

Vụ hầm chui HC1-02 tại nút giao An Phú ngập khoảng 0,5m sau cơn mưa tối 10.9, dư luận đặt vấn đề về việc khai thác sân bay Long Thành.

Ho Chi Minh City raises road surface 70 - 80cm to prevent flooding of An Phu intersection underpass

MINH QUÂN |

Ho Chi Minh City - The road surface elevation in the An Phu intersection area will be raised by 70 - 80cm, creating a suitable drainage direction, limiting surface water flowing into the tunnel causing flooding.

An Phu tunnel in Ho Chi Minh City closed in both directions, mobilizing large capacity pumps to pump water

NHƯ QUỲNH |

Ho Chi Minh City - After about 15 hours of deep flooding due to heavy rain, the An Phu intersection tunnel is still closed in both directions. Many large capacity pumps are mobilized to pump water out.