Image of the project worth nearly VND1,850 billion to replace Duong Bridge in Hanoi

CHÁNH TIẾN |

Hanoi - Some new railway and road bridge items across the Duong River, with an investment capital of nearly VND1,850 billion, are gradually emerging after more than 2 years of construction.

In July 2023, the Ministry of Transport (now the Ministry of Construction) coordinated with the Hanoi People's Committee to start the Duong River waterway upgrade project. The project includes a railway bridge and a road bridge, replacing the current Duong bridge.

The project has a total investment of VND 1,848.62 billion, of which the cost of site clearance (GPMB) for phase 1 is VND 650.8 billion from the State budget, assigned to the Railway Project Management Board (Ministry of Construction) as the investor.

Speaking to Lao Dong Newspaper reporter, Mr. Mai Xuan Tan, Director of the Duong River Waterway Upgrade Project (under the Railway Project Management Board) said that the road bridge is currently stuck with the entire site clearance on both sides of the bridge in Viet Hung ward and Phu Dong commune.

Regarding construction work, the contractor is implementing the T3 and T4 tower items under the river and waiting for the site to construct on the shore.

For the railway bridge, the contractor has completed the installation of 2 main girders and temporarily suspended construction from May to the end of October to ensure regulations on the Law on Dikes during the rainy and stormy season. Therefore, the bypass beams will be implemented from November.

Previously, in August 2025, the Ministry of Construction issued a document requesting the Hanoi People's Committee to urgently complete the site clearance for the Duong River waterway upgrade project.

According to the plan, the project's site clearance will be completed and the construction site handed over in the fourth quarter of 2024. The Railway Project Management Board (project investor) has been very proactive, actively coordinating and working with units related to local site clearance work to speed up site clearance work.

However, up to now, the project has only been handed over the site within the existing railway, public land in the existing Duong River bed area and 16/141 households in the old Long Bien District dyke safety corridor (about 0.4/4.96 ha, reaching about 8%); the remaining volume of land has not been cleared (accounting for over 92%), the relocation of technical infrastructure works has not been carried out more than 8 months behind the direction of the Hanoi People's Committee; the site has not been handed over according to the request of the Hanoi People's Committee on May 30, 2025.

The delay in handing over the site puts the project at high risk of not being completed in 2025 as planned.

Cong trinh co diem dau tai nut giao cau Duong cu tren duong Ngo Gia Tu, thuoc quan Long Bien; diem cuoi tai nut giao giua duong Ha Huy Tap voi duong Phan Dang Luu, huyen Gia Lam, cach cau Duong cu khoang 100m ve phia ha luu.
The road bridge project starts at the old Duong bridge intersection on Ngo Gia Tu street (Viet Hung ward) and ends at the intersection between Ha Huy Tap street and Phan Dang Luu street (Phu Dong commune), about 100m downstream from the old Duong bridge. Photo: Chanh Tien
Cau duong bo dai 382m, ket hop day vang, rong 18,5m, tinh khong duoi cau 4,75m. Duong dan dai 318m, van toc thiet ke 80km/h, 6 lan xe co gioi, 2 lan xe hon hop, giai doan phan ky truoc mat quy mo 4 lan xe co gioi. Anh: Chanh Tien
The road bridge is 382m long, combined with cable-stayed, 18.5m wide, with a clearance under the bridge of 4.75m. The approach road is 318m long, designed speed of 80km/h, 6 lanes for motor vehicles, 2 lanes for mixed vehicles, the first phase of the route is 4 lanes for motor vehicles. Photo: Chanh Tien
Hai tru cau T3, T4 giua long song Duong dang duoc nha thau trien khai xay dung.
Sau hon 2 nam thi cong, hai tru cau T3, T4 giua long song Duong da lo dien hinh hai. Anh: Chanh Tien
After more than 2 years of construction, the two piers of the T3 and T4 bridges in the middle of the Duong River have revealed their shape. Photo: Chanh Tien
s
Workers work at the construction site of the road bridge project across the Duong River. Photo: Chanh Tien
s
At the construction site of the road bridge across the Duong River, machinery, barges, construction materials... are gathered to serve the construction work. Photo: Chanh Tien
s
The railway bridge and approach road are 1km long according to the existing railway route, about 16.5m upstream from the old Duong bridge, coinciding with the investment location for the construction of Hanoi urban railway line No. 1. Photo: Chanh Tien
s
The railway bridge has 6 steel girder spans and a 280m long steel truss, built to ensure a railway with a gauge of 1,000mm and 1,435mm; designed speed of 80km/h. The limited clearance is divided into investment phases with a clearance of 7m, the completion phase is 9.5m. Photo: Chanh Tien
s
Construction site gathers machinery and materials for project construction. Photo: Chanh Tien
s
The contractor has completed the installation of the 2 main girders of the railway bridge. The implementation of the secondary girder spans will be implemented from November. Photo: Chanh Tien
s
A residential area in Phu Dong commune has not been cleared for handover to the construction unit. Photo: Chanh Tien
s
The existing Duong Bridge will be demolished when the new road and rail bridges are completed and put into use. Photo: Chanh Tien
CHÁNH TIẾN
RELATED NEWS

Duong Bridge behind schedule, completion date postponed to 2028

|

The road bridge project across the Duong River is expected to be completed in 2025, but due to slow implementation of the site clearance and resettlement sub-project, the project's progress will be delayed by at least 3 years.

20h News: Director of Thanh Hoa's largest wholesale market prosecuted for tax evasion

|

20h News: Director of Thanh Hoa's largest wholesale market prosecuted for tax evasion; The army discovered 14 martyrs' remains, including a relic with the name...

People accuse the electricity bill of up to 5 million VND as unreasonable, EVN explains

|

A household living in Tu Liem (Hanoi) has submitted a petition to Vietnam Electricity Group (EVN) to clearly explain the reason for the unusually high electricity bill.

Duong Bridge behind schedule, completion date postponed to 2028

Hữu Chánh |

The road bridge project across the Duong River is expected to be completed in 2025, but due to slow implementation of the site clearance and resettlement sub-project, the project's progress will be delayed by at least 3 years.

Hiện trạng nơi xây cầu vượt sông Hồng, sông Đuống trên Vành đai 4

NHÓM PV |

Có 3 cây cầu lớn trên Vành đai 4 sẽ được đầu tư xây dựng gồm Hồng Hà và Mễ Sở qua sông Hồng, cầu Hoài Thượng qua sông Đuống.

Hà Nội cải tạo Quốc lộ 1A, đoạn từ cầu Đuống mới đến Gia Lâm

KHÁNH AN |

Hà Nội cải tạo, nâng cấp Quốc lộ 1A, đoạn từ cầu Đuống mới đến hết địa phận huyện Gia Lâm nhằm đảm bảo trật tự an toàn giao thông, giảm ùn tắc.