Completed steel roof installation of Tan Son Nhat T3 terminal 2 months early

MINH QUÂN |

HCMC - The installation of the steel roof of Terminal T3 at Tan Son Nhat Airport was completed 2 months earlier than expected, helping to speed up the project's progress.

On the afternoon of September 17, Vietnam Airports Corporation (ACV) held a preliminary ceremony to summarize the 120-day emulation to complete the main steel roof structure of the passenger terminal and high-rise parking lot of the T3 Passenger Terminal project - Tan Son Nhat International Airport.

At the same time, ACV also launched a 90-day emulation movement with the goal of completing the entire roof, facade and powering the project.

Phat dong thi dua day nhanh hoan thanh nha ga T3 Tan Son Nhat.  Anh: Minh Quan
Launching a competition to speed up the completion of Tan Son Nhat T3 terminal. Photo: Minh Quan

The T3 Passenger Terminal construction project includes four main items: a passenger terminal, a multi-storey car park combined with non-aviation services, a flyover system in front of the terminal and an aircraft parking lot. With a total investment of up to VND 10,990 billion, the project is invested by ACV and is being constructed at an urgent pace.

The rough concrete part of the passenger terminal is 100% complete, while the rough construction has reached 90%. Similarly, the high-rise parking garage has also completed the rough construction and reached 85% architectural completion. The aircraft parking area alone has been completed and is in the process of acceptance before being put into operation.

Phan mai thep nha ga T3 nang 7.500 tan da duoc lap dat.  Anh: Minh Quan
The 7,500-ton steel roof of T3 terminal has been installed. Photo: Minh Quan

The highlight is the completion of the main steel roof of the terminal with 7,500 tons, 2 months ahead of schedule. The aluminum roof has a total area of ​​60,000 m², of which the first layer roof of the passenger terminal has reached 100%. Other items such as the glass curtain wall have been completed at the factory and are in the process of being transported to the construction site for installation.

For the electromechanical system, progress has reached from 70% to 95% depending on the area.

In addition, important station equipment such as elevators, escalators, bridge bridges and baggage conveyors have been brought to the construction site and are in the process of installation.

Nha ga T3 Tan Son Nhat du kien hoan thanh 30.4.2025.  Anh: Minh Quan
Tan Son Nhat Terminal T3 is expected to be completed on April 30, 2025. Photo: Minh Quan

According to Mr. Le Khac Hong - Head of the T3 Passenger Terminal Construction Project Management Board, the total project volume has reached about 70%.

To ensure the project is inaugurated on April 30, 2025, the 50th anniversary of the Liberation of the South and National Reunification, the entire project must be completed one month in advance - meaning there are only about 200 days left to complete.

Mr. Le Khac Hong added that this 90-day competition will focus all efforts on completing the entire station roof, facade glass, floor tiling, installation and connection of electromechanical equipment (UC), as well as energizing the project.

With the pressure of progress, ACV is mobilizing maximum resources, including more than 2,500 workers, engineers and hundreds of machines and equipment, to work continuously day and night 24/7.

Nha ga T3 Tan Son Nhat dang duoc day nhanh tien do. Anh: Minh Quan
Tan Son Nhat Terminal T3 is being accelerated. Photo: Minh Quan

The T3 Passenger Terminal project is scheduled to start construction at the end of 2022. When completed, this will be a domestic terminal with a capacity of serving 20 million passengers per year, serving about 7,000 passengers during peak hours, and handling all types of code C and code E aircraft.

The project will completely solve the current overload situation of Tan Son Nhat airport, contributing to improving passenger service capacity in the future.

MINH QUÂN
TIN LIÊN QUAN

Vượt khó thi công dự án nhà ga thứ 3, giảm tải cho sân bay Tân Sơn Nhất

MINH QUÂN |

TPHCM – Bất chấp gặp nhiều trở ngại như mặt bằng chật hẹp, thi công sát sân bay đang khai thác, dự án nhà ga T3 sân bay Tân Sơn Nhất vẫn được nỗ lực để thi công vượt tiến độ, đang băng băng về đích dịp 30.4.2025.

Vẻ hoành tráng của dự án ga T3 Tân Sơn Nhất đang thẳng tiến về đích

MINH QUÂN |

TPHCM - Nhà ga T3 sân bay Tân Sơn Nhất có quy mô 1 tầng hầm, 4 tầng nổi đã xây dựng xong phần thô, đang tiến hành lắp khung phần mái. Đây là ga quốc nội lớn nhất nước phục vụ 20 triệu lượt khách mỗi năm, sẽ hoàn thành đưa vào khai thác vào dịp 30.4.2025.

Dự án nhà ga gần 11.000 tỉ đồng lớn nhất sân bay Tân Sơn Nhất vượt tiến độ

MINH QUÂN |

TPHCM - Sau khoảng 1,5 năm thi công, dự án nhà ga T3 sân bay đã lộ rõ hình hài, đạt 100% khối lượng phần thô (vượt tiến độ 15 ngày). Khoảng 2.500 kỹ sư, công nhân đang gấp rút thi công trên công trường để đưa công trình vào khai thác dịp 30.4.2025, giúp giảm tải cho sân bay Tân Sơn Nhất.

Ảnh hưởng thi công âu thuyền, nhà dân bị ngập sâu trong nước

YẾN PHƯƠNG - TẠ QUANG |

Việc thi công công trình Âu thuyền Cái Khế đã khiến nhiều nhà dân tại TP Cần Thơ bị lún, nứt nghiêm trọng và ngập sâu trong nước.

Dân Hà Nội khám da liễu hàng tháng vì 6 năm không có nước sạch

KHÁNH AN |

Suốt 6 năm qua, hàng tháng, vợ chồng anh Nguyễn Đình Minh (Hoài Đức, Hà Nội) đều đưa các con đi khám da liễu vì không có nước sạch sử dụng.

6 lần thu hồi đất bất thành của chính quyền TP Thái Nguyên

Lam Thanh |

Thái Nguyên - Dù các cơ quan chức năng có hàng loạt thông báo yêu cầu di dời tài sản, bàn giao lại đất nhưng Trung tâm Nông nghiệp công nghệ cao vẫn phớt lờ.

Tăng trợ cấp thất nghiệp lên 75% giúp người lao động yên tâm

MINH HÀ - HOÀNG XUYẾN |

Tăng mức hưởng trợ cấp thất nghiệp lên 75% lương bình quân là mong mỏi của rất nhiều người lao động.

Barcelona mất người, thua trận ra quân tại Champions League

tam nguyên |

Eric Garcia sớm nhận thẻ đỏ khiến Barcelona không thể có điểm trên sân AS Monaco.

Vượt khó thi công dự án nhà ga thứ 3, giảm tải cho sân bay Tân Sơn Nhất

MINH QUÂN |

TPHCM – Bất chấp gặp nhiều trở ngại như mặt bằng chật hẹp, thi công sát sân bay đang khai thác, dự án nhà ga T3 sân bay Tân Sơn Nhất vẫn được nỗ lực để thi công vượt tiến độ, đang băng băng về đích dịp 30.4.2025.

Vẻ hoành tráng của dự án ga T3 Tân Sơn Nhất đang thẳng tiến về đích

MINH QUÂN |

TPHCM - Nhà ga T3 sân bay Tân Sơn Nhất có quy mô 1 tầng hầm, 4 tầng nổi đã xây dựng xong phần thô, đang tiến hành lắp khung phần mái. Đây là ga quốc nội lớn nhất nước phục vụ 20 triệu lượt khách mỗi năm, sẽ hoàn thành đưa vào khai thác vào dịp 30.4.2025.

Dự án nhà ga gần 11.000 tỉ đồng lớn nhất sân bay Tân Sơn Nhất vượt tiến độ

MINH QUÂN |

TPHCM - Sau khoảng 1,5 năm thi công, dự án nhà ga T3 sân bay đã lộ rõ hình hài, đạt 100% khối lượng phần thô (vượt tiến độ 15 ngày). Khoảng 2.500 kỹ sư, công nhân đang gấp rút thi công trên công trường để đưa công trình vào khai thác dịp 30.4.2025, giúp giảm tải cho sân bay Tân Sơn Nhất.