On January 10, speaking with a reporter from Lao Dong Newspaper, the leader of the Green Park Center of Thuan Hoa District (Hue City) said that the unit is implementing a project to build an outdoor stage combined with a walking path along the Huong River.
The investment objective of the project is to renovate and create a landscape to maximize the exploitation of the two banks of the Huong River for cultural tourism. The project will be a place for entertainment and to organize major events in Hue City.

According to the design, the promenade along the Huong River is 432m long and 3m wide. Main structure: Reinforced concrete retaining wall 1.7m high; reinforced concrete floor, 20cm thick, covered with 50mm thick ironwood, area 1,298m².
Semicircular stage, reinforced concrete floor structure, 20cm thick, covered with 50mm thick ironwood, area 430m².
The grandstand area will be covered with fertile soil, planted with grass and seasonal flowers, covering an area of 3,000 square meters. The seating steps will be made of monolithic stone benches 334 meters long. Lighting will include 2 floodlight columns (each column has 4 bulbs); 213 sets of LED recessed lights, and 330 sets of waterproof LED bar lights.
The project has a total budget of 28.5 billion VND from the central budget. The investor is Hue Green Park Center, the project implementation period is 2 years.