Temporary exploitation of a section of Ho Chi Minh City Ring Road 3 connecting Dong Nai from August 19

HÀ ANH CHIẾN |

Dong Nai - Component project 1A of Ho Chi Minh City Ring Road 3 is completing procedures for temporary exploitation.

On July 29, the working group of the Ministry of Construction led by Deputy Minister Bui Xuan Dung inspected the field and held a meeting to review the progress of component projects 1, 1A and 3 of the Ho Chi Minh City Ring Road 3 Project.

Reporting to the working group of the Ministry of Construction, Mr. Tran Van Thi, Director of the My Thuan Project Management Board (Ministry of Construction) said: Component project 1A is over 8km long, of which the section through Ho Chi Minh City is over 1.9km long, the section through Dong Nai province is 6.3km long.

Currently, the total construction output of package CW1 (building Nhon Trach bridge) is over 99% of the signed contract value. Meanwhile, package CW2 (entrance roads at both ends of the bridge) has more than 95% of the contract value.

Doan cong tac Bo Xay dung kiem tra tien do cac goi thau thuoc du an duong Vanh dai 3 TPHCM. Anh: HAC
The working group of the Ministry of Construction inspected the progress of the packages of the Ho Chi Minh City Ring Road 3 project. Photo: HAC

To ensure the plan to put Component Project 1A into operation from August 19, the My Thuan Project Management Board proposed that the Ministry of Construction allow the unit to organize the management of the exploitation and temporary maintenance of the project from the time of completion of construction and putting it into operation until it is officially handed over to the management unit (expected 90 days).

At the same time, the Ministry of Construction has consulted with the People's Committee of Ho Chi Minh City and the People's Committee of Dong Nai province to direct and urge investors of Component Projects 1 and 3 to speed up the progress of items connecting to Component Project 1A.

The Dong Nai Province Construction Investment Project Management Board said that currently, for Component Project 3 (section passing through Dong Nai province), construction and traffic organization on temporary roads at intersections with provincial routes 25B, 769, Ly Tu Trong Street has been implemented according to the construction design documents with a road surface width of 7-9m, road surface structure of crushed stone.

At the meeting, the leaders of the Ministry of Construction proposed that all related procedures must be completed before August 15. In particular, focusing on completing acceptance procedures, temporary maintenance plans and ensuring traffic safety during temporary operation.

HÀ ANH CHIẾN
RELATED NEWS

Tay Ninh commits to completing Ho Chi Minh City Ring Road 3 through the province on schedule

|

Tay Ninh - Up to now, the site clearance work for the Ho Chi Minh City Ring Road 3 project has reached 100% of households, completed the resettlement area and arranged plots for people.

Selecting the investment option to complete 15.3km of road coinciding with the Ho Chi Minh City Ring Road 3 project

|

HCMC - 6 overpasses or underpasses will be invested in construction at the intersection with My Phuoc Tan Van road, a 15.3km section coinciding with the Ho Chi Minh City Ring Road 3 project.

The 600 billion VND bridge over the Saigon River under the Ho Chi Minh City Ring Road 3 project

|

Binh Duong - On June 28, the Provincial People's Committee organized the closing ceremony of Binh Goi bridge across Saigon river under the Ho Chi Minh City Ring Road 3 project.

Coach Kim Sang-sik wants U23 Vietnam to improve their experience after winning the championship

|

Coach Kim Sang-sik hopes that the U23 Vietnam players will improve their experience and abilities after winning the U23 Southeast Asian Championship.

U23 Vietnam wins Southeast Asian U23 Championship for the 3rd consecutive time

|

On the evening of July 29, the U23 Vietnam team defeated U23 Indonesia 1-0 to win the 2025 U23 Southeast Asian Championship.

Upgrading the stock market, expanding capital mobilization channels for the economy

|

In order to improve quality and open up the ability to attract large-scale, stable and long-term international investment capital flows for the Vietnamese stock market, Lao Dong Newspaper in coordination with the Ministry of Finance organized a seminar on "Upgrading the stock market, expanding capital mobilization channels for the economy".

Tay Ninh commits to completing Ho Chi Minh City Ring Road 3 through the province on schedule

Duy Minh |

Tay Ninh - Up to now, the site clearance work for the Ho Chi Minh City Ring Road 3 project has reached 100% of households, completed the resettlement area and arranged plots for people.

Selecting the investment option to complete 15.3km of road coinciding with the Ho Chi Minh City Ring Road 3 project

ĐÌNH TRỌNG |

HCMC - 6 overpasses or underpasses will be invested in construction at the intersection with My Phuoc Tan Van road, a 15.3km section coinciding with the Ho Chi Minh City Ring Road 3 project.

The 600 billion VND bridge over the Saigon River under the Ho Chi Minh City Ring Road 3 project

ĐÌNH TRỌNG |

Binh Duong - On June 28, the Provincial People's Committee organized the closing ceremony of Binh Goi bridge across Saigon river under the Ho Chi Minh City Ring Road 3 project.