Binh Goi Bridge is part of the construction package of 4 Ho Chi Minh City Ring Road 3 projects through Binh Duong. This project has a total investment of nearly 600 billion VND, and construction started in October 2023.
Binh Goi Bridge is 1km long, with a scale of 4 lanes, and the speed limit is designed according to the highway standards of 100km/h.

After more than 1 year of construction, the bridge has now been officially closed. According to records, Binh Goi Bridge is one of the 4 strategic construction packages of the Ho Chi Minh City Ring Road 3 project through Binh Duong.
After the closure, the units will enter the completion stage to be able to complete the bridge by the end of 2025. This project will be the first item of the Ho Chi Minh City Ring Road 3 project through Binh Duong to be completed.
It is known that the Ho Chi Minh City Ring Road 3 project has a total length of 76.34 km, passing through 4 localities including Ho Chi Minh City, Dong Nai, Binh Duong and Long An. The total investment of this project is 75,378 billion VND, including 33,788 billion VND for construction costs and 41,590 billion VND for site clearance.
The Ho Chi Minh City Ring Road 3 passing through Binh Duong province is about 26.6 km long, with a total investment of VND 19,280 billion.
According to the Binh Duong Province Traffic Construction Investment Project Management Board, there is currently nearly 100% of the site for the entire Ho Chi Minh City Ring Road 3 project through Binh Duong.
Binh Duong province is directing contractors to speed up the construction progress, ensuring the construction progress, and putting the route into operation in 2026.