Lang Son approves nearly 200 billion VND transformer station project to supply electricity to VSIP

Khánh Linh |

Lang Son - The 110kV Huu Lung 2 power line and substation project has a total investment of more than 197 billion VND, aiming to provide stable energy sources for VSIP Industrial Park.

Lang Son Provincial People's Committee has just issued a decision approving the investment policy, and at the same time approving the investor for the 110kV Huu Lung 2 Transmission Line and Substation project.

The project is invested by Huu Lung Industrial Park Power Joint Stock Company.

The project has a total investment capital of more than 197.3 billion VND. Of which, the investor's contributed capital is more than 39.4 billion VND, and the remaining nearly 157.9 billion VND is mobilized from credit institutions.

The project is located in Huu Lung commune, using a land area of about 4.01 ha.

According to the design, the power line is about 1.8 km long, including 13 sections and 13 power poles. The substation is operated at two voltage levels of 110kV and 22kV. The substation scale includes two synchronous transformers with a capacity of 63 MVA each.

The core objective of the project is to transmit and distribute electricity, ensuring stable power supply to serve short-term and long-term production and business activities for customers at VSIP Lang Son Industrial Park.

The project has a operating term of 50 years from the date of land allocation and land lease, and the implementation progress is divided into two phases.

Phase 1 (from the second quarter of 2026 to the first quarter of 2027), the investor will start construction and build the power line and 110kV substation, pre-installing a transformer with a capacity of 63 MVA.

Phase 2 (2028), install the second transformer with a capacity of 63 MVA, increasing the total capacity of the entire station to 126 MVA.

In the approval decision, Lang Son Provincial People's Committee also requested the investor to be responsible for advanceing site clearance funds and closely coordinating with local authorities in compensation, support, and resettlement work.

At the same time, businesses must complete the margin measure to ensure the implementation of the investment project within 3 months from the date the policy is approved. If this obligation is not fulfilled, the project will be subject to termination of operation according to the provisions of law.

Khánh Linh
RELATED NEWS

Chairman of the Central Inspection Committee visits and presents gifts in Lang Son

|

Lang Son - The working delegation led by Mr. Tran Sy Thanh presented 200 gifts to policy families, poor households and workers.

VSIP Lang Son and 3 industrial clusters are required to accelerate

|

Lang Son requests to accelerate site clearance and complete procedures to accelerate 4 important industrial projects, including VSIP Lang Son Industrial Park.

Live football Song Lam Nghe An vs Hoang Anh Gia Lai at V.League

|

Live match between Song Lam Nghe An and Hoang Anh Gia Lai in round 21 of V.League 2025-2026, taking place at 6:00 p.m. today (May 3).

Many union members in Quang Ngai receive SH motorbikes and 9999 gold when playing mini games

|

Quang Ngai - 98 lucky union members received valuable prizes including Honda SH cars, 9999 gold, electric cars, refrigerators, washing machines and cash.

Chairman of the Central Inspection Committee visits and presents gifts in Lang Son

Khánh Linh |

Lang Son - The working delegation led by Mr. Tran Sy Thanh presented 200 gifts to policy families, poor households and workers.

VSIP Lang Son and 3 industrial clusters are required to accelerate

Khánh Linh |

Lang Son requests to accelerate site clearance and complete procedures to accelerate 4 important industrial projects, including VSIP Lang Son Industrial Park.

Bàn giao đất cho dự án VSIP, hộ dân ở Hữu Lũng mong mỏi chốn an cư

Khánh Linh |

Lạng Sơn - Nhường đất cho dự án, không còn nhà ở ổn định, gia đình ông Hoàng Trung Kiên phải sống nhờ trong căn nhà cấp 4 chật hẹp của bên ngoại.