Lang Son Provincial People's Committee has just issued a decision approving the investment policy, and at the same time approving the investor for the 110kV Huu Lung 2 Transmission Line and Substation project.
The project is invested by Huu Lung Industrial Park Power Joint Stock Company.
The project has a total investment capital of more than 197.3 billion VND. Of which, the investor's contributed capital is more than 39.4 billion VND, and the remaining nearly 157.9 billion VND is mobilized from credit institutions.
The project is located in Huu Lung commune, using a land area of about 4.01 ha.
According to the design, the power line is about 1.8 km long, including 13 sections and 13 power poles. The substation is operated at two voltage levels of 110kV and 22kV. The substation scale includes two synchronous transformers with a capacity of 63 MVA each.
The core objective of the project is to transmit and distribute electricity, ensuring stable power supply to serve short-term and long-term production and business activities for customers at VSIP Lang Son Industrial Park.
The project has a operating term of 50 years from the date of land allocation and land lease, and the implementation progress is divided into two phases.
Phase 1 (from the second quarter of 2026 to the first quarter of 2027), the investor will start construction and build the power line and 110kV substation, pre-installing a transformer with a capacity of 63 MVA.
Phase 2 (2028), install the second transformer with a capacity of 63 MVA, increasing the total capacity of the entire station to 126 MVA.
In the approval decision, Lang Son Provincial People's Committee also requested the investor to be responsible for advanceing site clearance funds and closely coordinating with local authorities in compensation, support, and resettlement work.
At the same time, businesses must complete the margin measure to ensure the implementation of the investment project within 3 months from the date the policy is approved. If this obligation is not fulfilled, the project will be subject to termination of operation according to the provisions of law.