VSIP Lang Son and 3 industrial clusters are required to accelerate

Khánh Linh |

Lang Son requests to accelerate site clearance and complete procedures to accelerate 4 important industrial projects, including VSIP Lang Son Industrial Park.

According to the conclusion of Standing Vice Chairman of Lang Son Provincial People's Committee Dinh Huu Hoc after a recent inspection, 4 projects in the old Huu Lung district were requested to accelerate, including: VSIP Lang Son Industrial Park, Ho Son 1 Industrial Cluster, Hoa Son 1 and Minh Son.

Although basically assessed as sticking to the plan, some items have changed, the overall progress of these projects is still slow due to site clearance, investment procedures and unsynchronized technical infrastructure.

For Hoa Son 1 Industrial Cluster, Lang Son requests Tan Thanh Commune People's Committee to coordinate with the Provincial Land Fund Development Center to complete mobilization and dialogue to clear the remaining 2.3 hectares before April 30; in case conditions are met but people do not comply, coercion will be organized according to regulations. The area of about 16.3 hectares that has been cleared must be handed over to the investor in April.

The investor sends a detailed construction plan before April 15, prioritizing completing the wastewater treatment plant to put it into operation in the fourth quarter of 2026.

At Ho Son 1 Industrial Cluster, Huu Lung Commune People's Committee must mobilize the relocation of the remaining grave before April 19, and at the same time develop a plan to relocate a affected household, reporting to the Provincial People's Committee before April 15.

The investor must complete synchronous technical infrastructure, especially the wastewater treatment system before June 30, complete procedures for secondary investors and hand over production land in the second quarter.

For VSIP Lang Son Industrial Park, the People's Committees of Huu Lung, Tuan Son communes and the Provincial Land Fund Development Center are assigned to urgently complete site clearance phase 1 in the direction of liền khoảnh, liền thửa; the relocation of the remaining graves must be completed before April 19.

Site clearance and resettlement support in phase 2 continue to be accelerated, cases of intentional non-compliance will have their dossiers consolidated for enforcement. VSIP Lang Son Co., Ltd. must accelerate infrastructure construction inside and outside the fence, striving to complete phase 1 technical infrastructure in the second quarter to be ready to attract secondary investors.

The Department of Construction is assigned to handle recommendations related to the interspersed land area between the expressway intersection project into Huu Lung Industrial Park and VSIP Lang Son Industrial Park, and report to the Provincial People's Committee before April 15.

The Provincial Land Fund Development Center must complete compensation for technical infrastructure works such as power lines, information lines, and BTS stations in the second quarter to hand over clean land.

For Minh Son Industrial Cluster, the investor must complete the cadastral measurement dossier and hand it over to the Provincial Land Fund Development Center before April 15 to serve site clearance.

Procedures such as bomb and mine clearance, environmental impact assessment, feasibility study report, land use purpose conversion, and fire prevention and fighting must be completed in June.

Tuan Son Commune People's Committee is assigned to approve the 1/500 detailed plan before April 30, and at the same time develop a land clearance plan, review resettlement needs and mobilize people to relocate graves before April 19.

Khánh Linh
RELATED NEWS

Lang Son establishes working group to remove obstacles for Mau Son cable car project 7. 352 billion VND

|

Lang Son - The Provincial People's Committee established an inter-sectoral working group to remove obstacles and promote the progress of the Mau Son eco-tourism and cable car complex project.

Lang Son adds 7 waste dumping yards to serve the Dong Dang - Tra Linh expressway

|

Lang Son - 7 surplus soil and rock dumping yards serving the construction of the Dong Dang - Tra Linh expressway have just been added.

Stop climbing activities in Lao Cai due to extremely dangerous forest fire risk

|

Lao Cai - Bat Xat Nature Reserve Management Board warns that forest fires are extremely dangerous, absolutely prohibiting entry into the forest, mountain climbing, and sightseeing.

Passenger car carrying 12 people overturned on Noi Bai - Lao Cai expressway at dawn

|

Lao Cai - A passenger car carrying 12 people overturned on the Noi Bai - Lao Cai expressway, blocking the lane, causing traffic congestion.

Standing Committee of the Central Committee of the Vietnam Fatherland Front

|

Based on the number and composition of the Standing Committee of the Central Committee of the Vietnam Fatherland Front (VFF) approved by the 10th National Congress of the VFF and the organization of the apparatus of the VFF Committee according to the new model. On April 12, 2026, the Conference of the VFF Central Committee consulted and elected personnel to participate in the Committee, Presidium and hold the position of Vice Chairman of the VFF Central Committee of the 10th term, term 2024 - 2029.

World Cup 2026 copyright and experiences for Vietnamese audiences

|

Besides professional factors, the 2026 World Cup is expected to increase the experience for viewers through backstage and sideline entertainment programs.

Mr. Trump declares 10th achievement: Israel - Lebanon ceasefire agreement

|

Mr. Trump suddenly announced the reaching of a 10-day ceasefire agreement between Israel and Lebanon after negotiations in Washington on April 16.

Nuclear fighter jets to arrive in Finland, Russia reacts strongly

|

Russia warns that the first batch of F-35A fighters, a type of aircraft capable of carrying nuclear weapons, will be handed over to Finland this year.

Lang Son establishes working group to remove obstacles for Mau Son cable car project 7. 352 billion VND

Khánh Linh |

Lang Son - The Provincial People's Committee established an inter-sectoral working group to remove obstacles and promote the progress of the Mau Son eco-tourism and cable car complex project.

Lang Son adds 7 waste dumping yards to serve the Dong Dang - Tra Linh expressway

Khánh Linh |

Lang Son - 7 surplus soil and rock dumping yards serving the construction of the Dong Dang - Tra Linh expressway have just been added.

Bàn giao đất cho dự án VSIP, hộ dân ở Hữu Lũng mong mỏi chốn an cư

Khánh Linh |

Lạng Sơn - Nhường đất cho dự án, không còn nhà ở ổn định, gia đình ông Hoàng Trung Kiên phải sống nhờ trong căn nhà cấp 4 chật hẹp của bên ngoại.