Installing ceiling for Long Thanh airport passenger terminal worth 35,000 billion VND

HÀ ANH CHIẾN |

Dong Nai - At the Long Thanh airport construction site, personnel and machinery are focused on installing and completing the passenger terminal ceiling system.

On June 27, according to information from Vietnam Airports Corporation (ACV), at the Long Thanh airport project site, ACV and the Project Management Board and construction units are focusing manpower, machinery and equipment, urgently deploying installation and completing the ceiling system in many areas of the terminal.

According to ACV, the construction work is carried out strictly and synchronously with electromechanical and architectural items, ensuring technical requirements, quality, and labor safety. Each stage is carefully controlled, ensuring accuracy, aesthetics and the set schedule, gradually shaping the modern and synchronous architectural space of Long Thanh airport passenger terminal.

According to ACV, package 5.10 construction of Long Thanh airport passenger terminal will be technically operational in September 2026.

This is a bidding package belonging to Component Project 3 - Long Thanh Airport Project phase 1.

The entire component project 3 of Long Thanh airport has 15 main construction packages (currently 3 packages have been completed and 12 packages are under construction).

In which, package 5.10, construction and installation of passenger terminal equipment, the project is likened to the "heart" of Long Thanh airport, and this package is also the deciding link for the progress of the entire project.

The bidding package is constructed by Vietur consortium, started in July 2023, with a contract value of more than 35,000 billion VND.

Up to now, the contractor consortium has mobilized thousands of personnel, machinery and equipment to deploy construction, basically completing the reinforced concrete structure, steel roof structure, and glass wall elevation.

According to ACV, contractors are simultaneously accelerating, organizing "3 shifts, 4 crews" day and night, and at the same time responding to the emulation period "180 days and nights to accelerate the completion of the Long Thanh International Airport Project". After nearly 3 weeks of campaign implementation, component project 3 has a total production value of about 65,602 billion VND, equivalent to 75.97% of the total value of signed contracts.

Regarding construction resources, the construction site currently maintains an average of more than 7,300 direct workers, an increase of about 4.54% compared to the beginning of the campaign.

Previously, on June 13, Minister of Construction Tran Hong Minh and the working delegation inspected the actual progress of the Long Thanh airport project and requested the parties to review the entire construction volume, settlement documents, and at the same time pay attention to caring for and encouraging the team of engineers and workers who are sticking to the construction site day and night.

According to the schedule, the Long Thanh airport project will be put into operation by the end of 2026.

Images of the construction of the ceiling system of Long Thanh airport passenger terminal:

Nhà ga hành khách sân bay Long Thành được thiết kế theo tiêu chuẩn 5 sao quốc tế, lấy cảm hứng từ hình ảnh hoa sen với hệ mái kính skylight ở mái trung tâm của nhà ga giúp lấy ánh sáng tự nhiên, tạo điểm nhấn về kiến trúc và mỹ thuật. Ảnh: HAC
Long Thanh International Airport passenger terminal (Long Thanh airport) is designed according to international 5-star standards, inspired by the image of lotus flowers with a skylight glass roof system on the central roof of the terminal to help bring natural light, creating architectural and artistic highlights. Photo: HAC
Tại các tầng của nhà ga hành khách sân bay Long Thành, công tác thi công phần trần áp mái cũng đang được triển khai đồng bộ. Ảnh: HAC
In addition to the skylight glass roof system on the central roof of the terminal, on the floors of the Long Thanh airport passenger terminal, the construction of the roof ceiling is also being implemented synchronously. Photo: HAC
Trong đó, Người lao động thi công luôn phải đảm bảo các yêu cầu về an toàn lao động. Ảnh: HAC
A construction area of the terminal ceiling is gradually being completed. Photo: HAC
Trong đó, người lao động thi công luôn phải đảm bảo các yêu cầu về an toàn lao động. Ảnh: HAC
In which, construction workers must always ensure occupational safety requirements. Photo: HAC
Một khu vực trần nhà ga sân bay Long Thành. Ảnh: HAC
A ceiling area of Long Thanh airport terminal. Photo: HAC
Hiện liên danh nhà thầu đang tiếp tục thi công hoàn thiện trần áp mái dưới lớp mái Skylight ở mái trung tâm nhà ga hành khách sân bay. Ảnh: HAC
Officials, engineers, and workers are urgently mobilized to construct the project. Photo: HAC
Cán bộ, kỹ sư, người lao động được huy động khẩn trương thi công dự án. Ảnh: HAC
Currently, the contractor consortium is continuing to complete the ceiling ceiling under the Skylight roof in the center of Long Thanh airport passenger terminal. Photo: HAC
Nhà ga hành khách sân bay Long Thành nhìn từ bên ngoài. Ảnh: HAC
Long Thanh airport passenger terminal seen from the outside. Photo: HAC
Theo kế hoạch dự án sân bay Long Thành đưa vào khai thác thương mại vào cuối năm 2026. Ảnh: HAC
According to the plan, the Long Thanh airport project will be put into commercial operation at the end of 2026. Photo: HAC

The Long Thanh International Airport project was approved for investment policy by the National Assembly in Resolution No. 94/2015/QH13 dated June 25, 2015, with the goal of building a modern international airport, playing an important aviation gateway for Vietnam and gradually becoming an aviation transshipment hub of the region. According to the plan, the project will reach level 4F according to the standards of the International Civil Aviation Organization (ICAO), with a capacity of 100 million passengers and 5 million tons of cargo per year when fully completed, and will be implemented in 3 investment phases.

The Long Thanh International Airport phase 1 project is adjusted in the direction of synchronous completion with a scale including 2 runways, 1 passenger terminal and related auxiliary works; the goal is to be completed by the end of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Long Thanh airport passenger terminal technical operation in September

|

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Close-up of the "heart" construction site of Long Thanh airport passenger terminal

|

Dong Nai - Long Thanh Airport aims to put into commercial operation in the fourth quarter of 2026.

Da Nang expands T2 international terminal, preventing passenger overload

|

Da Nang - The project to expand international terminal T2 at Da Nang airport with a total investment of nearly 1,500 billion VND has just officially started construction.

Commencement of expansion of Da Nang International Terminal, increasing capacity to 6 million passengers/year

|

Da Nang - Groundbreaking ceremony for the project to expand International Passenger Terminal T2, expected to increase operating capacity to 6 million passengers/year.

Removing the computer-simulated traffic situation test from July 1, 2026

|

The Circular Regulating the testing and issuance of driver's licenses; issuance and use of international driver's licenses stipulates the removal of the traffic situation simulation test.

Warning for thunderstorm areas today, with heavy rain over 60mm in some places

|

The meteorological agency warns that the concentrated rain and thunderstorms in the mountainous and midland areas of the Northern region are morning, evening and night.

Truck plunges into abyss in Son La, killing 2 people, 1 injured

|

Son La - 2 people died, 1 person was injured after a truck plunged into a ravine.

Red River bank becomes a dormitory area, Long Bien ward promises to handle it for 3 months and it remains the same

|

Along the Red River alluvial ground area in Long Bien ward, dozens of hectares of alluvial ground are being turned into a playground, accommodation and food service business area.

Long Thanh airport passenger terminal technical operation in September

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport passenger terminal will be technically operational in September 2026, moving towards commercial operation at the end of the year.

Close-up of the "heart" construction site of Long Thanh airport passenger terminal

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport aims to put into commercial operation in the fourth quarter of 2026.

Da Nang expands T2 international terminal, preventing passenger overload

Nguyễn Linh - Trần Thi |

Da Nang - The project to expand international terminal T2 at Da Nang airport with a total investment of nearly 1,500 billion VND has just officially started construction.

Commencement of expansion of Da Nang International Terminal, increasing capacity to 6 million passengers/year

Trần Thi |

Da Nang - Groundbreaking ceremony for the project to expand International Passenger Terminal T2, expected to increase operating capacity to 6 million passengers/year.