Close-up of the "heart" construction site of Long Thanh airport passenger terminal

HÀ ANH CHIẾN |

Dong Nai - Long Thanh Airport aims to put into commercial operation in the fourth quarter of 2026.

According to Vietnam Airports Corporation (ACV), the entire component project 3 of Long Thanh airport has 15 main construction packages (currently 3 packages have been completed and 12 packages are under construction).

In which, package 5.10, construction and installation of passenger terminal equipment, the project is likened to the "heart" of Long Thanh airport, and at the same time this package is also the deciding link for the progress of the entire project.

Thi công bên trong nhà ga hành khách sân bay Long Thành. Ảnh: HAC
Construction inside Long Thanh airport passenger terminal. Photo: HAC

Package 5. 10 construction and installation of equipment for the Long Thanh airport passenger terminal project is constructed by Vietur consortium, started in July 2023.

Up to now, the contractor consortium has mobilized thousands of personnel, machinery and equipment to deploy construction, basically completing the reinforced concrete structure, steel roof structure, and glass wall elevation.

The construction of plastering, waterproofing, foundation rolling, floor surface finishing, water-painting tile tiles are expected to be completed in May 2026; stone and plaster wall finishing work is completed in July 2026; ceiling, roof, glass wall, and exterior stone finishing work are expected to be completed in June 2026.

The work of the station roof and Skylight lighting roof was basically completed in March.

Electricity, water, and air conditioning systems are deployed on the floors according to a rolling plan, meeting the progress.

Regarding equipment installation, the station is deploying the installation of luggage processing system (BHS), security scanning equipment (SSE), passenger bridge system (PBB), aircraft landing system (VDGS), escalator system, staircase (ES/MW), and elevator system (EL).

According to ACV, the component project 3 of Long Thanh airport to date assesses overall progress, completing the technical operation target in September 2026 and organizing commercial operation in the fourth quarter of 2026 is feasible.

Images recorded by reporters of urgent construction inside the passenger terminal of Long Thanh airport:

Nhà ga hành khách sân bay Long Thành được thiết kế theo tiêu chuẩn 5 sao quốc tế, lấy cảm hứng từ hình ảnh hoa sen với hệ mái kính skylight ở mái trung tâm của nhà ga giúp lấy ánh sáng tự nhiên, tạo điểm nhấn về kiến trúc và mỹ thuật. Ảnh: HAC
Long Thanh airport passenger terminal is designed according to international 5-star standards, inspired by the image of lotus flowers with a skylight glass roof system on the central roof of the terminal to capture natural light, creating architectural and artistic highlights. Photo: HAC
Tại các tầng của nhà ga hành khách sân bay Long Thành, công tác thi công phần trần áp mái cũng đang được triển khai đồng bộ. Ảnh: HAC
On the floors of the Long Thanh airport passenger terminal, the construction of the roof ceiling is also being deployed synchronously. Photo: HAC
Người lao động thi công luôn phải đảm bảo các yêu cầu về an toàn lao động. Ảnh: HAC
Construction workers must always ensure occupational safety requirements. Photo: HAC
Liên danh nhà thầu đang tiếp tục thi công hoàn thiện trần áp mái dưới lớp mái Skylight ở mái trung tâm nhà ga hành khách sân bay. Ảnh: HAC
The contractor consortium is continuing to complete the ceiling ceiling under the Skylight roof in the central roof of the airport passenger terminal. Photo: HAC
Hàng ngàn cán bộ, kỹ sư, người lao động được huy động thi công dự án. Ảnh: HAC
Officials, engineers, and workers are mobilized to construct the project. Photo: HAC
Một khu vực nhà ga hành khách sân bay Long Thành đang được hoàn thiện. Ảnh: HAC
A passenger terminal area of Long Thanh airport is being completed. Photo: HAC
Công nhân lao động thi công gấp rút. Ảnh: HAC
Workers are working urgently. Photo: HAC
Người lao động thi công hoàn thiện các chi tiết phần mái nhà ga trước khi được lắp đặt. Ảnh: HAC
Số lượng nhân lực thi công công trình nhà ga hành khách chưa đáp ứng so với nhu cầu khiến công tác thi công gặp khó khăn. Ảnh: HAC
Workers complete the details of the terminal roof before being installed. Photo: HAC
Theo ACV, dự án sân bay Long Thành đưa vào khai thác vào quý IV/2026 là khả thi. Ảnh: HAC
According to ACV, the Long Thanh airport project put into operation in the fourth quarter of 2026 is feasible. Photo: HAC
HÀ ANH CHIẾN
RELATED NEWS

Leasing more than 1,900ha of land in 2 industrial parks near Long Thanh airport

|

Dong Nai - Bau Can - Tan Hiep Industrial Park and Xuan Que - Song Nhan Industrial Park have prime locations near Long Thanh airport.

Close-up of 6 aircraft fuel tanks of 6,000 m3/tank at Long Thanh airport

|

Dong Nai - Each floating tank of the fuel supply system at Long Thanh airport has a capacity of 6,000 m3.

National Assembly Vice Chairman Nguyen Hong Dien inspects Long Thanh airport project

|

Dong Nai - National Assembly Vice Chairman Nguyen Hong Dien and the working delegation inspected the progress of the Long Thanh airport project and connecting traffic routes.

Many projects connecting Long Thanh airport are completed and started in June

|

Long Thanh airport is expected to be put into commercial operation in the fourth quarter of 2026, Dong Nai city is accelerating the progress of completing and starting new connecting transportation projects.

Hanoi requests to abolish the decision to revoke the red book of the old Soc Son district

|

Hanoi - The red book of Soc Son District People's Committee was previously issued to people in hamlet 20 Xuan Bang, Nam Son commune (old), but was later revoked because it was issued in violation of regulations.

VN-Index gradually moves away from the 1,900 point mark

|

The "suffering" of the pillar stock group is the reason why VN-Index lost points sharply in the last 2 sessions.

People complain about being delayed from leaving the country because the amount of tax debt is very small, the Tax Department speaks out

|

In case of small tax debts but temporary exit suspension due to taxpayers abandoning business addresses, tax debts from 2023 and have been notified and enforced in accordance with regulations.

More than 1 million views after 1 hour of posting, the clip made by Hanoi Traffic Police received a "storm" of praise

|

Hanoi - A propaganda clip about alcohol concentration violations made by the Hanoi Traffic Police Department is spreading "widely" on social networks.

Leasing more than 1,900ha of land in 2 industrial parks near Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Bau Can - Tan Hiep Industrial Park and Xuan Que - Song Nhan Industrial Park have prime locations near Long Thanh airport.

Close-up of 6 aircraft fuel tanks of 6,000 m3/tank at Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Each floating tank of the fuel supply system at Long Thanh airport has a capacity of 6,000 m3.

National Assembly Vice Chairman Nguyen Hong Dien inspects Long Thanh airport project

HÀ ANH CHIẾN |

Dong Nai - National Assembly Vice Chairman Nguyen Hong Dien and the working delegation inspected the progress of the Long Thanh airport project and connecting traffic routes.

Many projects connecting Long Thanh airport are completed and started in June

HÀ ANH CHIẾN |

Long Thanh airport is expected to be put into commercial operation in the fourth quarter of 2026, Dong Nai city is accelerating the progress of completing and starting new connecting transportation projects.