A series of traffic black spots on National Highway 3 are gradually being eliminated

Nguyễn Hoàn |

After more than 1 year of implementation, many traffic black spots on National Highway 3 through Bac Kan province have been eliminated, helping to ensure safety for people and vehicles.

The project to repair the roadbed and surface and handle traffic safety (TS) points on National Highway 3 (QL3) through Bac Kan province is invested by the Department of Transport of Bac Kan province.

This is a group C project with a total investment of over 50 billion VND, starting construction at the end of 2023, with an implementation period of 2 years.

The project's goal is to upgrade infrastructure and eliminate a series of traffic black spots concentrated at the sections Km 129 + 428.7 - Km 131 + 171.9; Km 131 + 900 - Km 133 + 881.2; Km 135 + 723.2 - Km 140 + 500... to help ensure safety for people and vehicles.

On January 12, after more than a year of implementation, many traffic black spots on the above sections have been repaired and renovated. Roads have been widened, guardrails and warning signs have been installed.

Toan canh tuyen duong QL.3 doan qua dia phan tinh Bac Kan sau 1 nam trien khai sua chua, nang cap va xu ly cac diem gay mat ATGT. Anh: Nguyen Hoan.
Overview of National Highway 3 through Bac Kan province after 1 year of repairing, upgrading and handling traffic safety issues. Photo: Nguyen Hoan.

At the construction site at the hard bridge in Cao Ky commune (Cho Moi), the construction unit urgently reinforced, repaired, spread stones, and built access roads.

In some other areas, workers are marking roads, constructing drainage ditches and some other ancillary items.

Mr. Nguyen Van Sang, a worker at the construction site, said that the section from Dong Tam town to Cao Ky commune has now been basically completed. Many narrow corners have been widened and the road surface has been paved with asphalt.

"We are marking the road and constructing the drainage system. The weather is dry at the end of the year so the work is going relatively smoothly," said Mr. Sang.

As a driver on the Bac Kan - Thai Nguyen route, Mr. Ha Trong Dong (Thai Nguyen City) shared that before the project was implemented, the roadway on National Highway 3 was quite narrow, with many sharp turns, causing the fear of collisions and accidents to always be present.

"In the past, every time I traveled on this section of Highway 3, even though I had been traveling for many years, I still couldn't help but feel worried. Especially when coming to a corner, the road is quite narrow, collisions here are not uncommon.

Now the road has been repaired, upgraded and expanded, making travel easier. We feel much more secure when passing through here than before," Mr. Dong added.

Speaking to reporters, Mr. Leng Van Chien - Director of the Department of Transport of Bac Kan province said that up to now, the project to upgrade and repair National Highway 3 through the province has been basically completed, reaching over 80% of the workload.

"The road surface of the entire project will be completed before Tet. As for the hard bridge and other items, it is planned to be completed by mid-2025.

When the project is completed, it will help develop traffic infrastructure, eliminate a series of traffic safety hazards, and help ensure safety for people and vehicles," said the Department of Information leader.

Some recorded images:

1
A series of traffic black spots on National Highway 3 through Bac Kan province have been eliminated.
2
Most of the route is upgraded and paved.
3
Roads, sharp turns, and blind spots are now widened to help avoid collision risks and make travel easier.
4
The railing is installed by the contractor to ensure safety for people and vehicles.

Statistics from 2019 - 2022, on National Highway 3 through Bac Kan province, there were 100 collisions and traffic accidents, killing 13 people, injuring 63 people, and damaging dozens of vehicles.

Nguyễn Hoàn
TIN LIÊN QUAN

Exemption from second-round fees for candidates who have lost their BDNL test time

|

Candidates who have wasted time taking the first round of the Ho Chi Minh City National University's competency assessment test will be exempted from exam fees in the second round.

Sudden checking around school gates in Hanoi

|

Hanoi - The city will conduct a surprise inspection of food safety control work in and around school gates.

Phu Yen receives the First Class Labor Medal

|

Phu Yen - On the evening of April 1, at April 1 Square (Tuy Hoa City), Phu Yen province solemnly held a ceremony to celebrate the 50th anniversary of the Provincial Liberation Day (April 1, 1975 - April 1, 2025).

10 workers of Nghe An Fishing Inspectorate hope to have their rights guaranteed

|

Nghe An - 10 workers working on the province's fishing vessels are currently only allowed to sign contracts each year, and have not signed long-term labor contracts.

Vietnamese architects admire the colors of Lao culture

|

Mr. Nguyen Hong Nhat (35 years old, architect in Hanoi) and his family had memorable experiences when traveling to Laos for 6 days.

Assigning Hanoi to build a roadmap to collect fees for cars entering the inner city

|

The Deputy Prime Minister requested Hanoi to develop a roadmap to gradually reduce motorbikes in the inner city, collecting fees for cars entering the central area during rush hour.

The maximum average retail price of electricity is VND 2,444.09/kWh

|

According to the new regulations, the minimum average retail price for electricity is VND 1,826.22/kWh; the maximum average retail price for electricity is VND 2,444.09/kWh.

Pay attention to training cadres, meeting the requirements of restructuring the apparatus

|

In the coming time, it is necessary to pay attention to training and fostering cadres, meeting the requirements of restructuring the apparatus...

Người dân mong sớm xử lý điểm đen giao thông trên Quốc lộ 70

Đinh Đại |

Yên Bái - Nhiều năm qua, người dân sinh sống trên Quốc lộ 70, đoạn qua xã Tân Hương, huyện Yên Bình luôn lo sợ mỗi khi tham gia giao thông trên tuyến đường chực chờ nguy cơ xảy ra tai nạn.

Điểm đen giao thông chờ được loại bỏ trên Quốc lộ 2

Lam Thanh |

Tuyên Quang - Những khúc cua gấp, khuất tầm nhìn trên tuyến QL2 đoạn qua xã Tứ Quận (Yên Sơn) là nỗi ám ảnh đối với các tài xế vì thường trực nguy cơ tai nạn giao thông.

Cần xóa bỏ điểm đen giao thông tại đường tròn TP Thái Nguyên

Minh Hạnh |

Thái Nguyên - Theo phản ánh của người dân, khu vực đường tròn của tuyến đường Bắc Sơn kéo dài thuộc địa phận xã Quyết Thắng và xã Thịnh Đán (TP Thái Nguyên), do thi công kéo dài nhiều năm chưa xong nhưng có nhiều xe tải lớn đi qua, đã thường xuyên xảy ra tai nạn giao thông, gây bất an cho người dân.