The reason why the 400 billion VND square project in Dak Nong is slow to reach the finish line

THANH QUỲNH |

Dak Nong - The Gia Nghia City Central Square project has been delayed for a long time and has yet to set a completion date due to many problems.

On November 2, the Gia Nghia City Central Square project (Dak Nong) had not yet completed many investment items.

This project has a total investment of 400 billion VND, including items such as: Exhibition center, bridge over the lower lake, leveling, landscape axis combined with flower garden, water music system, installation of power supply system, lighting, trees, flagpole...

This is a key project of Dak Nong province towards the 20th anniversary of the province's re-establishment (January 1, 2024). The project is located in Nghia Duc ward (Gia Nghia city), with a total area of ​​18.58 hectares and 210 households affected. The project started construction at the end of 2022 and is expected to be completed by the end of 2023. However, the project is behind schedule due to 2 major problems that have not yet been resolved.

That is, the project is lacking about 210,000m3 of fill soil and 7.18ha of land has not been cleared.

Mr. Nguyen Van Nghia - Director of Dak Nong Province Construction Investment Project Management Board (project investor) - said that the unit is urgently removing obstacles.

Regarding the fill soil, the unit is coordinating with the construction contractor to complete the environmental impact assessment procedures and prepare the dossier for mining the soil at Dak Nut B hill. The parties are trying to complete the procedures by the end of 2024 to have fill soil for the project.

Regarding site clearance, the investor has worked with the Gia Nghia City People's Committee to speed up the progress of declaration and inventory of the remaining site clearance. The goal is for the construction unit to complete the project in 2025.

THANH QUỲNH
RELATED NEWS

What happened to the billion-dollar road project with a fraudulent contractor?

|

Hoa Binh - The People's Committee of Luong Son district has just decided to ban Nguyen Ha Company Limited from participating in bidding activities for 3 years because of fraudulent behavior in bidding.

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

|

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.

Earthquake of magnitude 4.0 occurred in Son La

|

Son La - An earthquake with a magnitude of 4.0 occurred in the Muong Hung commune area.

Live football U17 Vietnam vs U17 Korea at the Asian tournament

|

Live match between U17 Vietnam and U17 Korea at the 2026 AFC U17 Championship, taking place at 11:00 PM on May 10.

Yen So pumping station is ready to operate at maximum capacity in the 2026 rainy season

|

Yen So Headworks Complex Management Enterprise proactively deploys plans to respond to heavy rain, ensuring safe drainage for the southern area of the Capital.

What happened to the billion-dollar road project with a fraudulent contractor?

Đặng Tình |

Hoa Binh - The People's Committee of Luong Son district has just decided to ban Nguyen Ha Company Limited from participating in bidding activities for 3 years because of fraudulent behavior in bidding.

Tide prevention project behind schedule, burdened with 2,500 billion VND in loan interest

MINH QUÂN |

HCMC - The flood prevention project with a total capital of nearly 10,000 billion VND after 6 years of delay has incurred interest of about 2,500 billion VND, an average of 1.73 billion VND per day.

Chặng nước rút trên dự án Quảng trường trung tâm ở Đắk Nông

Phan Tuấn |

Cuối năm 2022, dự án Quảng trường trung tâm thành phố Gia Nghĩa (Đắk Nông) chính thức khởi công với tổng mức đầu tư 400 tỉ đồng. Đây là công trình trọng điểm nhằm phục vụ sự kiện chào mừng Kỷ niệm 20 năm tái lập tỉnh.