Reasons why Vinh Phuc is slow to disburse public investment capital

Bảo Nguyên |

By September, the disbursement of public investment capital in Vinh Phuc had only reached more than 3,998 billion VND, equal to 51.4% of the capital plan assigned by the Central Government.

In 2024, Vinh Phuc province was assigned more than 7,895 billion VND of public investment capital, including more than 7,776 billion VND of state budget capital assigned by the Central Government; additional provincial budget capital assigned nearly 120 billion VND.

Based on the allocated capital, the provincial level has allocated more than 4,460 billion VND in detail; the district and commune levels have allocated more than 3,430 billion VND in detail.

The disbursement results of public investment capital in Vinh Phuc as of mid-September 2024 reached more than VND 3,998 billion, equal to 51.4% of the capital plan assigned by the Central Government and equal to 48.4% of the total planned capital (including the extended planned capital for 2023).

Of which, the provincial disbursement rate reached 32.5%; the disbursement rate of districts and cities reached 70.8%.

Du an cau vuot duong sat tren duong Nguyen Tat Thanh su dung von dau tu cong dang duoc day nhanh tien do. Anh: UBND tinh Vinh Phuc
The railway overpass project on Nguyen Tat Thanh Street using public investment capital is being accelerated. Photo: Vinh Phuc Provincial People's Committee

At the conference to review the progress of public investment disbursement in the first 9 months of 2024 and the directions and tasks for the last months of the year, organized by the People's Committee of Vinh Phuc province on September 27, delegates frankly reviewed and analyzed and evaluated the reasons for the low disbursement rate of public investment capital.

The reason is that in the first months of the year, contractors focused on paying the 2023 public investment capital plan; compensation and site clearance for projects still faced many difficulties due to delayed and prolonged procedures for converting the purpose of using rice fields and forest land.

In addition, some projects that do not have names or do not meet land use criteria in the approved planning list must carry out procedures to update and supplement the Land Use Planning for the period 2021 - 2030 of the district level.

In addition, additional capital from the local budget for public investment expenditure in 2024 has not been allocated yet, leading to many projects not being allocated capital for implementation; many projects are scarce in terms of earth filling materials...

In order to disburse public investment capital in 2024 to reach the target of more than 95%, Chairman of Vinh Phuc Provincial People's Committee Tran Duy Dong requested all levels, sectors, localities, and project management boards to strengthen discipline, order, and strictly comply with regulations in public investment management, bidding, construction, and capital settlement.

In addition, strengthen management and effective use of public investment capital; strictly implement the provisions of the Law on Bidding, strengthen supervision and inspection of contractors in project construction.

Bảo Nguyên
RELATED NEWS

U17 Vietnam beat U17 Singapore in the U17 Asian qualifiers

|

U17 Vietnam won 6-0 against U17 Singapore in the opening match of the 2026 U17 Asian qualifiers.

National Highways 1A and 29 in Dak Lak have been opened to traffic but essential goods are still locally scarce

|

Dak Lak - National Highways 1A and 29 have been opened to traffic to serve the transportation needs of the people. However, some essential goods are still locally scarce.

High tide continues to rise in Ho Chi Minh City, many people have to stay vigil and prevent water

|

HCMC - On the evening of November 22, the high tide rose, many households had to stay up watching over the planks and sandbags to prevent water from flooding into their homes.

Deputy security team in Gia Lai rushed into the fierce flood, saving people struggling

|

Gia Lai - Deputy Head of the Security and Order Team of Duong Thien village Nguyen Tan Diep promptly rushed out into the flood, saving the lives of people about to drown in the rushing water.

Baby born safely at flood shelter in Nha Trang

|

Khanh Hoa - The medical team of the Provincial General Hospital has just successfully given birth to a pregnant woman at a temporary hotel in Nha Trang ward.

The body of a tractor-trailer driver suspected of being swept away was found more than 30km away

|

Quang Tri - A body was discovered by a local volunteer team on the river, suspected to be a tractor-trailer driver swept away by floodwaters.

Cracked hill threatens houses and schools in A Vuong commune, Da Nang

|

Da Nang - Cracked soil, subsided 5m deep, A Vuong commune urgently evacuated dozens of households at night.

Sạt lở ở dự án chống ngập nghìn tỉ tại Vĩnh Phúc

Thanh Bình - An Vi |

Dự án Quản lý nguồn nước và ngập lụt Vĩnh Phúc với tổng vốn đầu tư nghìn tỉ dù mới hoàn thành và đang vận hành thử nghiệm nhưng đã xuất hiện sạt lở, nứt vỡ.

Lo River bank landslide, Vinh Phuc declares emergency situation

An Vi |

According to the People's Committee of Vinh Phuc province, the serious landslide on the bank of Lo River directly threatens the safety of more than 164,000 people.

Vĩnh Phúc công khai 106 người nợ thuế hơn 560 tỉ đồng

Bảo Nguyên |

Cục Thuế tỉnh Vĩnh Phúc thực hiện công khai thông tin 106 người nợ thuế và các khoản thu khác thuộc ngân sách nhà nước với số tiền hơn 560 tỉ đồng.