Nhon - Hanoi Railway Station Metro expected to complete tunnel digging in 2025

Tô Thế |

Up to now, both TBM tunnel boring machines of the Nhon - Hanoi station metro project have officially operated on the underground section.

On February 3 (the 6th day of the Lunar New Year), the Hanoi Urban Railway Management Board (MRB), together with the consulting unit and contractor, started drilling the tunnel using the second TBM (Tunnel Boring Machine) named "Bold" for the underground section of the Nhon - Hanoi Station metro project.

Previously, the first TBM named “Than Thuong” started drilling the tunnel on July 30, 2024. To date, the first TBM of the project has drilled 985m of tunnel.

In fact, the fact that the TBM “Bold” has only now begun its tunneling mission is behind schedule. According to the previous plan, when the TBM “Speed” drilled 240m (around September 2024), the TBM “Bold” would be started. However, at that time, the TBM “Speed” encountered obstacles during the drilling process.

“The first TBM encountered very complicated geological problems, the gravel layer was harder than expected... At this time, the machine's parameters had to be continuously adjusted and the speed reduced. At that time, the contractor decided to let the first machine continue drilling to collect complete geological data, as a basis for adjusting the second TBM, ensuring the second TBM's operation was smoother and more effective,” said Mr. Nguyen Ba Son - Deputy Head of the Hanoi Urban Railway Management Board.

According to Mr. Son, after changing the parameters to suit the geological situation, the “Speed” TBM has now reached a speed of 18m/day (the previous plan was about 10-12m/day). It is expected that by the end of 2025, both tunnels of the Nhon - Hanoi Railway Station metro project will complete drilling and move on to the next phase.

Regarding the construction progress of the 4km underground section of the Nhon - Hanoi station metro project, up to now, the tunnel and underground stations have reached 53.46%; the underground ramp has been completed 75.66%; station S9 has been completed 50.48%; the vertical shaft has been completed 24.09%; the tunnel has reached 47.41%; stations S10, S11, S12 (including lane change and garage) have been completed 64.44%, 58.1%, 58.4% respectively.

“During the excavation process of the first TBM, we supplied more air to the compression chamber and reduced the amount of soil and rock in the chamber to balance the pressure, while performing other difficult techniques to get the first TBM through the complex geological area. We are completely confident that we can achieve the desired progress when starting the second TBM,” informed Mr. Park Young Ill - Project Director, Hyundai & Ghella Joint Venture.

It is expected that the underground section of the Nhon - Hanoi Railway Station metro project will be completed and put into operation in 2027.

Tô Thế
RELATED NEWS

The second tunnel boring machine of Nhon - Hanoi station metro starts

|

The second TBM named “Bold” for the underground section of the Nhon - Hanoi Railway Station metro project has officially started.

More than 3.1 million passengers have traveled on the Nhon - Hanoi station metro

|

Hanoi - After more than 4 months of operation, the Nhon - Hanoi Railway Station metro has safely transported over 3.1 million passengers.

Underground metro section Nhon - Hanoi station revealed

|

Hanoi - The progress of the underground metro section Nhon - Hanoi station has reached 50.27%, in which the TBM excavator has drilled more than 600m underground.

Commune government in Gia Lai speaks out about the case of large trees rising unusually in the middle of the Ayun River bank

|

Gia Lai - Phu Thien commune authorities determined that the large piece of wood that had risen on the banks of the Ayun River had been submerged in water for a long time, with no signs of being newly sawed and the owner unknown.

Cold air intensifies and causes rain, forecast coldest day

|

Due to the strengthening of cold air, the temperature continued to decrease on the night of November 3 and November 4. The mountainous areas of the North will have severe cold, with temperatures dropping below 15 degrees Celsius.

Banning all cars across the Lo River bridge in Phu Tho

|

Phu Tho - The provincial Department of Construction has just announced the adjustment of traffic flow through the Lo River Bridge, Doan Hung Commune.

Quoc Cuong Gia Lai has spent an additional VND900 billion to get back the Bac Phuoc Kien project

|

HCMC - Quoc Cuong Gia Lai's biggest financial burden is still the obligation related to the Bac Phuoc Kien residential area project.

Heartbroken by the family of a young man who died while attending a wedding in Hoa Binh lake

|

Phu Tho - The landslide on Hoa Binh Lake took the life of the only pillar of a poor family, leaving behind a heartbreaking pain for his family.

The second tunnel boring machine of Nhon - Hanoi station metro starts

Tô Thế |

The second TBM named “Bold” for the underground section of the Nhon - Hanoi Railway Station metro project has officially started.

More than 3.1 million passengers have traveled on the Nhon - Hanoi station metro

Tô Thế |

Hanoi - After more than 4 months of operation, the Nhon - Hanoi Railway Station metro has safely transported over 3.1 million passengers.

Underground metro section Nhon - Hanoi station revealed

HỮU CHÁNH |

Hanoi - The progress of the underground metro section Nhon - Hanoi station has reached 50.27%, in which the TBM excavator has drilled more than 600m underground.