Metro No. 2 has reached 60% of the infrastructure relocation progress, and will start construction of bidding packages in 2026

Anh Tú |

HCMC - Metro Line 2 has completed 100% of the site, infrastructure relocation has reached 60%, and is expected to start construction of all major packages in 2026.

Mr. Phan Cong Bang - Head of the Ho Chi Minh City Urban Railway Management Board - said that up to now, the site clearance of Metro Line 2 (Ben Thanh - Tham Luong) has been 100% completed, with all 585/585 cases having handed over the site to the investor. On that basis, contractors are simultaneously implementing the relocation of technical infrastructure at many key locations.

Truong Ban Quan ly duong sat do thi TP HCM Phan Cong Bang thi sat goi thau di doi ha tang ky thuat thuoc tuyen metro so 2 dem 13.7. Ảnh: My Quynh
Head of the Ho Chi Minh City Urban Railway Management Board Phan Cong Bang inspected the package to relocate technical infrastructure for Metro Line 2 on the night of July 13. Photo: My Quynh

As of mid-July 2025, the volume of infrastructure relocation for the entire route has reached about 60%, with an implementation value of nearly 600 billion VND. Some areas such as Dan Chu Station, Ba Queo Station, Pham Van Bach Station are complex points that need to be synchronously coordinated with many units such as electricity, water supply and drainage, telecommunications, etc.

Cong nhan thi cong hang muc di doi ha tang tuyen metro so 2 trong dem de day nhanh tien do. Ảnh: My Quynh
Workers constructed the infrastructure relocation of Metro Line 2 overnight to speed up the progress. Photo: My Quynh

To keep up with the progress, the Management Board will hold an operating meeting and update the construction progress every night. Some items are constructed at night to take advantage of time, reduce the impact on urban traffic and shorten the total implementation time. At construction sites, traffic police were deployed to support traffic flow, along with warning staff to ensure safety.

According to the plan, the relocation of infrastructure will be completed around December 2025, creating conditions for the simultaneous start of construction of the main packages in 2026. We have identified this as a key foundation phase of the project. Any problems beyond the authority are immediately reported for handling, not to affect the overall progress of the entire route, Mr. Phan Cong Bang emphasized.

Khu vuc ga Dan Chu hien la noi co khoi luong ha tang can di doi nhieu nhat, doi hoi phai phoi hop cung luc nhieu don vi nhu dien luc, cap thoat nuoc, vien thong...
The Dan Chu Station area is currently the place with the largest amount of infrastructure that needs to be relocated, requiring the coordination of many units such as electricity, water supply and drainage, telecommunications, etc. Photo: My Quynh
Tuyen Metro so 2 da giai phong 100% mat bang. Ảnh: Anh Tu
Metro Line 2 has cleared 100% of the land. Photo: Anh Tu

Metro Line 2 is more than 11km long, including 10 stations (9 underground, 1 elevated), with a total investment of more than VND 47,890 billion.

Anh Tú
TIN LIÊN QUAN

HCMC is about to start construction of Metro Line 2, expected to be operational by 2030

|

Ho Chi Minh City is preparing to start construction of Metro Line 2, more than 11 km long, after completing 100% of site clearance work, expected to be operational by the end of 2030.

Morning news 11.7: Uprooting Metro No. 2 construction site after 100% of cleared land

|

Morning news on 11.7: Rehabilitation at Metro No. 2 construction site after 100% of cleared land; Tunnel collapse in the US, 31 workers stuck;...

Metro No. 2 construction site is bustling after 100% of the site is clean

|

HCMC - Metro Line 2 project has completed site clearance and is urgently constructing the relocation of technical infrastructure, aiming to start construction in December 2025.

Husband goes to work far away, is stunned when he hears the news of his wife and children dying at home due to landslides

|

Lao Cai - While the mother and child in Xuan Ai commune were sleeping, the hill behind the house collapsed, mud collapsed, killing the two victims.

The difficulty of Vietnamese broadcasters when buying the copyright for the 2026 World Cup

|

In addition to the high copyright price for the 2026 World Cup broadcast, Vietnamese broadcasters are also facing the problem of "smuggling" that has not been completely handled.

Innovation in thinking, improving the effectiveness of internal political security protection

|

On July 13 and 14, in Hanoi, the Party Committee of the Department of Internal Political Security (ANCTNB), Ministry of Public Security held the 2nd Congress, term 2025-2030. Senior General Pham The Tung, member of the Standing Committee of the Central Public Security Party Committee, Deputy Minister of Public Security attended and directed the congress.

The case of dozens of workers being owed wages in Dien Bien, businesses continue to promise

|

Dien Bien - The case of dozens of workers being owed wages, the enterprise promised to repay the debt in July. Previously, this enterprise committed to repay the debt before June 30 and then broke the promise.

The long-term upward trend of stocks is still maintained

|

The liquidity of the stock market is still likely to improve and the cash flow waiting to buy when a correction appears is still there.

HCMC is about to start construction of Metro Line 2, expected to be operational by 2030

Nhóm PV |

Ho Chi Minh City is preparing to start construction of Metro Line 2, more than 11 km long, after completing 100% of site clearance work, expected to be operational by the end of 2030.

Morning news 11.7: Uprooting Metro No. 2 construction site after 100% of cleared land

HUYỀN TRANG - DUY HƯNG |

Morning news on 11.7: Rehabilitation at Metro No. 2 construction site after 100% of cleared land; Tunnel collapse in the US, 31 workers stuck;...

Metro No. 2 construction site is bustling after 100% of the site is clean

Anh Tú |

HCMC - Metro Line 2 project has completed site clearance and is urgently constructing the relocation of technical infrastructure, aiming to start construction in December 2025.