On May 2nd, Chairman of Thanh Xuan Ward People's Committee Do Quang Duong went to inspect the site of demolition and handover of the site of Ring Road 2.5 Project.
During the April 30th and May 1st holidays, Thanh Xuan ward still maintains forces closely following the area, supporting people to move property, dismantle eligible works and prepare ground for construction.
The mobile team and the standing militia force of the ward participated in transporting belongings, supporting the dismantling of some items, and at the same time propagating and mobilizing people to coordinate in handing over the site.


Previously, Thanh Xuan ward handed over about 8,000m2 of cleared land to the Hanoi City Traffic Construction Investment Project Management Board, serving the construction of the 2.5 Ring Road project, Nguy Nhu Kon Tum - Nguyen Trai section.
At the same time, the ward continues to complete the tasks to hand over the remaining area in the total recovered area of about 1.8ha, equivalent to 40% of the area to be recovered in the area.
The handed over land area includes 4 groups of areas. In which, the Quan Nhan - Nhan Hoa street intersection area has an area of 4,411.1m2, including land for the Ward Police headquarters, Ward People's Committee headquarters, Ao Ngoi But land area managed by the Ward People's Committee and a part of traffic land on Nhan Hoa street, Quan Nhan street.
The remaining areas include 1,076.6m2 of traffic land at the intersection of Hoang Dao Thuy street, Nguy Nhu Kon Tum street, alley 116 Nhan Hoa street; 1,170.9m2 of traffic land in the Nguyen Trai street area; 1,300.65m2 belonging to 28 households and individuals who have handed over land and dismantled works on land.
After handover, Thanh Xuan ward continues to collect waste and remaining materials to serve barricades, machinery gathering and construction; at the same time, coordinate to handle arising problems within the project scope.



On the same day, at Thanh Xuan Ward People's Committee, Agribank Hanoi Branch coordinated with the Ward Investment - Infrastructure Project Management Board, State Treasury Area 1 Branch No. 5 to deploy the payment of compensation and site clearance support costs for the Ring Road 2.5 project.
Even on holidays, officials are still ready to accompany and support the payment of compensation costs to people quickly and promptly, with a sense of responsibility and transparency.
Ring Road 2.5 section passing through Thanh Xuan ward is nearly 1km long, with a cross-section of about 50m, with a land area to be recovered of more than 39,000m2. The road passes through a densely populated residential area, including the old Nhan Chinh village area, related to 472 land plots and about 700 households, so site clearance is very difficult.