Road expansion project worth nearly 300 billion VND in HCMC is in disarray

Tâm Tú |

Ho Chi Minh City - The Hoang Hoa Tham Street expansion project with a total investment of nearly 300 billion VND is still in disarray, and the site has not been handed over yet.

The project to expand Hoang Hoa Tham Street, from the gate of the military barracks (adjacent to the airport) to Cong Hoa Street, is nearly 800 m long, the road surface is 8-10 m wide and will be expanded to 22 m.

The project was approved in October 2016 with a total investment of VND255 billion. However, after many years of not being implemented, in July 2022, the project was approved by the Ho Chi Minh City People's Council to adjust the total investment to nearly VND291 billion (mainly due to the cost of site clearance).

 Nhieu nha dan sau hoan tat viec ban giao mat bang da sua sang nha cua, on dinh cuoc song. Anh: Anh Tu
Many households have renovated their houses and stabilized their lives after completing the handover of the land. Photo: Anh Tu

The project to upgrade and expand Hoang Hoa Tham Street, with 150 cases within the clearance area, has achieved positive progress after more than a year of implementing compensation and site clearance work.

2 can nha so 247 va 251 Hoang Hoa Tham thuoc du an mo rong duong Hoang Hoa Tham (tu cong doanh trai quan doi den cau vuot Hoang Hoa Tham) da hoan tat giao mat bang vao chieu 22.11. Anh: Anh Tu
149/150 households in the Hoang Hoa Tham Street expansion project (from the military barracks gate to Hoang Hoa Tham overpass) have completed handover of land. Photo: Anh Tu

According to the representative of the Compensation and Site Clearance Board of Tan Binh District, up to now, the unit has completed the land acquisition of 149/150 households in the Hoang Hoa Tham Street expansion project (from the gate of the military barracks to the Hoang Hoa Tham overpass). The unit is continuing to mobilize the last household, if the household does not hand over the land, the land acquisition will be carried out on November 26. The delay in handing over the land affects the progress of the Hoang Hoa Tham Street expansion project, which is expected to be completed in 2025.

Con mot ho dan duy nhat o can nha so 151 Hoang Hoa Tham van chua thong nhat ban giao mat bang thi cong. Anh: Anh Tu
A case of undelivered handover. Photo: Anh Tu

At the same time, according to Lao Dong reporters, a section of Hoang Hoa Tham Street leading to Cong Hoa Street is currently littered with bunkers, construction materials and machinery. This narrows the road, making it difficult for people to travel through.

Vat lieu xay dung, may moc ngon ngang o via he doc tuyen duong Hoang Hoa Tham (quan Tan Binh). Anh: Anh Tu
Construction materials and machinery are scattered on the sidewalk along Hoang Hoa Tham Street (Tan Binh District). Photo: Anh Tu

Mr. Nguyen Chi Cuong (residing in Tan Binh district) said: “During rush hour, a section of Hoang Hoa Tham Street towards Cong Hoa is always congested, the reason being that materials and machinery are left lying around, occupying the entire road. I hope the project will be completed soon so that people can travel more easily.”

Lo cot chan mot phan dien tich mat duong, khien giao thong qua doan nay thuong xuyen dong duc, xe co di chuyen cham. Anh: Anh Tu
The bunker blocks part of the road surface, causing traffic through this section to be often congested and vehicles to move slowly. Photo: Anh Tu
Mat duong Hoang Hoa Tham doan huong ve duong Cong Hoa nham nho, loi lom, via he chat day vat lieu xay dung. Anh: Anh Tu
Hoang Hoa Tham Street, the section towards Cong Hoa Street, is bumpy, the sidewalk is full of construction materials. Photo: Anh Tu

The Hoang Hoa Tham Street Upgrade Project is not only an important step in developing transport infrastructure, but also has great significance in improving the quality of life for residents in the area. The rapid completion of the project will contribute significantly to the urban beautification process and improve traffic in the area.

Duong Hoang Hoa Tham va duong noi Tran Quoc Hoan - Cong Hoa khi hoan thanh ngoai ket noi truc tiep vao nha ga T3 (du kien hoan thanh nam 2025), con giup pha the doc dao cua duong Truong Son ra vao san bay Tan Son Nhat, giup giam un tac cho khu vuc quan Tan Binh. Anh: Anh Tu
Hoang Hoa Tham Street and the Tran Quoc Hoan - Cong Hoa connecting road, when completed, will not only directly connect to Terminal T3 (expected to be completed in 2025), but will also help break the monopoly of Truong Son Street to and from Tan Son Nhat Airport, helping to reduce traffic congestion in Tan Binh District. Photo: Anh Tu
Tâm Tú
TIN LIÊN QUAN

Appearance of Tan Son Nhat T3 terminal after nearly 2 years of construction

|

HCMC - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, and overpass.

Land prices for sale along Ring Road 4 pushed up

|

Hanoi - Many plots of land along Ring Road 4 (Hanoi) have recently been pushed up in price rapidly.

Reasons why teachers in Son La province had their allowances for group leaders and deputy group leaders cut

|

Son La province has not yet paid allowances for group leaders and deputy group leaders to teachers despite instructions from the Department of Teachers and Educational Managers (Ministry of Education and Training).

Apartment prices may remain flat at peak

|

After a long period of increasing momentum, experts predict that apartment prices will slow down and remain stable next year.

Brainstorming to choose university admission options in 2025

|

Changes in the 2025 high school graduation exam make it difficult for students to choose combinations and university admission options.

Gold price update morning of November 25: Bright outlook, high expectations

|

Gold price update on the morning of November 25: After a week of strong increases, gold is receiving positive forecasts from experts.

Leveraging AI - the golden key to increasing labor productivity

|

In the era of the 4.0 industrial revolution, artificial intelligence (AI) is becoming a key factor changing the global economic landscape. From manufacturing, management to healthcare, AI not only helps improve labor productivity but also opens up new opportunities and challenges for the labor market. The explosion of AI has been reshaping the way Vietnamese businesses operate.

Investors are cautious with the story of probing the market bottom

|

The stock market is relatively difficult to predict as major macro policies have not been issued in detail, making investors quite apprehensive.

Appearance of Tan Son Nhat T3 terminal after nearly 2 years of construction

MINH QUÂN |

HCMC - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, and overpass.

Hoàn thành lắp mái thép nhà ga T3 Tân Sơn Nhất sớm 2 tháng

MINH QUÂN |

TPHCM - Công tác lắp đặt mái thép của nhà ga T3 sân bay Tân Sơn Nhất đã hoàn thành sớm hơn dự kiến 2 tháng, giúp đẩy nhanh tiến độ dự án.

TPHCM chi gần 300 tỉ đồng mở rộng đường vào sân bay Tân Sơn Nhất lên 22m

MINH QUÂN |

TPHCM - Đường Hoàng Hoa Thám (từ cổng doanh trại quân đội đến đường Cộng Hòa), dài gần 800m được mở rộng lên 22m với tổng vốn gần 300 tỉ đồng, hoàn thành năm 2025 giúp kết nối nhà ga T3 sân bay Tân Sơn Nhất.