Appearance of Tan Son Nhat T3 terminal after nearly 2 years of construction

MINH QUÂN |

HCMC - After nearly two years of construction, Tan Son Nhat Airport's T3 terminal has been revealed with important items such as the roof, basements and above-ground floors, commercial area, and overpass.

In early November, workers were urgently installing glass walls on the passenger terminal floors, with the goal of completing this item by the end of the year.

Mr. Le Dang Bien - a 45-year-old worker - participating in the project, shared: "This is an important project of the city, so everyone is trying their best to complete the station and put it into use soon."

Inside Terminal 3, the steel frame and roof structure have been installed. Currently, contractors are completing items such as ceilings, installing glass walls and paving stone floors.

Ben trong ga hanh khach da lap ket cau khung va mai sat thep.  Anh: Minh Quan
Inside the passenger terminal, a steel frame and roof structure has been installed. Photo: Minh Quan

The passenger waiting area, check-in counter and security screening areas also have completed the structural frame.

The terminal has 90 traditional airline check-in counters, 20 automatic bagdrop counters and 42 check-in kiosks, 27 boarding gates (including 13 telescopic gates and 14 bus gates), 6 departure baggage handling islands and 10 arrival baggage return islands, and 25 security control gates.

Thi cong ong long ra tau bay.  Anh: Minh Quan
Construction of the aircraft's tube. Photo: Minh Quan

The overpass system at the station is under construction and is expected to be closed by the end of December and completed in February next year. The auxiliary systems such as elevators and escalators are expected to be completed by December this year.

He thong cau can o nha ga du kien hoan thanh thang hai nam sau.  Anh: Minh Quan
The overpass system at the station is expected to be completed in February next year. Photo: Minh Quan

Contractors are actively deploying equipment and machinery systems for items such as air conditioning ducts, fire protection and water supply and drainage. More than 90% of this work has been completed on the B2 floors of the commercial building, as well as the B1 floors and the 1st floor of the passenger terminal.

Nha ga T3 co 1 tang ham, 4 tang noi, duoc thiet ke thanh hai phan di - den rieng biet.
Terminal T3 has 1 basement and 4 floors above ground, designed into two separate departure and arrival sections. Photo: Minh Quan

Terminal T3 of Tan Son Nhat airport is expected to be completed on April 30, 2025, two months ahead of schedule.

When put into operation, this will be the largest domestic terminal in the country with a capacity to serve 20 million passengers per year, helping to increase the total capacity of Tan Son Nhat airport to 50 million passengers per year.

fff
T3 station glass has been almost installed. Photo: Minh Quan
Nha thau huy dong khoang 2.500 ky su, cong nhan thi cong.  Anh: Minh Quan
The contractor mobilized about 2,500 engineers and construction workers. Photo: Minh Quan

Mr. Le Khac Hong - Head of T3 Terminal Project Management Board - said that after nearly 2 years since the start of construction in December 2022, the total workload has reached about 75%, with most of the main items having completed the structural part.

“The entire project must be completed before the inauguration date on April 30, 2025, to celebrate the 50th anniversary of the Liberation of the South and National Reunification Day. To achieve this goal, the investor and contractors are launching a 90-day and night competition, with the determination to complete the entire roof, facade glass and power the project,” said Mr. Le Khac Hong.

Currently, more than 2,500 engineers and workers along with hundreds of equipment and machines have been mobilized to work continuously 24/7 to ensure progress.

To enhance connectivity with Terminal T3, Ho Chi Minh City is implementing the Tran Quoc Hoan - Cong Hoa connecting road project and expanding Hoang Hoa Tham Street.

Of which, the Tran Quoc Hoan - Cong Hoa connecting road project is more than 4 km long, with a total investment of over 4,800 billion VND, and will be completed by the end of 2024.

The project to expand Hoang Hoa Tham Street, from the military barracks gate to Cong Hoa Street, with a total investment of nearly 300 billion VND, is expected to be completed in the first quarter of 2025.

MINH QUÂN
TIN LIÊN QUAN

Iran wins best film, Vietnam has 1 award at HANIFF 2024

|

The closing ceremony and awards ceremony of the Hanoi International Film Festival (HANIFF) announced the winning works and individuals.

Awarding the press prize on national solidarity

|

The 2023-2024 "For the cause of great national unity" Press Award was held on the evening of November 11.

8pm News: Subsidies increase, people with police status enjoy the benefits

|

News at 8pm on November 11: Pensions and allowances for meritorious people increase, the elderly feel secure in their old age; Hanoi plans to reclaim land from more than 300 households to open a 60m wide road...

Selling at a difference of 300 - 500 million VND/lot after Hoai Duc land auction

|

Hanoi - Immediately after the auction in Hoai Duc district ended, many land brokers quickly sold each plot of land for a difference of 300-500 million VND.

Fierce street fighting in strategic eastern Ukraine city

|

Russia says street fighting has begun in strategic eastern Ukraine city.

Mr. Pham Thanh Ngai was elected Chairman of Ca Mau Provincial People's Committee

|

Ca Mau - Before being elected Chairman of the Provincial People's Committee, Mr. Pham Thanh Ngai was the Standing Deputy Secretary of the Provincial Party Committee.

Parents entered the school to "disperse" the student's vehicle that violated the law

|

Hanoi - When the authorities inspected the school's parking lot, some students called their parents to come to school to get their cars back to avoid being fined.

Hoàn thành lắp mái thép nhà ga T3 Tân Sơn Nhất sớm 2 tháng

MINH QUÂN |

TPHCM - Công tác lắp đặt mái thép của nhà ga T3 sân bay Tân Sơn Nhất đã hoàn thành sớm hơn dự kiến 2 tháng, giúp đẩy nhanh tiến độ dự án.

Vượt khó thi công dự án nhà ga thứ 3, giảm tải cho sân bay Tân Sơn Nhất

MINH QUÂN |

TPHCM – Bất chấp gặp nhiều trở ngại như mặt bằng chật hẹp, thi công sát sân bay đang khai thác, dự án nhà ga T3 sân bay Tân Sơn Nhất vẫn được nỗ lực để thi công vượt tiến độ, đang băng băng về đích dịp 30.4.2025.

Vẻ hoành tráng của dự án ga T3 Tân Sơn Nhất đang thẳng tiến về đích

MINH QUÂN |

TPHCM - Nhà ga T3 sân bay Tân Sơn Nhất có quy mô 1 tầng hầm, 4 tầng nổi đã xây dựng xong phần thô, đang tiến hành lắp khung phần mái. Đây là ga quốc nội lớn nhất nước phục vụ 20 triệu lượt khách mỗi năm, sẽ hoàn thành đưa vào khai thác vào dịp 30.4.2025.