Reasons for Khanh Hoa's slow disbursement of public investment capital

Hữu Long |

Khanh Hoa - The disbursement of local public investment capital is still slow due to many reasons such as land clearance and failure to issue bond capital.

As of early December 2024 in Khanh Hoa, the estimated disbursement rate for the first 11 months of 2024, compared to the capital plan assigned by the Prime Minister, was 55.8% of the 2024 capital plan. Compared to the actual capital plan assigned by the Khanh Hoa Provincial People's Committee, the disbursement rate for the 2024 capital plan was 62.2%.

Meanwhile, the estimated implementation rate of the 13-month period of 2024 (from January 1, 2024 to January 31, 2025) is 85.3% compared to the capital plan assigned by the Prime Minister. Compared to the actual capital plan assigned by the People's Committee of Khanh Hoa province, the estimated disbursement rate of the capital plan for the 13 months of 2024 is 95.1%.

The disbursement results of the public investment capital plan for the 11 months of 2024 are still low due to objective reasons such as the proposed local government bond capital source not being issued is VND 855.6 billion.

Regarding this content, up to now, Khanh Hoa province has sent a document reporting to the Ministry of Finance and the Ministry of Planning and Investment on the proposal to adjust and reduce the source of local government bonds in 2024.

Along with that, the reason for the current slow site clearance work is that the district-level human resources allocated to carry out compensation work in districts, towns and cities are still limited compared to the increasing site clearance needs of localities to serve projects.

Khanh Hoa province also identified subjective causes due to slow investment procedures and contractor selection affecting the project's disbursement progress; the implementation of compensation and site clearance is currently facing difficulties due to the slow implementation of the work of determining specific land prices for compensation and resettlement support at the district level...

From the above reasons, Khanh Hoa province has directed for newly started projects, investors to urgently complete investment procedures, select contractors to speed up the implementation progress and disburse the assigned capital plan.

For projects that have been constructed, are not involved in compensation, site clearance, or are only involved in part of compensation, site clearance, investors urge contractors to speed up the implementation progress, ensure to meet and exceed the set progress, promptly pay for completed and accepted volumes, and not let payment and disbursement files accumulate at the end of the year.

In addition, based on the ability to implement and disburse the actual capital plan of the projects in 2024, the Provincial People's Committee has flexibly operated, submitted to the Provincial People's Council to adjust the capital plan for 2024, transferred capital of projects that are not feasible, disbursed all the assigned capital plan to projects with good disbursement, and need additional capital to speed up the implementation progress.

Hữu Long
RELATED NEWS

Khanh Hoa should not abandon the resettlement area worth nearly 400 billion any longer

|

The nearly 400 billion VND resettlement area called Xom Quan in Khanh Hoa is abandoned because not many people come to live there.

Progress of site clearance for 2 key highways in Khanh Hoa

|

The Van Phong - Nha Trang Expressway and the Khanh Hoa - Buon Ma Thuot Expressway have reached the finish line. Up to now, the site clearance work has been carried out urgently.

Chairman of Lam Dong Provincial People's Committee requested an investigation into the case of a dam burst causing flash floods

|

Lam Dong - Chairman of the Provincial People's Committee directed competent agencies to focus on investigating and clarifying the cause of the water reservoir burst in village 2, Tuy Phong commune.

Revealing the ecosystem of hundreds of billions of VND of actor Truong Ngoc Anh

|

Before being arrested, Truong Ngoc Anh had built a business ecosystem worth hundreds of billions of VND, from real estate, advertising, beauty rights, entertainment, etc.

Urgently rescue people in a house buried by landslides in Da Nang

|

Da Nang - Severe landslides buried 6 houses, authorities saved 1 person.

Commune government in Gia Lai speaks out about the case of large trees rising unusually in the middle of the Ayun River bank

|

Gia Lai - Phu Thien commune authorities determined that the large piece of wood that had risen on the banks of the Ayun River had been submerged in water for a long time, with no signs of being newly sawed and the owner unknown.

Cold air intensifies and causes rain, forecast coldest day

|

Due to the strengthening of cold air, the temperature continued to decrease on the night of November 3 and November 4. The mountainous areas of the North will have severe cold, with temperatures dropping below 15 degrees Celsius.

New road to the East of Ho Chi Minh City opens more direction, reducing pressure on Vo Nguyen Giap traffic axis

|

The Vo Nguyen Giap parallel road has just been put into operation, opening a new traffic direction, contributing to reducing pressure on the East of Ho Chi Minh City.

Tân Bí thư Khánh Hòa tiếp dân vụ thu hồi đất kéo dài 15 năm

Hữu Long |

Tân Bí thư tỉnh ủy Khánh Hòa sẽ tiếp dân có đất bị thu hồi tại dự án Khách sạn Sasco Nha Trang kéo dài đã 15 năm qua.

Khanh Hoa should not abandon the resettlement area worth nearly 400 billion any longer

Lê Thanh Phong |

The nearly 400 billion VND resettlement area called Xom Quan in Khanh Hoa is abandoned because not many people come to live there.

Progress of site clearance for 2 key highways in Khanh Hoa

Hữu Long |

The Van Phong - Nha Trang Expressway and the Khanh Hoa - Buon Ma Thuot Expressway have reached the finish line. Up to now, the site clearance work has been carried out urgently.