Compared to the national average, the disbursement rate of public investment capital in Kon Tum is still low.
The project of embankment against floods and landslides in ethnic minority villages along Dak Bla river in Kon Tum city has disbursed more than 5.7 billion VND/205.4 billion VND; the project of main road in the West of Kon Tum city has disbursed 9 billion VND/353 billion VND;
The project of traffic road from Dak Pne commune, Kon Ray district to Kbang district (Gia Lai province) disbursed 529 million VND/58.6 billion VND; the project of investment in construction, renovation and upgrading of Provincial Road 676 connecting Kon Plong district, Kon Tum province with Son Tay and Son Ha districts, Quang Ngai province disbursed 12 billion VND/232 billion VND.
Kon Tum Provincial Department of Planning and Investment assessed that delays in disbursing investment capital occurred at all stages from the investment preparation stage to the project implementation stage.
In the preparation stage, the main problems are related to the slow preparation, approval, and adjustment of general urban planning, zoning planning, and detailed planning.
In addition, the process and procedures for converting forest use to other purposes according to the provisions of the Forestry Law are still complicated. Kon Tum has to ask for opinions from many levels and ministries, which does not create initiative for the locality.
Many projects in Kon Tum province are also stuck in site clearance, related to determining land origin, inventory, declaration to classify compensation land...
Project investors as well as construction units have to struggle and face difficulties when wanting to speed up construction progress to avoid having their capital recovered.