The billion-dollar intersection in the East of Ho Chi Minh City is expected to be completed in 2026

Tâm Tú |

HCMC - After 9 years of construction, the My Thuy intersection project - a project expected to "rescue" traffic congestion in the East of HCMC continues to start construction in phase 3.

On March 14, the Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) held a groundbreaking ceremony for the My Thuy intersection construction project (phase 3) in Thu Duc City.

According to the Traffic Department, this is a key traffic project of Ho Chi Minh City.

Le khoi cong xay dung nut giao My Thuy (TP Thu Duc) ngay 14.3. Anh: Minh Tam
The groundbreaking ceremony for the construction of My Thuy intersection (Thu Duc City) on March 14. Photo: Minh Tam

The project aims to invest in the construction of a complete My Thuy intersection to increase the capacity of traffic through the intersection, contributing to solving traffic congestion, ensuring traffic safety and order on Nguyen Thi Dinh - Dong Van Cong roads and Ring Road 2 (now Vo Chi Cong road); meeting the increasing demand for freight and passenger transport in the area, especially the Phu My bridge area and Cat Lai port cluster; serving local socio-economic development.

Hinh anh nut giao My Thuy (TP Thu Duc) nhin tu tren cao. Anh: Anh Tu
Image of My Thuy intersection (Thu Duc City) seen from above. Photo: Anh Tu

The project items are divided into 3 investment phases. Up to now, the Traffic Department has completed a number of items in phase 1 and phase 2 of the project, put into use from the beginning of 2019 to 2021 such as: left turn underpass, a single bridge over 4 lanes on Ring Road 2 and Ky Ha 3 bridge - left branch, My Thuy 3 bridge with 6 lanes located between My Thuy 1 bridge and My Thuy 2 bridge.

Cac phuong tien noi dai khi luu thong qua nut giao My Thuy (TP Thu Duc). Anh: Anh Tu
Vehicles are extended when traveling through My Thuy intersection (Thu Duc City). Photo: Anh Tu

From the end of 2023 to now, the Traffic Department has also been urgently implementing the construction of a number of items that have been handed over, including the left overpass from Cat Lai to Phu My, and Ky Ha 4 bridge.

Phase 3 of the project will include an overpass on Ring Road 2 - right branch and Ky Ha 3 Bridge - right branch with 4 lanes.

Mr. Le Ngoc Hung - Deputy Director of the Ho Chi Minh City Traffic Construction Investment Project Management Board - said that the entire My Thuy intersection construction project is divided into 2 component projects, with a total investment of more than VND 3,600 billion.

Ket xe thuong xuyen xay ra tai khu vuc nut giao My Thuy (TP Thu Duc). Anh: Anh Tu
Traffic jams often occur at My Thuy intersection (Thu Duc City). Photo: Anh Tu

In which, component project 1 is a construction project with a total investment of 1,826 billion VND (of which the items of phase 3 have an investment of 312 billion VND); component project 2 is a compensation, site clearance and resettlement project with a total investment of 1,623 billion VND invested by the Thu Duc City Construction Investment Project Management Board.

The total land use area for the project to carry out compensation, support and resettlement is 16.6 hectares, with 195 households having to hand over the land to implement the project.

Du kien toan bo du an xay dung nut giao My Thuy se hoan thanh vao nam 2026. Anh: Anh Tu
It is expected that the entire My Thuy intersection construction project will be completed in 2026. Photo: Anh Tu

Immediately after the Ho Chi Minh City People's Committee approved the additional investment in phase 3 to ensure the construction of the intersection in accordance with the complete scale approved by the Ho Chi Minh City People's Council, the Traffic Department urgently focused resources, coordinated with the Ho Chi Minh City Department of Transport to speed up the appraisal of design documents, organize the selection of construction contractors, and supervision consultants to start construction today, said Mr. Hung.

According to the Deputy Director of the Traffic Department, the organization of the construction of phase 3 of the project must ensure close coordination with the items being implemented to minimize the impact on existing traffic, minimize the impact of the construction process on people's daily life and travel and strive to complete the entire project by April 30, 2026.

At the groundbreaking ceremony, Mr. Mai Huu Quyet - Vice Chairman of Thu Duc City People's Committee - said that the project has great significance, meeting the expectations of the Party, government and people of Ho Chi Minh City in general and Thu Duc City in particular. The project will complete the transport infrastructure and promote the socio-economic development of the area.

According to Mr. Quyet, compensation, support, resettlement and site clearance have been accelerated, ensuring progress according to plan.

Tâm Tú
TIN LIÊN QUAN

The largest intersection in Ho Chi Minh City is about to open the first underpass

|

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

Current status of the billion-dollar intersection in Ho Chi Minh City has been congested for 9 years due to land clearance

|

HCMC - Construction started in 2016, but the My Thuy intersection (Thu Duc City) has not yet been completed due to land clearance problems.

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

|

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.

less than 1km of road in Hanoi is littered with garbage due to slow progress

|

Hanoi - The road connecting Do Duc Duc - Me Tri (Nam Tu Liem district) is less than 1km long, but the progress has been delayed after nearly 10 years of construction and is still not completed.

Current status of a 29-storey apartment building in Ho Chi Minh City with cracked walls after an earthquake

|

HCMC - A series of apartments in a 29-storey apartment building in District 8 were affected by a series of earthquakes due to an earthquake of more than 7 degrees richter in Myanmar, causing cracked walls and peeling brick floors.

Jisoo arrives in Hanoi, fans spend hundreds of millions of VND to welcome her

|

On the morning of March 30, Jisoo (Blackpink) went to Hanoi to prepare to perform at the fan meeting event in the afternoon of the same day.

The largest intersection in Ho Chi Minh City is about to open the first underpass

MINH QUÂN |

HCMC - The underpass from the HCMC - Long Thanh Expressway to Mai Chi Tho is 760m long, with 4 lanes, part of the An Phu Intersection project (Thu Duc City) and will open to traffic before April 30.

Current status of the billion-dollar intersection in Ho Chi Minh City has been congested for 9 years due to land clearance

TÚ QUỲNH |

HCMC - Construction started in 2016, but the My Thuy intersection (Thu Duc City) has not yet been completed due to land clearance problems.

The VND3,600 billion intersection in Ho Chi Minh City is stalled due to 186 land congestion

MINH QUÂN |

HCMC - The My Thuy intersection project with a total capital of more than VND3,600 billion continues to be stalled because Thu Duc City has not yet handed over 186 sites, greatly affecting the construction progress.