less than 1km of road in Hanoi is littered with garbage due to slow progress

THIỆN NHÂN |

Hanoi - The road connecting Do Duc Duc - Me Tri (Nam Tu Liem district) is less than 1km long, but the progress has been delayed after nearly 10 years of construction and is still not completed.

Du an xay dung tuyen duong noi Do Duc Duc - Me Tri co diem dau giao voi duong Do Duc Duc, diem cuoi giao voi duong Me Tri, do UBND quan Nam Tu Liem lam chu dau tu.
The project to build a road connecting Do Duc Duc - Me Tri has an starting point intersecting with Do Duc Duc road, an ending point intersecting with Me Tri road, invested by the People's Committee of Nam Tu Liem district.
Tuyen duong co tong chieu dai 828,58m va tong muc dau tu hon 264 ti dong. Sau khi hoan thien, tuyen duong du kien se cai thien giao thong, thuc day phat trien kinh te - xa hoi tai quan Nam Tu Liem. Tuy nhien, hien nay, ngay truoc tru so Dang uy va UBND phuong Me Tri, rac thai va vat lieu xay dung chat dong, gay o nhiem moi truong va bui ban.
The route has a total length of 828.58m and a total investment of more than 264 billion VND. After completion, the route is expected to improve traffic and promote socio-economic development in Nam Tu Liem district. However, currently, right in front of the headquarters of the Party Committee and People's Committee of Me Tri ward, garbage and construction materials are piled up, causing environmental pollution and dirt.
Mac du da duoc UBND TP Ha Noi phe duyet tu nam 2014 va khoi cong nam 2017 du an van chua hoan thanh.
Although approved by the Hanoi People's Committee in 2014 and started construction in 2017, the project is still behind schedule and has not been completed.
Ngay 30.3, theo ghi nhan cua Lao Dong, cong truong du an vang bong cong nhan va khong co dau hieu thi cong. Mot phan khu vuc con duoc tan dung lam bai do xe, trong khi nhieu diem rac thai tu phat chat dong doc theo tuyen duong, tao ra canh tuong nhech nhac, o nhiem.
On March 30, according to Lao Dong, the project site was deserted and there were no signs of construction. Part of the area is still used as a parking lot, while many spontaneous garbage dumps piled up along the road, creating a shabby, polluted scene.
Ngay truoc tru so Dang uy va UBND phuong Me Tri, rac thai va vat lieu xay dung chat dong, gay o nhiem moi truong va bui ban.
Right in front of the headquarters of the Me Tri Ward Party Committee and People's Committee, garbage and construction materials piled up, causing environmental pollution and dirt.
Nhieu khu vuc ben trong du an tro thanh bai gui xe, diem tap ket phe thai, sat vun.
Many areas inside the project have become parking lots, garbage collection points, and scrap iron.
Ben canh do, cac vat lieu xay dung nhu be tong, soi cat chat dong hai ben duong gay anh huong khong nho den nguoi tham gia giao thong.
In addition, construction materials such as concrete and gravel piled up on both sides of the road have a significant impact on traffic participants.
Tre nho choi dua ngay ben trong cong truong du an.
Children playing right inside the project site.
Du an keo dai suot nhieu nam qua da anh huong nghiem trong den doi song nguoi dan va canh quan do thi.
The project has lasted for many years and has seriously affected people's lives and the urban landscape.
Theo Ban Quan ly Du an Dau tu Xay dung quan Nam Tu Liem, tien do thuc hien du an gap kho khan do vuong mac ve giai phong mat bang. Du an phai thu hoi gan 30.000m2 dat, lien quan den 152 ho dan va 5 to chuc.
According to the Nam Tu Liem District Construction Investment Project Management Board, the project implementation progress is facing difficulties due to problems with site clearance. The project must reclaim nearly 30,000m2 of land, involving 152 households and 5 organizations.
Du kien, trong quy II nam 2025, cac vuong mac lien quan den mat bang se duoc giai quyet. Den quy III, quy IV nam 2025, toan bo cong tac giai phong mat bang se hoan tat, voi muc tieu hoan thanh du an va dua vao su dung trong nam 2026. Anh chup he thong thoat nuoc lo thien, o nhiem tren tien duong du an.
It is expected that in the second quarter of 2025, problems related to the site will be resolved. By the third and fourth quarters of 2025, all site clearance work will be completed, with the goal of completing the project and putting it into use in 2026. Photo of the exposed and polluted drainage system on the project road.
THIỆN NHÂN
TIN LIÊN QUAN

Land clearance problems, Mo Cay bridge project is about 40% behind schedule

|

Ben Tre - Due to land clearance problems, the construction volume of the Mo Cay bridge project has only reached about 18% of the contract value, about 40% behind schedule compared to the plan.

Land clearance problems, Bai Dinh - Ba Sao road project behind schedule

|

Ninh Binh - Due to problems in site clearance (GPMB), the Bai Dinh (Ninh Binh) - Ba Sao (Ha Nam) road project is behind schedule.

The Ministry of Construction explains the delay in the National Highway 14E expansion project

|

The Ministry of Construction has just responded to Quang Nam voters about the reason for the delay in the National Highway 14E expansion project.

Reasons for the fierce fire of a gasoline tank truck on the highway

|

The authorities have determined the initial cause of the fire of a gas tank truck on the Noi Bai - Lao Cai Expressway, passing through Yen Bai province.

Location of 40 gold mines with a total reserve of nearly 30 tons

|

40 gold mines with a total reserve of nearly 30 tons were discovered in scattered Northwestern provinces, of which Tuyen Quang and Bac Kan are the two localities with the most mines.

3 unfinished BT projects of Phuc Son Group in Khanh Hoa

|

Phuc Son Group currently has 3 BT (build - transfer) projects in Nha Trang, of which only the Ngoc Hoi Intersection project has determined the construction roadmap. The remaining two projects are currently on hold due to legal problems.

HCMC will expand National Highway 13 to accommodate 10 lanes connecting Binh Duong

|

The Chairman of the Ho Chi Minh City People's Committee assigned the project preparation task, the investor of the project to expand National Highway 13 (from Binh Trieu Bridge to the border of Binh Duong province) to 60 m, accommodating 10 lanes.

Gold price today 1.4: Breaking a new peak

|

Gold price today 1.4: World gold increased sharply. Domestic gold prices officially broke the 102 million VND/tael mark.

Land clearance problems, Mo Cay bridge project is about 40% behind schedule

Thành Nhân |

Ben Tre - Due to land clearance problems, the construction volume of the Mo Cay bridge project has only reached about 18% of the contract value, about 40% behind schedule compared to the plan.

Land clearance problems, Bai Dinh - Ba Sao road project behind schedule

NGUYỄN TRƯỜNG |

Ninh Binh - Due to problems in site clearance (GPMB), the Bai Dinh (Ninh Binh) - Ba Sao (Ha Nam) road project is behind schedule.

The Ministry of Construction explains the delay in the National Highway 14E expansion project

Xuyên Đông |

The Ministry of Construction has just responded to Quang Nam voters about the reason for the delay in the National Highway 14E expansion project.