Quang Nam revives the Truong Giang River with a trillion-dollar project

Hoàng Bin |

The Quang Nam Province Integrated Adaptive Development Project, with a total investment of more than VND 2,722 billion, will be implemented in September 2025.

Key project over 2,700 billion VND

On October 5, Chairman of Quang Nam Provincial People's Committee Le Van Dung chaired a meeting with departments, branches and localities related to the Quang Nam Province Integrated Adaptive Development project.

This is a trillion-dong project with main components: dredging the 60km-long Truong Giang River, ensuring the circulation of 100-ton ships; building 6 bridges across the Truong Giang River and a flood drainage project for Tam Ky City.

Du an nghin ti se nao vet song Truong Giang, Quang Nam dai 60km, xay dung ke tai cac noi nguy co sat lo bo. Anh: Nguyen Hoang
The trillion-dollar project will dredge the 60km-long Truong Giang River in Quang Nam, increasing flood drainage capacity. Photo: Nguyen Hoang

In addition, some businesses are researching investment in the Dam River urban area project (Tam Ky city) and upgrading Chu Lai airport (Nui Thanh district).

The project has a total investment of more than VND 2,722 billion, of which ODA loan from the World Bank is about VND 1,838 billion, counterpart capital is about VND 884.196 billion. The project implementation period is from 2022 - 2027.

The project's land use area is about 483 hectares, affecting 1,068 households due to land acquisition. Regarding the impact on aquaculture, there are about 7,122 households living along the river.

SCD
Dredging the Yangtze River will help "revive" the river which is gradually shrinking, polluted, and eroded. Photo: Nguyen Hoang

The project has been approved in principle for investment by the Prime Minister, and the Ministry of Natural Resources and Environment has approved the environmental impact assessment report.

Quang Nam provincial leaders assessed that this is a “key of the key” project that will revive the Truong Giang River, create a smooth traffic system; overcome flooding, and create momentum to promote inter-regional socio-economic development of Thang Binh - Duy Xuyen - Tam Ky...

Deployment in September 2025

With thousands of households located in the project's affected area, the Chairman of the Quang Nam Provincial People's Committee especially noted the need to propagate and mobilize people to agree to implement the project; focus on managing the current situation, not allowing illegal expansion and construction to wait for compensation...

"With the spirit that the lives of people affected by the project will be better, avoiding relocation and difficult lives" - Mr. Le Van Dung emphasized.

Chu tich UBND tinh Quang Nam nhan manh phai dam bao doi song nguoi dan khi trien khai du an nghin ti. Anh: Nguyen Hoang
The Chairman of the People's Committee of Quang Nam province emphasized that it is necessary to ensure people's lives when implementing the trillion-dollar project. Photo: Nguyen Hoang

For the construction of bridges, it is necessary to ensure both technical and aesthetic aspects; the project must be beautiful, associated with urban development, tourism, etc.

According to Quang Nam leaders, this is a trillion-dollar project using ODA loans, so compensation and site clearance are extremely important. It is necessary to mobilize the entire political system to direct the project resolutely so that it can be implemented on schedule and improve the efficiency of capital use.

Strive to start the project in October 2025, to welcome the 23rd Quang Nam Provincial Party Congress.

The Quang Nam Province Traffic Construction Investment Management Board (investor) said it is racing to complete procedures and is expected to start construction of the first project in September 2025.

Hoàng Bin
RELATED NEWS

Villas in Hoi An open free of charge for people to avoid floods at night

|

Da Nang - The owner of a villa in Hoi An has posted information about opening the door for free to people to avoid flooding.

Discovering land on the red book overlapping with the location of 4 other households in reality

|

The Ministry of Agriculture and Environment responded to the people to resolve the case of discovering that the land granted on the red book matched the location of 4 other families in reality.

Heavy rain in Da Nang, landslides, mother cries for help in the flood

|

Da Nang - Mountain swerves away houses, soldiers cross streams to save people in the midst of floods

Live football Hanoi Police 1-0 Ho Chi Minh City Police: Round 2

|

Live match between Hanoi Police and Ho Chi Minh City Police in round 8 of LPBank V.League 2025-2026, taking place at 7:15 p.m. today (October 27).

Landslide on Dai Ninh Pass causes traffic congestion on National Highway 28B

|

Lam Dong - Rocks and soil on the hill suddenly slid down the road, causing traffic congestion on National Highway 28B.

The key link in tracing the cash flow of the AntEx case related to Shark Binh

|

The exchange is an important link to help trace blockchain cash flow. In the Shark Binh case, the authorities have issued wallet addresses and related cash flow.

Quang Nam struggles to trace the origin of seafood

Hoàng Bin |

Quang Nam is facing many difficulties in tracing the origin of seafood, due to the inability to control output.

Cửa ngõ Tây Bắc TPHCM sắp thoát kẹt xe nhờ 4 dự án nghìn tỉ

MINH QUÂN |

Cao tốc TPHCM - Mộc Bài, mở rộng Quốc lộ 22, đường Trường Chinh, làm đường trên cao trục Trường Chinh - Cộng Hòa giúp giải cứu kẹt xe cửa ngõ Tây Bắc TPHCM.

Dừng triển khai đại dự án nạo vét sông Sào Khê ở Ninh Bình vì thiếu vốn

NGUYỄN TRƯỜNG |

Ninh Bình - Sau 24 năm triển khai xây dựng, dự án nạo vét, xây kè và bảo tồn cảnh quan sông Sào Khê vẫn dở dang, chậm tiến độ, UBND tỉnh đã quyết định dừng triển khai thực hiện dự án để quyết toán đối với dự án này.