Quang Ngai resolves problems for 20,400 billion VND expressway

VIÊN NGUYỄN |

Quang Ngai actively supports the investor of the Quang Ngai - Hoai Nhon expressway, speeds up construction progress, site clearance, and ensures completion on schedule.

Working 24/24

Quang Ngai - Hoai Nhon Expressway is one of 12 component projects of the North - South Expressway that started construction in early 2023. The project has a total investment of more than VND 20,400 billion, with a length of 88km, of which the section through Quang Ngai province is 60.3km long, and the section through Binh Dinh province is 27.7km long. The project is invested by Project Management Board 2 (Ministry of Transport), the construction contractor is led by the Deo Ca Group consortium.

According to the reporter, Quang Ngai is currently in the rainy season, however, contractors are still mobilizing human resources and machinery to speed up the construction of tunnel items. Talking to the reporter, a representative of Deo Ca Group said that up to now, the entire project has mobilized 3,716 personnel along with 1,445 machines and equipment, implementing the construction of "3 shifts and 4 crews" on the entire route. Particularly for the tunnel item, workers and engineers take turns working 24/7.

Quang Ngai dang vao mua mua lu, nen cac nha thau chu yeu tap trung thi cong cac hang muc ham. Anh: Vien Nguyen
Quang Ngai is in the rainy season, so contractors are mainly focusing on constructing tunnels. Photo: Vien Nguyen

Currently, 77/77 bridges are under construction. Of which, the largest bridge on the route, Song Ve Bridge, has completed the installation of girders and bridge deck. Tunnel 1 and Tunnel 2 have basically completed the construction and installation, and are currently installing equipment in the tunnel and completing the operation house. As for Tunnel 3 (3,200m long), the left tunnel has been dug 1,990m, the right tunnel has been dug 2,200m, and the tunnel is expected to be cleared before April 30, 2025.

Speaking to reporters, Mr. Hoang Dinh Thinh - Head of the Northern Command of Tunnel No. 3 (Deo Ca Group) said: "We are increasing personnel and equipment, as well as encouraging engineers and workers to work 24/7 to ensure the set progress."

According to the representative of Deo Ca Group, the plan is that by the end of 2024, the project will complete about 61% of the total contract volume. Completing tunnel No. 1 and tunnel No. 2 (including tunnel lining concrete, roadbed and equipment installed in the tunnel), completing 63/77 bridges, and simultaneously deploying asphalt concrete paving on all 3 packages XL1, XL2 and XL3.

Side by side with investors

Implementing the Prime Minister's Decision on promulgating the Plan to implement the peak emulation period "500 days and nights of emulation to complete 3,000 km of expressways" nationwide, the Provincial People's Committee has issued a Plan to organize the implementation of the peak emulation period "500 days and nights of emulation to complete 3,000 km of expressways" in Quang Ngai province. The province determined that the implementation of this peak emulation period aims to promote the strength of the entire political system, relevant agencies, organizations and individuals in the organization and implementation of construction works, items, site clearance... to focus on the peak to successfully implement the goal of "completing 3,000 km of expressways before December 31, 2025".

Talking to reporters, Mr. Nguyen Dang Vinh - Chairman of Tu Nghia District People's Committee confided that during the construction of Quang Ngai - Hoai Nhon expressway, if the contractor needs coordination with local authorities, the district will always accompany the contractor and the people, focusing on directing the removal of obstacles.

In order for the Quang Ngai - Hoai Nhon expressway project to be implemented most smoothly, the provincial People's Committee leaders requested that departments, branches, districts, and communes where the project passes through be proactive and creative in resolving difficulties and problems related to site clearance and resettlement support...

Speaking to reporters, Mr. Tran Phuoc Hien - Vice Chairman of Quang Ngai Provincial People's Committee expressed that Quang Ngai is very pleased to fulfill its commitment to the Government in ensuring the site, as well as proactively sourcing materials to construct the Quang Ngai - Hoai Nhon expressway, contributing to the project's completion on schedule.

VIÊN NGUYỄN
TIN LIÊN QUAN

The largest bridge on the Quang Ngai - Hoai Nhon highway is about to be completed

|

Song Ve Bridge, the largest bridge on the Quang Ngai - Hoai Nhon expressway, is pouring concrete on the final span, urgently completing important items before the rainy season.

8pm News: Landslide at apartment project, Long Bien district takes action

|

National Assembly passes Trade Union Law (amended); Landslide at apartment project in Long Bien, Hanoi...

Traffic in District 7 and Nha Be will change dramatically with the 500 billion VND bridge

|

HCMC - Tomorrow morning (November 28), the Rach Dia bridge worth over 500 billion VND will officially open to traffic, bringing about a major change in traffic between District 7 and Nha Be district.

Banh mi poisoning in Vung Tau: More than 100 people hospitalized

|

Ba Ria - Vung Tau - More than 100 cases of poisoning have been recorded, the People's Committee of Vung Tau City has directed urgent tracing and investigation to clarify.

Quang Ngai resolves problems for 20,400 billion VND expressway

|

Quang Ngai actively supports the investor of the Quang Ngai - Hoai Nhon expressway, speeds up construction progress, site clearance, and ensures completion on schedule.

National Assembly Delegate: Sugary soft drinks are not a sin

|

According to the National Assembly delegate, sugary soft drinks are not to blame. Sugar is not to blame, only chemical additives are to blame, increasing obesity.

Construction cracked neighbor's house, compensation of 3.5 billion VND still not agreed

|

The owner of 57-59-61 Hang Buom, Hanoi had to sign an agreement to compensate his neighbor 3.5 billion for the subsidence and cracks caused by the construction. However, this neighbor still has not agreed.

The largest bridge on the Quang Ngai - Hoai Nhon highway is about to be completed

VIÊN NGUYỄN |

Song Ve Bridge, the largest bridge on the Quang Ngai - Hoai Nhon expressway, is pouring concrete on the final span, urgently completing important items before the rainy season.

Cao tốc Quảng Ngãi - Hoài Nhơn tăng tốc ngay cả trong dịp lễ

VIÊN NGUYỄN |

Kỳ nghỉ lễ Quốc khánh 2.9 kéo dài 4 ngày. Tuy nhiên, hàng nghìn kỹ sư, công nhân vẫn miệt mài làm việc xuyên lễ trên cao tốc Quảng Ngãi - Hoài Nhơn.

Thi công xuyên Tết trên đại công trường cao tốc Quảng Ngãi - Hoài Nhơn

VIÊN NGUYỄN |

Quảng Ngãi - Dịp Tết Nguyên đán Giáp thìn 2024, hàng trăm kỹ sư, công nhân… vẫn miệt làm việc xuyên Tết trên đại công trường cao tốc Quảng Ngãi - Hoài Nhơn.