Quang Ngai to completely handle the existence of the Quang Ngai - Hoai Nhon expressway before June 30

VIÊN NGUYỄN |

Quang Ngai - Resolutely remove obstacles and completely handle existing problems related to the Quang Ngai - Hoai Nhon Expressway before June 30

According to the Quang Ngai Province Traffic Construction Investment Project Management Board, for the sub-project of compensation, support, and resettlement of the Quang Ngai - Hoai Nhon component project, the section through Quang Ngai province has now completed site clearance and handed over 60.3/60.3 km, reaching 100% of the route length through the province.

Regarding the 3 locations that are still stuck with land clearance in Mo Duc district (1 location) and Duc Pho town (2 locations), up to now, 1/3 of the location (North gate of tunnel No. 1, Duc Pho town) has been completely resolved; the remaining 2 locations include:

Mo Duc District: 1 location at the DH.41B overpass (Km31+480)

Duc Pho Town: 1 location at the DH.46 overpass (Km42+922)

For 7 locations where households obstructed and did not allow construction, 5.7 locations have been resolved; the remaining 2 locations include:

1 location in Nghia Hanh district, at Km8+500 - Km8+700, Mr. Ngo Van Su's household (Hanh Dung commune) again obstructed on May 28 and 29, 2025

1 location in Mo Duc district at Km26+450, on the M1 abutment of DH.38-1 bridge, including 6 plots of land.

Thi cong hang muc ham cao toc Quang Ngai - Hoai Nhon. Anh: Vien Nguyen
Construction of the Quang Ngai - Hoai Nhon expressway tunnel project. Photo: Vien Nguyen

A representative of the Quang Ngai Provincial Traffic Construction Investment Project Management Board requested the Provincial Police to pay attention and support forces to ensure security and order in the area of Km8+500 - Km8+700, according to the proposal of the People's Committee of Nghia Hanh district in Official Dispatch No. 1004/UBND dated May 29, 2025.

On June 24, the Standing Committee of the Quang Ngai Provincial Party Committee held the 20th Provincial Party Executive Committee Conference, term XX, to disseminate the conclusions of the Politburo; assess the implementation of tasks for the first 6 months of the year and deploy tasks for the last 6 months of the year; and at the same time organize questions and answers.

At the conference, Ms. Bui Thi Quynh Van - Secretary of the Quang Ngai Provincial Party Committee - suggested that localities focus on compensation and site clearance for key projects, national urgent projects, and projects with spillover effects. The province must completely complete the existing problems related to the Quang Ngai - Hoai Nhon expressway before June 30.

Quang Ngai - Hoai Nhon Expressway belongs to the North - South Expressway Construction Project in the East, phase 2021 - 2025. The project has a total investment of more than VND 20,400 billion, with a length of 88 km, of which the section passing through Quang Ngai province is 60.3 km long, and the section passing through Binh Dinh province is 27.7 km long. Phase 1 is divided into investment phases with a scale of 4 lanes, designed speed of 80 km/h. The project is invested by Project Management Board 2 (Ministry of Transport), the contractor is the consortium of Deo Ca Group.

The Quang Ngai - Hoai Nhon section is one of the most difficult sections on the North - South expressway with 3 tunnels across the mountain, including a special tunnel on the Km60 route, with a length of 3,200 meters. The construction period of the bridge and road part is 34 months and the tunnel part is 42 months, expected to complete the entire route in the second quarter of 2026.

VIÊN NGUYỄN
TIN LIÊN QUAN

The 900 billion VND key project in Quang Ngai has not made much progress due to land clearance problems

|

Quang Ngai - From 2024 to now, no compensation plan has been approved, causing the Dung Quat - Sa Huynh road project phase IIb to not have much progress.

The 3,500 billion VND project in Quang Ngai lacks land for construction

|

Quang Ngai - The progress of the Hoang Sa - Doc Soi road is delayed due to lack of land. Investors require localities to complete the determination of specific land prices...

Taking his child to do high school graduation exam procedures, father in Binh Dinh died, child seriously injured

|

Binh Dinh - Father drove a motorbike carrying his son to the high school graduation exam preparation point when he suddenly crashed into an electric pole, causing him to die on the spot and seriously injuring his son.

Mobilized with the message to 2k7 students before the graduation exam day of the principal in Nha Trang

|

Khanh Hoa - The principal of a high school in Nha Trang sent to 2k7 students with many emotions from the boat drivers before the special boat trip in 2025.

Hour 9: Unexpected meeting - Part 1

|

Hour 9 No. 160 - The wife waited for her missing husband for 10 years and then took another step. One day, if the husband returns, what will happen to this family?

Unbelievable confusion on the day of completing the procedures for taking the high school graduation exam in Hanoi

|

Hanoi - Some candidates confused the exam scores between My Dinh High School and My Dinh 1 Secondary School in the afternoon to complete the procedures for taking the high school graduation exam.

HCMC will auction land along 5 metro lines, expected to collect 152,000 billion VND

|

Ho Chi Minh City plans to collect about VND152,000 billion from the auction of land along 5 metro lines, including lines 1, 2, 3a, 4 and 5.

Bac Kan Secretary Hoang Duy Chinh becomes a member of the National Assembly Standing Committee

|

Mr. Hoang Duy Chinh - Secretary of the Bac Kan Provincial Party Committee was elected by the National Assembly to hold the position of Member of the National Assembly Standing Committee.

The 900 billion VND key project in Quang Ngai has not made much progress due to land clearance problems

VIÊN NGUYỄN |

Quang Ngai - From 2024 to now, no compensation plan has been approved, causing the Dung Quat - Sa Huynh road project phase IIb to not have much progress.

Dự án đường ven biển ở Quảng Ngãi khiến nhiều cán bộ xã và giám đốc vướng lao lý

VIÊN NGUYỄN |

Quảng Ngãi - Con đường dài 1,6 km bị nâng khống dự toán, gây thất thoát hơn 1 tỉ đồng, khiến nhiều cán bộ xã, giám đốc bị khởi tố.

The 3,500 billion VND project in Quang Ngai lacks land for construction

VIÊN NGUYỄN |

Quang Ngai - The progress of the Hoang Sa - Doc Soi road is delayed due to lack of land. Investors require localities to complete the determination of specific land prices...