The 900 billion VND key project in Quang Ngai has not made much progress due to land clearance problems

VIÊN NGUYỄN |

Quang Ngai - From 2024 to now, no compensation plan has been approved, causing the Dung Quat - Sa Huynh road project phase IIb to not have much progress.

The Dung Quat - Sa Huynh coastal road project, phase IIb, has a total investment of nearly 900 billion VND, the route length is more than 16.2 km, including 4 sections passing through Binh Son district, Quang Ngai city and Mo Duc district. The project is invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Board. The project implementation period is from 2022 to 2025. Although the deadline is approaching, the project is struggling due to land clearance problems.

Talking to reporters of Lao Dong Newspaper, the investor's representative said that up to now, the project has handed over 6.1/8.83 hectares of land, reaching 69%. Of which, Binh Son district has 2.2/3.38 hectares, reaching 65%, Quang Ngai city has 3.9/5.45 hectares, reaching 71.5%. The section through Mo Duc district alone has been handed over 6.935/7.085 km, reaching 98%.

Du an duong ven bien Dung Quat - Sa Huynh doan qua huyen Mo Duc, tinh Quang Ngai. Anh: Vien Nguyen
Dung Quat - Sa Huynh coastal road project, section through Mo Duc district, Quang Ngai province. Photo: Vien Nguyen

The site clearance work is delayed, not ensuring the site handover for construction. From 2024 to now, no compensation plan has been approved, leading to limited site handover for construction and little progress. The section through Quang Ngai city has not been able to hand over more land since 2024, the section through Binh Son district has only handed over an additional 300m.

Faced with this situation, the investor is requesting the People's Committee of Binh Son district to urgently adjust specific land prices to calculate compensation for agricultural land. Approving the plan, handing over 1.9 hectares of land (agricultural land, non-agricultural land other than residential land) no later than June 10, 2025 and 0.36 hectares (residential land + land without documents) no later than June 30, 2025.

Establish procedures according to regulations to enforce land recovery for 8 households and individuals/8 plots of land that do not agree to receive money and hand over the site (the Provincial Land Fund Development Center has completed, supplemented documents and proposals in Submissions from No. 53-60/TTr-TTPTQD dated February 19, 2025) and continue to organize the mobilization of 2 households to receive money and hand over the site; complete no later than June 10, 2025.

For the People's Committee of Quang Ngai City, direct the resolution of problems in the process of appraising compensation plans such as: determining demographics to calculate support, support for stabilizing production... to promptly appraise and approve compensation plans to ensure the required progress.

The Provincial Land Fund Development Center and the Mo Duc District Land Fund Development Center must focus on speeding up the progress of site clearance, urgently completing documents and procedures to submit for appraisal and approval of compensation plans to ensure the area according to the direction of the Chairman of the Provincial People's Committee in Notice No. 148/TB-UBND dated March 25, 2025.

VIÊN NGUYỄN
TIN LIÊN QUAN

3,500 billion VND project in Quang Ngai waiting for... sand

|

The People's Committee of Quang Ngai province has identified 9 sand mining locations to provide for the Hoang Sa - Doc Soi project with a total investment of VND 3,500 billion. However, after 18 months, the sand mines have not been granted an exploitation license, affecting the project's progress.

Two projects worth VND3,700 billion, elevating Quang Ngai City is doing well

|

Quang Ngai - The two projects of the Tra Khuc River downstream dam and Tra Khuc 1 bridge with a total investment of nearly 3,700 billion are making good progress after a difficult time.

Two key projects in Quang Ngai are stalled because determining specific land prices is very slow

|

Quang Ngai - Determining specific land prices is very slow to implement, which is one of the main reasons why two traffic projects worth VND4,194 billion are delayed.

Trong Tan talks about the wealth and the gap in salary between red music singers and young music

|

Young musicians who are "hot" in the market today have a high fee, which can be up to 600-700 million VND/show. Trong Tan said that each music genre will have its own position.

Fire in a house and office for rent in Ho Chi Minh City, rescued 2 people trapped

|

HCMC - A fire broke out on the ground floor of a house on Nguyen Gia Tri Street (Binh Thanh District). Fire police promptly rescued 2 trapped people.

Strong earthquake in Japan, raising concerns about predicting Tsunami disasters

|

A 6.1-magnitude earthquake hit off the Nemuro peninsula, southeast of Japan, on the morning of June 19.

Discovering the preservation of ancient snow sweet soup in the mountainous areas of Lao Cai

|

Lao Cai - Hundreds of years old Shan snow tea trees in Ta Cu Ty commune are being carefully cared for and preserved.

Running around 2 wards just to get 1 certificate of marriage status

|

From marriage registration to car sales, there are cases where people report having to go through 2 wards just to get a certificate of marriage status.

3,500 billion VND project in Quang Ngai waiting for... sand

VIÊN NGUYỄN |

The People's Committee of Quang Ngai province has identified 9 sand mining locations to provide for the Hoang Sa - Doc Soi project with a total investment of VND 3,500 billion. However, after 18 months, the sand mines have not been granted an exploitation license, affecting the project's progress.

Two projects worth VND3,700 billion, elevating Quang Ngai City is doing well

VIÊN NGUYỄN |

Quang Ngai - The two projects of the Tra Khuc River downstream dam and Tra Khuc 1 bridge with a total investment of nearly 3,700 billion are making good progress after a difficult time.

Two key projects in Quang Ngai are stalled because determining specific land prices is very slow

VIÊN NGUYỄN |

Quang Ngai - Determining specific land prices is very slow to implement, which is one of the main reasons why two traffic projects worth VND4,194 billion are delayed.