Temporarily putting aside the September 2 holiday, focusing on the construction of key intersections in the East of Ho Chi Minh City

TÚ QUỲNH |

HCMC - Putting aside the National Day holiday on September 2, hundreds of engineers and workers at the An Phu intersection are still working hard at the construction site to keep up with the schedule.

According to the reporter's records at the construction site of the An Phu intersection project, during the September 2 National Day holiday, the working atmosphere was still urgent. Lining machines, trucks, cranes, workers and engineers are busy working.

Cong nhan miet mai lam viec tren cong truong trong ky nghi le 2.9. Anh: Anh Tu
Workers worked tirelessly at the construction site during the September 2 holiday. Photo: Anh Tu

At the XL10 package (N3 and N4 overpasses) undertaken by the CIENCO8 - Thien Hoang consortium, dozens of workers are divided into two construction teams to work in turns.

Khoang 50 cong nhan chia hai mui thi cong cau vuot N3, N4 (goi XL10). Anh: Anh Tu
About 50 workers divided into two teams to construct the N3, N4 overpass (package XL10). Photo: Anh Tu

According to Mr. Ngo Xuan Tu - Deputy Commander of CIENCO8, the construction site of the package has been basically completed. On this holiday, the number of workers ranges from 30 to 50 people depending on the day, with equipment to focus on construction to make up for the progress.

The N3 bridge has completed the pillars from T5 to T11 and the M2 pier; currently, the foundation of the T1 - T3 pier is under construction, the M1 pier is preparing to pour concrete for the second time for the span between T5 and T6. The N4 bridge has also completed pillars T4 - T10 and pier M2, and is constructing the foundation of pillars T1 - T3, pier M1, reducing the load-bearing piles and retaining walls.

Khong khi khan truong tren cong truong du an nut giao An Phu. Anh: Anh Tu
Urgent atmosphere at the construction site of the An Phu intersection project. Photo: Anh Tu

However, because the XL10 package was only constructed after the HC1 - 01 tunnel was opened in July 2025, the output to date has only reached about 22%. The contractor is committed to increasing human resources and machinery, taking advantage of even the evenings to speed up the construction progress.

Cong nhan va may moc dong loat thi cong tai goi XL12 va XL06, nhieu mui trien khai nhip nhang trong khu vuc rao chan. Anh: Anh Tu
Workers and machinery are simultaneously constructing at packages XL12 and XL06, many of which are deployed smoothly in the barrier area. Photo: Anh Tu

In package XL12 (overpass branch N1.1, N1.3, N2 and tunnel roof HC1‐02), workers and machinery are also operating busily in the fenced areas. All equipment is continuously operated, coordinating with the construction team at many locations on the project.

Cac nhanh cau dang danh hinh thanh. Anh: Anh Tu
The branches of the bridge at the An Phu intersection are gradually taking shape. Photo: Anh Tu

According to Mr. Luong Minh Phuc - Director of the Traffic Department (project investor), the unit is implementing measures to speed up the progress such as relocating technical infrastructure, expanding the construction barrier of 4 parallel HC1‐02 tunnel sections and carrying out overpass items at the same time. The goal is to complete the N2 overpass before the end of 2025, the HC1 - 02 tunnel before the Lunar New Year 2026 and the entire project before June 30, 2026.

To achieve that goal, the Traffic Department proposed that Ho Chi Minh City establish a project coordination working group led by the Department of Construction, with the participation of departments and branches. At the same time, it is recommended to add a Deputy Director of the Board to share the work.

Regarding traffic safety, Cat Lai Traffic Police are requested to support traffic flow during peak hours and organize quick response forces to ensure safety throughout the construction period.

Toan canh nui keo An Phu dang day nhanh tien do. Anh: Anh Tu
Panorama of the An Phu intersection speeding up progress. Photo: Anh Tu

Regarding the site, it is proposed to hand over an additional 22,012 m2 in An Phu urban area before February 28, 2026 and coordinate with electricity and water supply for appropriate relocation.

The investor commits to arranging 3 shifts, 4 teams, day and night to work, and strictly handle contractors who do not meet the schedule through measures such as volume transfer, contract termination, guarantee confiscation and public disclosure of bidding violations.

According to the Traffic Department, with this proactive strategy, the progress can be shortened by about 6 months, when the N2 bridge and the HC1 - 02 tunnel are completed before the Lunar New Year 2026, it will help reduce 80% of traffic congestion at the An Phu intersection. At the same time, a smooth connection road will be opened with the Ho Chi Minh City - Long Thanh - Dau Giay Expressway when completed in December 2026.

TÚ QUỲNH
RELATED NEWS

The most complicated intersection in Ho Chi Minh City is at risk of being delayed, causing congestion in the East

|

HCMC - An Phu intersection is a key project in HCMC that is facing the risk of being behind schedule, causing great pressure on traffic at the eastern gateway of the city.

Chaos at the most modern intersection in Ho Chi Minh City due to the risk of broken progress

|

HCMC - The An Phu intersection project with a total capital of more than VND3,400 billion is still being constructed sluggishly, with the risk of being delayed by up to a year compared to the plan.

HCMC completes 4-storey intersection project to relieve congestion by 2026

|

HCMC - The My Thuy intersection project with 4 floors is expected to help relieve traffic congestion in the East of HCMC, and will be completed in 2026.

The female Major said that she felt the biggest pressure when she was the one who explained the opening ceremony of the A80 parade

|

As one of 13 people participating in the explanation team at the A80 mission, Major Ngoc Vu shared with Lao Dong reporter about the pressures, pride and emotions.

Submarine Kilo, majestic missile patrol boat parade at sea in Khanh Hoa

|

On the morning of September 2, in the Cam Ranh sea area (Khanh Hoa), the Navy chaired a parade of armed forces at sea to celebrate the 80th anniversary of the August Revolution and National Day on September 2.

"K3 Tam Dao con - Quang Tri ancient citadel con" - the soldier who kept his oath to the river during the post-war war

|

During the fierce battle at Quang Tri ancient citadel, the soldiers firmly kept their oath to "must protect every section of the sacred land of the ancient citadel". After the war, they always remember their comrades who fell on the battlefield in the past.

Running more than 1,600km across Vietnam to Hanoi to celebrate National Day 2.9

|

In the midst of the atmosphere towards the 80th anniversary of National Day on September 2, "recent" Nguyen Van Long had a special journey across Vietnam.

Successful excess bowel surgery, saving a child with severe abdominal pain while watching the 2.9 parade

|

On the night of September 1, doctors at Xanh Pon General Hospital successfully treated a child with severe excess intestinal pain while waiting to watch the A80 parade.

The most complicated intersection in Ho Chi Minh City is at risk of being delayed, causing congestion in the East

TÚ QUỲNH |

HCMC - An Phu intersection is a key project in HCMC that is facing the risk of being behind schedule, causing great pressure on traffic at the eastern gateway of the city.

Chaos at the most modern intersection in Ho Chi Minh City due to the risk of broken progress

Tú Quỳnh |

HCMC - The An Phu intersection project with a total capital of more than VND3,400 billion is still being constructed sluggishly, with the risk of being delayed by up to a year compared to the plan.

HCMC completes 4-storey intersection project to relieve congestion by 2026

NHƯ QUỲNH - THÁI BẢO |

HCMC - The My Thuy intersection project with 4 floors is expected to help relieve traffic congestion in the East of HCMC, and will be completed in 2026.