Advance payment of 2.5 billion to compensate for houses cracked due to construction of boat dock

YẾN PHƯƠNG - TẠ QUANG |

Can Tho - The construction unit of Cai Khe Boat Dock project will advance 2.5 billion VND to pay compensation to households affected during the construction process.

Worry about house sinking and cracking before storm season

As a resident whose house was affected by the construction of Cai Khe Boat Dock in Ninh Kieu District, Can Tho City, Mr. The Huu (63 years old) - said that his family and many surrounding households are waiting every day to receive compensation for damages from the insurance company, the construction contractor and the project investor.

Mr. Huu is worried because his house is currently tilted and sunk a lot, but for many months he still hasn't had enough money to repair it, especially in the upcoming storm situation.

“My family was on the list of people to be compensated for damages, and we agreed to pay more than 35 million VND. Although this amount is only enough for partial repairs, we accepted it and tried to repair the damage as it occurred. However, until today (September 19), I still have not received the compensation,” said Mr. Huu.

Nha nguoi dan bi lun, nut do thi cong cong trinh Au thuyen Cai Khe. Anh: Ta Quang
People's houses were severely affected by the construction of Cai Khe fishing port. Photo: Ta Quang

Similarly, Mr. Tran Van Phu Lam (45 years old) whose 4 houses have sunk and cracked due to the construction of Cai Khe Boat Dock also expressed his wish to receive compensation soon, and at the same time, relevant units need to be responsible for the damage to people's houses.

“I hope that relevant units will soon overcome the consequences and compensate appropriately and properly for the affected people during the construction process. In particular, units must be responsible for visiting and encouraging people to repair their houses and overcome the consequences,” Mr. Lam expressed.

Complete processing before October 31

Regarding the above issue, speaking with Lao Dong on September 19, Mr. Nguyen Ngoc Huong - the construction unit of Cai Khe Boat Dock project - informed that while waiting to work with the insurance unit, the construction unit will advance an amount of about 2.5 billion VND to pay compensation; including the cost of supporting affected households in their business and the cost of renting temporary housing for households affected during the construction process.

“The contractor has sent the records of the affected households to the ward People’s Committee and is waiting for the local authorities to sign confirmation, then will proceed to pay compensation in installments. This list has the correct owners and residents, these are the necessary records for the contractor to work with the insurance company later,” said Mr. Huong.

According to Mr. Nguyen Van Tho - Deputy Director of the ODA Project Management Board of Can Tho City, the Cai Khe Boat Dock project has a total of 141 affected households, so far, the unit has compensated about 60 households. Currently, there are still some households that have not agreed on the compensation value, so the unit is continuing to discuss and negotiate.

“We are compiling the records of the households to sign and transfer to the insurance unit to pay the third installment. It is expected that this week the records will be completed and compensation will be made to the households. After that, the unit will continue to complete the records to pay the fourth and fifth installments, trying to complete the process before October 31,” Mr. Tho added.

Anh: Ta Quang
Cai Khe boat dock project has been completed. Photo: Ta Quang

The Cai Khe Boat Lock project is worth about 437 billion VND, a package under the Can Tho City Development Project and enhancing urban resilience, invested by the Can Tho City ODA Project Management Board, and started construction in September 2022.

The project has been completed, especially with the performance of artistic lighting system and water music. However, the project is still facing difficulties in compensation for households whose houses have sunk and cracked during the construction process.

YẾN PHƯƠNG - TẠ QUANG
TIN LIÊN QUAN

The Ministry of Public Security guides vehicle registration after July 1

|

Implementing the policy of arranging and reorganizing administrative units at all levels, the Ministry of Public Security has just issued instructions to local police on vehicle registration.

Russia launches nearly 540 UAVs and missiles, Ukraine suffers unprecedented attack

|

Russia launched a series of fierce airstrikes, simultaneously launching a total of nearly 540 missiles and unmanned aerial vehicles (UAVs) into Ukrainian territory.

Stock market waiting for liquidity boom

|

The stock market may have a few adjustment sessions in the context of still waiting for positive supporting information.

A series of important policies take effect from July 1, 2025

|

Chairmen of commune-level People's Committees with the authority to issue Red books; norms for cars serving general work at the commune level... are some important policies effective from July 1, 2025.

Âu thuyền hoàn thành, nhà dân bị lún nứt chưa được bồi thường

YẾN PHƯƠNG - TẠ QUANG |

Cần Thơ - Công trình Âu thuyền Cái Khế đã hoàn thành nhưng nhiều hộ dân bị lún, nứt do thi công vẫn chưa nhận được bồi thường.

Chiếu sáng nghệ thuật, nhạc nước ở Âu thuyền 437 tỉ đồng

Tạ Quang - Yến Phương |

Cần Thơ – Tối 2.9, đơn vị quản lý Âu thuyền Cái Khế đã vận hành hệ thống chiếu sáng nghệ thuật và nhạc nước làm cho người dân bất ngờ và thích thú.

Bên trong những ngôi nhà chằng chịt vết nứt to, nhỏ ở Cần Thơ

Tạ Quang |

Cần Thơ - Thi công âu thuyền Cái Khế (quận Ninh Kiều) làm sụt, lún, nứt hàng chục căn nhà, khiến cuộc sống của người dân quanh dự án đứng ngồi không yên.