Acceleration on construction site 500kV circuit 3

TRẦN TUẤN |

On the 500kV circuit 3 construction site in Ha Tinh , the contractor is still focusing heavily on speeding up construction to soon complete the project on September 2.

On August 2, Lao Dong Newspaper reporters were present at the construction site of the 500kV circuit 3 project at column 174 in Cam My commune (Cam Xuyen, Ha Tinh), recording dozens of workers of the Construction Joint Stock Company. and Song Da Services is focusing on completing the column installation and porcelain transportation stages to prepare for wire pulling.

Double column No. 174 is nearing completion of erecting the top of the column to pull the rope. Photo: Tran Tuan.
Double column No. 174 is nearing completion of erecting the top of the column to pull the rope. Photo: Tran Tuan.
Construction workers on top of the column. Photo: Tran Tuan.
Construction workers on top of the column. Photo: Tran Tuan.

The workers were divided into two teams, one team hoisting equipment to erect the column, the other team transported porcelain. This is the column location where previously, dozens of officers and workers of Thua Thien Hue Provincial Electricity Company went out to strengthen the erection. When they were about to complete, they withdrew to carry out their tasks in Hue.

The workers are working hard. Photo: Tran Tuan.
The workers are working hard. Photo: Tran Tuan.

Mr. Nguyen Van Ti - technical officer of Song Da Construction and Services Joint Stock Company - said that this position of column No. 174 is a 2-body anchorage column (double column) with a height of 56m, weighing 235 tons. The unit is in the process of erecting the remaining top of the column to proceed with installing the wires.

Workers climbing on electric poles are tightening the screws. Photo: Tran Tuan.
Workers climbing on electric poles are tightening the screws. Photo: Tran Tuan.

"We are still trying to focus on speeding up construction to ensure completion before September 2 according to the Government's direction," Mr. Ti shared.

Crane the metal bars up to build the top of the column. Photo: Tran Tuan.
Crane the metal bars up to build the top of the column. Photo: Tran Tuan.
The electric wire pulled from pole number 173 is being transported to pole number 174. Photo: Tran Tuan.
The electric wire pulled from pole number 173 is being transported to pole number 174. Photo: Tran Tuan.

At column 175 next to it is one of the three highest columns at the 500kV line project through Ha Tinh province with a height of 145m.

Workers of Song Da Construction and Services Joint Stock Company are joining the final steel tie bars to complete the column.

Column number 175 is 145m high. Photo: Tran Tuan.
Column number 175 is 145m high. Photo: Tran Tuan.

Mr. Bui Van Quang - in charge of the construction team of column 175 - said that it is expected that in 3 days he will complete the pairing of the final steel tie bars to proceed with pulling the wires.

“With a high pole like this and a long wire crossing across the surface of Boc Nguyen lake, construction will be very difficult, requiring caution, meticulousness, and certainty. The time to complete pulling the rope up this pole is probably about 10 days," Mr. Quang shared.

Mr. Quang is listening to the radio directing construction workers on high electric poles. Photo: Tran Tuan.
Mr. Quang is listening to the radio directing construction workers on high electric poles. Photo: Tran Tuan.

According to the Central Power Project Management Board, the 500kV 3-circuit line project through Ha Tinh is 141.52km long with 285 column foundations passing through 9 districts and towns. To date, 285 foundation positions have been cast, 249 columns have been erected, and 36 columns are being erected.

TRẦN TUẤN
TIN LIÊN QUAN

“Chạy nước rút” trên công trường đường dây 500kV mạch 3

QUÁCH DU |

Thanh Hóa - Những ngày này, bất chấp nắng mưa, các cán bộ kỹ sư, công nhân ngành điện đang “chạy nước rút” thi công đường dây 500kV mạch 3.

Công nhân ngành điện “đội mưa” thi công đường dây 500kV

QUÁCH DU |

Thanh Hóa - Bất chấp thời tiết mưa, những ngày qua các cán bộ kỹ sư, công nhân ngành điện vẫn miệt mài thi công trên công trường đường dây 500kv mạch 3.

Hoàn thành đường dây 500kV mạch 3 dịp kỷ niệm Quốc khánh

PHẠM ĐÔNG |

Thủ tướng Chính phủ yêu cầu hoàn thành dự án đường dây 500kV mạch 3 chào mừng kỷ niệm 79 năm Cách mạng tháng Tám và Quốc khánh 2.9.

Vụ công trình làm nứt nhà dân ở Hà Nội, chính quyền nói gì?

NHÓM PV |

Theo chính quyền phường Quang Trung, hình ảnh công nhân đang làm việc tại công trình số nhà 19, ngõ 136/98 Tây Sơn là để hút nước phòng dịch sốt xuất huyết.

Triều Tiên cho nổ tung tuyến đường bộ nối với Hàn Quốc

Khánh Minh |

Triều Tiên cho nổ tung các tuyến đường nối với Hàn Quốc vốn từng được coi là biểu tượng của sự hợp tác liên Triều.

Thân tín của bà trùm ma túy Oanh "Hà" được trả công 15 tỉ

Việt Dũng |

Trong số hơn 626kg ma túy mua bán xuyên quốc gia do bà trùm Oanh "Hà" cầm đầu, Nguyễn Văn Nam có mặt hầu hết ở các chuyến hàng, nhận công hậu hĩnh.

Bất cập tiền công đức 2 đền ở Ninh Bình do nguồn thu quá lớn

NGUYỄN TRƯỜNG |

Ninh Bình - Những tồn tại, bất cập trong việc quản lý tiền công đức tại đền Dâu và đền Quán Cháo (thành phố Tam Điệp) là do nguồn thu quá lớn.

Chánh văn phòng hãng luật bị tố đe dọa, xúc phạm phụ nữ

TRÍ MINH |

Một chánh văn phòng hãng luật bị tố cáo có hành vi đe dọa, xúc phạm danh dự, nhân phẩm phụ nữ. Người dân đã trình báo sự việc tới cơ quan công an.

“Chạy nước rút” trên công trường đường dây 500kV mạch 3

QUÁCH DU |

Thanh Hóa - Những ngày này, bất chấp nắng mưa, các cán bộ kỹ sư, công nhân ngành điện đang “chạy nước rút” thi công đường dây 500kV mạch 3.

Công nhân ngành điện “đội mưa” thi công đường dây 500kV

QUÁCH DU |

Thanh Hóa - Bất chấp thời tiết mưa, những ngày qua các cán bộ kỹ sư, công nhân ngành điện vẫn miệt mài thi công trên công trường đường dây 500kv mạch 3.

Hoàn thành đường dây 500kV mạch 3 dịp kỷ niệm Quốc khánh

PHẠM ĐÔNG |

Thủ tướng Chính phủ yêu cầu hoàn thành dự án đường dây 500kV mạch 3 chào mừng kỷ niệm 79 năm Cách mạng tháng Tám và Quốc khánh 2.9.