Busy laying asphalt to complete the road to Phan Thiet airport

Duy Tuấn |

Binh Thuan - About 1km of road is still being paved to complete the Phan Thiet airport road project as planned.

The Phan Thiet airport access road project (phase 2) is 3.63 km long, with a 13.5 m wide road surface and 5 m wide sidewalks on each side.

Tu duong Vo Nguyen Giap nhin vao diem dau cua du an Duong vao san bay Phan Thiet. Anh: Duy Tuan
From Vo Nguyen Giap Street looking at the starting point of the Phan Thiet airport access road project. Photo: Duy Tuan

The project is invested by the Binh Thuan Province Traffic Construction Investment Project Management Board with a total investment of about 117.9 billion VND. The project also includes drainage, tree, lighting and fire-fighting water supply systems.

Xe lu dang thi cong tham nhua duong. Anh: Duy Tuan
Road roller is constructing asphalt pavement. Photo: Duy Tuan

Recorded on the afternoon of December 10 at this project, many groups of workers and machines were busy working at many locations. Near the end of the project, construction teams were spraying and paving a section of about 1.5km of road surface.

Duong vao san bay Phan Thiet hoi thang 11.2023. Anh: Duy Tuan
The road to Phan Thiet airport in November 2023. Photo: Duy Tuan
Den thang 12.2024, duong vao san bay Phan Thiet da duoc tham nhua lang min. Anh: Duy Tuan
By December 2024, the road to Phan Thiet airport will be paved with smooth asphalt. Photo: Duy Tuan

The asphalt concrete section on the right side of the route (from Vo Nguyen Giap to the airport) has been completed, the asphalt section on the left side of the route is in the process of being completed.

Cong nhan thi cong o via he. Anh: Duy Tuan
Construction workers on the sidewalk. Photo: Duy Tuan
Cac cot dien chieu sang, cay xanh da thi cong hoan tat. Anh: Duy Tuan
The lighting poles and trees have been completed. Photo: Duy Tuan

Many other workers are working on paving sidewalks, drainage pipes, etc. According to records, the lighting system, trees, and signs have been completed.

Vi tri gan cuoi duong dang duoc tham nhua. Anh: Duy Tuan
The location near the end of the road is being paved. Photo: Duy Tuan
Cong nhan tham nhua tai cong trinh. Anh: Duy Tuan
Workers laying plastic carpets at the construction site. Photo: Duy Tuan

A supervisor at the construction site said that the asphalt paving of the entire main route will be completed in just a few days.

Gach de thi cong lot via he. Anh: Duy Tuan
Bricks for pavement construction. Photo: Duy Tuan
Cong nhan ti mi do tung vien gach de lat gach via he. Anh: Duy Tuan
Workers meticulously measure each brick to cut and pave the sidewalk. Photo: Duy Tuan

The Phan Thiet airport access road project connecting Phan Thiet International Airport with the Vo Nguyen Giap coastal road, started construction in January 2024 and is scheduled to be completed on December 22, 2024.

Duy Tuấn
TIN LIÊN QUAN

Submit to the National Assembly to build runway number 3 of Long Thanh airport

|

The immediate construction of runway number 3 at Long Thanh airport will meet the needs of phase 1 exploitation.

Investing 1,400 billion VND in road connecting the North of Long Thanh airport

|

Dong Nai Provincial People's Committee is completing procedures to invest in a road worth more than VND1,400 billion connecting the northern area of ​​Long Thanh airport.

Stock market regains excitement

|

The stock market's uptrend will be reinforced if liquidity improves.

Vietnam team wins over Indonesia and issues to look back on

|

The Vietnamese team is almost in the semi-finals of the AFF Cup 2024, but their playing style cannot reassure fans.

Russia withdraws troops and weapons from Syria

|

Russia is withdrawing troops and equipment from the front line in northern Syria but is not abandoning its two main military bases in the country.

What did "Sister" Thuy Hien say when she was eliminated from the show Dap Gio?

|

"Sister" Thuy Hien shared her feelings when she was eliminated at "Sister Who Makes Wave 2024".

Two Russian oil tankers sink, split in two in the Black Sea

|

Two Russian oil tankers with 29 crew members sank on December 15 in the Black Sea.

The concerns of "Elephant King" Dang Nang Long

|

Dak Lak currently has 36 domesticated elephants. If no timely conservation measures are taken, they will face the risk of disappearing forever. This makes the "Elephant King" worried.

Submit to the National Assembly to build runway number 3 of Long Thanh airport

PHẠM ĐÔNG |

The immediate construction of runway number 3 at Long Thanh airport will meet the needs of phase 1 exploitation.

Investing 1,400 billion VND in road connecting the North of Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai Provincial People's Committee is completing procedures to invest in a road worth more than VND1,400 billion connecting the northern area of ​​Long Thanh airport.

Gần 118 tỉ đồng để nhựa hoá, hoàn chỉnh đường vào sân bay Phan Thiết

DUY TUẤN |

Bình Thuận - Tuyến đường dài 3,6 km dẫn từ đường Võ Nguyên Giáp vào sân bay Phan Thiết sẽ được thảm nhựa và triển khai hệ thống chiếu sáng, trồng cây xanh… tạo điều kiện thúc đẩy phát triển kinh tế - xã hội của địa phương.