Submit to the National Assembly to build runway number 3 of Long Thanh airport

PHẠM ĐÔNG |

The immediate construction of runway number 3 at Long Thanh airport will meet the needs of phase 1 exploitation.

On the afternoon of November 12, the National Assembly listened to the submission and report on the review of the adjustment of the investment policy for the Long Thanh International Airport project (Long Thanh airport) in Resolution No. 94/2015/QH13 of the National Assembly.

Minister of Transport Nguyen Van Thang said that at the time of submitting the project investment policy for approval, due to difficulties in determining investment capital, the National Assembly decided that phase 1 of the project would only invest in "runway number 1" in the northern region.

In case Long Thanh airport has to temporarily stop operating due to an incident on "runway 1", Tan Son Nhat airport will play a supporting role for Long Thanh.

Bo truong Bo Giao thong, van tai Nguyen Van Thang trinh bay to trinh ve viec dieu chinh chu truong dau tu du an san bay Long Thanh. Anh: Pham Thang
Minister of Transport Nguyen Van Thang presented a proposal on adjusting the investment policy for the Long Thanh airport project. Photo: Pham Thang

During the implementation of phase 1, the Government realized that the immediate construction of "runway number 3" 400m north of "runway number 1" under investment right in phase 1 would bring many benefits.

According to the plan, Tan Son Nhat airport serves 50 million passengers/year; currently it has served over 41 million passengers/year. It is expected that by 2030, the demand for air transport in Ho Chi Minh City and neighboring provinces will be about 71 million passengers/year.

In case Long Thanh airport's "runway 1" has a problem, flights will have to be transferred to Tan Son Nhat. At that time, Tan Son Nhat will be overloaded, planes will have to wait in the air, causing additional costs and affecting the environment.

Therefore, the immediate construction of "runway number 3" will meet the needs of exploiting phase 1 of Long Thanh airport when "runway number 1" has an incident, without having to switch to Tan Son Nhat.

The immediate construction of "runway number 3" will not interrupt the operation of Long Thanh airport due to infrastructure connections and the impact of dust during construction.

Currently, "runway 3" has been leveled to the design elevation, the investment cost for completion is low, only about 3,304 billion VND and does not exceed the total investment of component project 3 of 99,019 billion VND but still contributes to increasing the capacity and operational efficiency of the port.

Investing in "runway number 3" in phase 1 has many advantages such as being in line with approved planning.

Immediate implementation not only improves investment efficiency but also contributes to perfecting transport infrastructure, reducing logistics costs, enhancing economic competitiveness, and serving the task of ensuring national defense and security.

Regarding the implementation time of phase 1, Minister Nguyen Van Thang said that the preparation and investment progress for "runway number 3" will take about 24 months, and after being approved by the National Assembly, it will be completed by the end of 2026.

Minister Nguyen Van Thang said that the Government proposed that the National Assembly consider adjusting phase 1: Investing in the construction of 2 runways in the North and 1 passenger terminal along with synchronous auxiliary items with a capacity of 25 million passengers/year, 1.2 million tons of cargo/year; completed and put into operation by the end of 2026 at the latest.

PHẠM ĐÔNG
TIN LIÊN QUAN

National Assembly sets GDP growth target of over 7.0% in 2025

|

The National Assembly resolved to increase the gross domestic product (GDP) by about 6.5-7.0% and strive for about 7.0-7.5%; GDP per capita reaches about 4,900 USD.

Government proposes to restart nuclear power project

|

The Prime Minister said the Government has been proposing to competent authorities to restart nuclear power projects and strongly develop offshore wind power.

Large contract worth 7,200 billion VND at Long Thanh airport ahead of schedule

|

Dong Nai - Package 4.6 for the construction of Long Thanh airport runway is 3 months ahead of schedule, according to the Airports Corporation of Vietnam (ACV).

Clarifying responsibility for issuing wrong red books on prison land

|

Lam Dong - Provincial inspectors determined that 4.29 hectares of land of Dai Binh Prison had been illegally granted red books by local authorities to 7 households.

Inadequate treatment of officials and workers

|

National Assembly delegates said that the treatment of officials and employees working at drug rehabilitation facilities is not commensurate with the requirements and tasks of the job.

Nam Dinh has a new Provincial Party Secretary

|

Nam Dinh - Mr. Dang Khanh Toan was mobilized and appointed by the Politburo to hold the position of Secretary of Nam Dinh Provincial Party Committee.

Go Cong sea dike "fluctuates" before monsoon season

|

Tien Giang - Some sections of the Go Cong sea dike are degraded, local authorities in Go Cong Dong district have proposed investing in wave-reducing dikes.

Sad news

|

Mr. Ignatius Do Van Luan, born in 1956, father of comrade Do Thi Yen Phuong, father-in-law of comrade Nguyen Van Quang - reporter of Lao Dong Newspaper working at the Representative Office in the Mekong Delta, passed away at 2:00 p.m. on November 13, 2024, October 13, Giap Thin year. He was 68 years old.

National Assembly sets GDP growth target of over 7.0% in 2025

PHẠM ĐÔNG |

The National Assembly resolved to increase the gross domestic product (GDP) by about 6.5-7.0% and strive for about 7.0-7.5%; GDP per capita reaches about 4,900 USD.

Government proposes to restart nuclear power project

PHẠM ĐÔNG |

The Prime Minister said the Government has been proposing to competent authorities to restart nuclear power projects and strongly develop offshore wind power.

Large contract worth 7,200 billion VND at Long Thanh airport ahead of schedule

HÀ ANH CHIẾN |

Dong Nai - Package 4.6 for the construction of Long Thanh airport runway is 3 months ahead of schedule, according to the Airports Corporation of Vietnam (ACV).