Binh Phuoc 1 Bridge opens to traffic after raising the bridge clearance by 1.25 m

Anh Tú |

HCMC - On December 23, Binh Phuoc 1 Bridge on National Highway 1 was officially opened to traffic after raising the clearance, ensuring road and waterway traffic.

After a period of construction in complicated conditions, the project to lift the clearance of Binh Phuoc 1 bridge on National Highway 1 has been completed and officially opened to traffic. The project contributes to ensuring safety and smooth traffic on roads and waterways and synchronously completing the Saigon River overpass system according to the plan.

Cau Binh Phuoc 1 sau khi hoan thanh nang tinh khong, bao dam thong thuyen tren song Sai Gon. Ảnh: Anh Tu
After completing the clearance, Binh Phuoc 1 Bridge will ensure smooth boat travel on the Saigon River. Photo: Anh Tu

Binh Phuoc 1 Bridge was built before 1975, and was repaired and expanded in 2012, but the clearance clearance has not met the exploitation requirements. In response to that reality, the bridge clearance project was implemented to meet the standards of a level II waterway, with a 50 m wide boat clearance and a minimum height of 7 m, meeting the requirements of inland waterway development.

The project is invested by the Road Traffic Infrastructure Management Center, with a total investment of about 110 billion VND, the total length of the entire route is nearly 760 m, raising the bridge clearance by 1.25 m. The project will start construction in February 2025.

Tinh khong cau Binh Phuoc 1 duoc nang len 7 m, dap ung tieu chuan duong thuy cap II. Ảnh: Anh Tu
The width of Binh Phuoc 1 Bridge has been raised to meet the standards of a level II waterway. Photo: Anh Tu

During the construction process, the project encountered many difficulties in both ensuring waterway traffic and organizing vehicles to travel through the bridge. Raising the stimulation with a large height is a new technical solution, requiring strict calculation, strict control of safety and quality of the project.

One of the major problems is the system of two D450 water supply pipes on the bridge. If relocated at the same time, the risk of affecting the domestic water source of local people is very high. In that situation, relevant units have coordinated to install a temporary water pipeline system across Binh Phuoc 2 bridge to ensure stable water supply, while not interrupting the construction progress.

Cac phuong tien luu thong qua cau Binh Phuoc 1 sang 13.12. Ảnh: Anh Tu
Vehicles traveling through Binh Phuoc 1 Bridge on the morning of December 23. Photo: Anh Tu

In parallel with the construction work, the traffic police force, police and local authorities are mobilized to regulate, divert traffic, limit congestion, and ensure traffic safety in the construction area.

Speaking at the opening ceremony, Mr. Vo Khanh Hung - Deputy Director of the Department of Construction said that the completion of raising the clearance of Binh Phuoc 1 bridge not only removed the bottleneck of waterway traffic but also showed the increasingly synchronous development of the transportation and construction sector, creating more convenience for people in traveling and transporting goods.

Lanh dao So Xay dung TPHCM phat bieu tai buoi le thong xe. Ảnh: Anh Tu
Leaders of the Ho Chi Minh City Department of Construction spoke at the opening ceremony. Photo: Anh Tu

The operation of Binh Phuoc 1 Bridge helps promote the effectiveness of waterway infrastructure, promote the development of the port and inland waterway wharf system in Ho Chi Minh City and Tay Ninh province; thereby contributing to reducing the load on road traffic, enhancing regional connectivity and actively contributing to the economic and social development of the Southern region and the Southern key economic region.

Anh Tú
RELATED NEWS

Many trucks weighing hundreds of tons are mobilized to test the load on Binh Phuoc 1 bridge in Ho Chi Minh City

|

HCMC - On the afternoon of December 17, about 10 trucks, each weighing 25-27 tons, were mobilized to test the load structure of Binh Phuoc 1 Bridge after a period of clearing the clearance.

Mobilizing 14 trucks to check the load capacity of Binh Phuoc 1 bridge in Ho Chi Minh City

|

HCMC - On the afternoon of December 17, 14 heavy trucks were mobilized to test the load capacity of Binh Phuoc 1 Bridge (HCMC), checking the strength of the bridge structure after raising the clearance.

Close-up of Binh Phuoc 1 Bridge in Ho Chi Minh City being raised 1.25 m using modern technology

|

HCMC - Binh Phuoc 1 Bridge is being raised to 1.25 m using synchronous hydraulic shock technology.

Saigon University speaks out when pedagogical students are owed support money

|

HCMC - Pedagogical students of Saigon University reported that they were late in paying living allowances according to Decree 116, affecting their studies.

French lawmaker admits Europe is running low in aid to Ukraine

|

The French lawmaker admitted that Europe no longer has enough financial potential to maintain aid and is gradually losing the decisive voice in negotiations on Ukraine.

Coach Mai Duc Chung asks to stop leading the Vietnam women's team

|

Coach Mai Duc Chung confirmed that he has asked the Vietnam Football Federation to stop leading the Vietnam women's team.

Hanoi reclaims land from 422 households to build a bridge worth VND7,302 billion across the Red River

|

Hanoi plans to reclaim land from 422 households in Thuong Cat ward and Thien Loc commune to build Thuong Cat bridge across the Red River, with a total capital of 7,302 billion VND.

Kim Ma Street opens after narrowing the barrier of the Nhon - Hanoi Railway Station metro project

|

Hanoi - A section of the fence of the Nhon - Hanoi Railway Station metro project on Kim Ma Street has been narrowed, the road has been wide, making it easier for vehicles to travel.

Many trucks weighing hundreds of tons are mobilized to test the load on Binh Phuoc 1 bridge in Ho Chi Minh City

Thái Bảo - Ngọc Ánh |

HCMC - On the afternoon of December 17, about 10 trucks, each weighing 25-27 tons, were mobilized to test the load structure of Binh Phuoc 1 Bridge after a period of clearing the clearance.

Mobilizing 14 trucks to check the load capacity of Binh Phuoc 1 bridge in Ho Chi Minh City

Tâm Tú |

HCMC - On the afternoon of December 17, 14 heavy trucks were mobilized to test the load capacity of Binh Phuoc 1 Bridge (HCMC), checking the strength of the bridge structure after raising the clearance.

Close-up of Binh Phuoc 1 Bridge in Ho Chi Minh City being raised 1.25 m using modern technology

ÁNH TÚ |

HCMC - Binh Phuoc 1 Bridge is being raised to 1.25 m using synchronous hydraulic shock technology.