Promoting the progress of traffic projects in Hanoi

HOÀI ANH |

On April 19, Chairman of Hanoi People's Committee Vu Dai Thang requested to complete site clearance for road 70 and National Highway 21B projects in the second quarter of 2026.

Encountering site clearance

The project to invest in building, upgrading and expanding road 70 (section from Trinh Van Bo to the end of the old Nam Tu Liem district) was approved by the Hanoi People's Committee on March 15, 2024. The project passes through Xuan Phuong ward, Tay Mo ward and Son Dong commune, invested by Tay Mo ward People's Committee, with a total investment of more than 3,377 billion VND.

Regarding site clearance, in Xuan Phuong ward, the recovered area is about 139,208.7m2; land recovery notices have been issued for 338/510 households (reaching 66.3%), striving to be completed in the fourth quarter of 2026. In Tay Mo ward, the recovered area is about 68,879.6m2. For 59 agricultural land households (13,338.7m2), households have received money and handed over the site. The locality sets a target to complete site clearance in the fourth quarter of 2026.

For Son Dong commune, the recovered area is about 21,231.3m2. Among them, the biggest difficulty currently is that the resettlement location for households whose land is recovered has not been approved. Son Dong Commune People's Committee has issued a document proposing the City People's Committee to consider and resolve. The plan to complete site clearance is also set by the locality in the fourth quarter of 2026.

At the National Highway 21B upgrade and expansion project, the section from the beginning of provincial road 427 to Kim Bai town (investor Thanh Oai Commune People's Committee), the current construction volume has reached about 82%, but some sections of the route about 520m long have not been completed due to site clearance.

The project to upgrade and expand National Highway 21B section from Kim Bai town to the Vác intersection (investor: Dan Hoa Commune People's Committee) has a total investment of about 386.2 billion VND, implemented in the period 2021-2026. To date, the project has basically completed the items of foundation, road surface, drainage, green trees, and lighting on the handed-over site; the total construction volume has reached about 95%. However, site clearance work still faces many difficulties.

The project to upgrade and expand National Highway 21B, the section from Thach Bich bridge to the intersection of provincial road 427 and the section from Vac intersection to the end of the old Thanh Oai district (now belonging to Binh Minh, Dan Hoa communes; investor Binh Minh Commune People's Committee) has a total investment of about 382.3 billion VND, implemented in the period 2021-2026. Construction items on the handed-over site have been basically completed. However, site clearance is still slow, which is the main reason why the project has not ensured the schedule according to the plan.

Dự án đầu tư xây dựng nâng cấp mở rộng đường 70. Ảnh: Lê Hải
Project to invest in building and upgrading and expanding road 70. Photo: Le Hai

Key stage deciding the progress of the entire project

Regarding the implementation of the above 2 projects, Chairman of the City People's Committee Vu Dai Thang emphasized the requirement to accelerate the progress of site clearance, considering this as a key stage determining the progress of the entire project.

Regarding the Project to invest in building, upgrading and expanding Road 70, Mr. Vu Dai Thang said that the mechanisms and policies serving compensation, support, and resettlement are basically complete. In case there are still problems, departments and branches are responsible for coordinating to remove them immediately; localities are allowed to flexibly apply the policies issued by the city.

There is no reason to prolong the progress. If site clearance is delayed, it will directly affect public investment disbursement and socio-economic development efficiency" - Chairman of the City People's Committee emphasized.

Chairman of the City People's Committee Vu Dai Thang requested 3 localities Tay Mo, Xuan Phuong, Son Dong to focus highly, mobilize the entire political system to participate, and completely complete site clearance work in the second quarter of 2026, instead of extending it to the end of 2026. For resettlement locations that are still problematic, assign relevant departments and branches of the city to urgently review and complete procedures, and soon arrange to serve the project.

Regarding the National Highway 21B upgrade and expansion project, the Chairman of the City People's Committee requested relevant units to fully apply current mechanisms and policies in the project implementation process, with the highest goal of ensuring the best interests of the people. Along with that, localities need to strengthen mobilization work, create consensus for people to accompany in the process of renovating and upgrading the road.

Mr. Vu Dai Thang also assigned the Department of Construction to closely coordinate with relevant localities to implement the project in a comprehensive manner, in accordance with the urban development orientation of the area.

Regarding progress, city leaders requested units to focus highly on completing site clearance work in June 2026. After that, construction and installation items must be deployed quickly.

HOÀI ANH
RELATED NEWS

8 PM News: Hanoi Police will work with management of combined cars and convenient cars

|

8 PM News on April 19th: Hanoi Police will work with the administrator of the group of combined cars and convenient cars; Whales swim and open their mouths to hunt prey at Mui Ne beach...

Nearly 130,000 students register for the 10th grade entrance exam in Hanoi

|

Nearly 130,000 Hanoi students registered to participate in the 10th grade high school (THPT) entrance exam for the 2026-2027 school year.

Landfill in a residential area in Can Tho stops operating, pollution concerns still exist

|

Can Tho - The landfill in Thoi Nhut 2 residential area has stopped operating, but the situation of illegal dumping of garbage and the risk of pollution still make people uneasy.

US fires naval artillery, pierces Iranian ship engine room

|

The cargo ship Touska flying the Iranian flag was intercepted by the US destroyer USS Spruance while trying to break through the US Navy's blockade.

Police major dies in accident on Noi Bai - Lao Cai expressway

|

The victim who died in the traffic accident on the Noi Bai - Lao Cai expressway is a police major working at Lao Cai Provincial Police.

Forecast of thunderstorms in provinces and cities due to cold air, with heavy rain in some places over 70mm

|

According to the meteorological agency, it is forecast that today, April 20, the North, Thanh Hoa and Nghe An will have rain due to the impact of a weak cold air mass.

Police investigate the case of a woman being beaten repeatedly in the middle of the road

|

Gia Lai - Police investigate the case of a woman being blocked by a man, beaten repeatedly in the middle of the road, causing public outrage.

Need to thoroughly handle pollution at Song Cong waste landfill

|

Thai Nguyen - The pollution situation at Song Cong waste landfill continues while prolonged problems cannot be completely resolved.

8 PM News: Hanoi Police will work with management of combined cars and convenient cars

Nhóm PV |

8 PM News on April 19th: Hanoi Police will work with the administrator of the group of combined cars and convenient cars; Whales swim and open their mouths to hunt prey at Mui Ne beach...

Hà Nội phát thông báo thu hồi đất dự án 925.000 tỉ đồng tới 922 hộ dân

SÓNG HỮU |

Hà Nội - Từ ngày 8.4 đến nay, xã Đại Thanh đã phát thông báo thu hồi đất dự án Khu đô thị thể thao Olympic tới tay 922 hộ dân tại nhiều thôn trên địa bàn.

Hà Nội đối thoại tháo gỡ vướng mắc giải phóng mặt bằng cầu Trần Hưng Đạo

Minh Hạnh |

Hà Nội tổ chức đối thoại với người dân phường Bồ Đề nhằm tháo gỡ vướng mắc giải phóng mặt bằng, đẩy nhanh tiến độ dự án cầu Trần Hưng Đạo.