The progress of the billion-dollar road in Hanoi is being accelerated, to be completed in 2026

SÓNG HỮU |

Hanoi - The Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being accelerated by the contractor, the entire route is expected to be completed in 2026.

The project to build the Ring Road 2.5, Dam Hong - National Highway 1A section (Hanoi) is invested in the form of a BT (build - transfer) contract with a length of 1.6km, with a total investment of more than 1,300 billion VND.

The project started in 2014 and was expected to be completed in 2017 but was behind schedule.

In 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason is due to difficulties in site clearance and extension of BT contract appendices.

Du an xay dung duong Vanh dai 2,5 doan Dam Hong - Quoc lo 1 nhin tu tren cao. Anh: Song Huu
The project to build the Ring Road 2.5 section Dam Hong - National Highway 1A (Hanoi) seen from above. Photo: Song Huu

After 5 years of suspension, at the end of May 2025, with the permission of the Hanoi People's Committee, Hoang Mai - Hanoi Construction Investment Company Limited (project enterprise) held a restart ceremony for the Ring Road 2.5 Construction Project, Dam Hong - National Highway 1A section.

Speaking to Lao Dong Newspaper reporters on September 10, a representative of Hoang Mai Construction Investment Company Limited - Hanoi said that after the project was restarted, the project enterprise had directed the contractor to mobilize many machines and personnel to carry out the construction of project items.

s
The construction unit has deployed the section of the median strip from the intersection of alley 192 Le Trong Tan to Dam Hong. Photo: Song Huu

For package No. 1 (section 1, Km0+00 to Km1+381.7), the contractor has completed the crushed stone aggregate (base) for the section from lane 192 Le Trong Tan to Dam Hong, including both sides of the road.

In parallel with the granting of crushed stone, the contractor is also constructing the sidewalk item in this section.

Also in package 1, the construction of sidewalks from lane 192 Le Trong Tan to bridge L1, including the installation of information pipes, electricity (underground), water... is also being implemented by the contractor.

May moc,
Machinery and workers working at the project site. Photo: Song Huu
s
The project of package 1 of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, is being implemented by the contractor. Photo: Song Huu

For package No. 2 (construction of L3 bridge across Lu river, route Km1+394) has organized the construction of 20 bored piles, all bridge piers and cast all girders (temporarily suspended from 2020 to present).

Currently, the contractor is moving technical infrastructure works around the bridge including electricity, water, information (cable)... according to the approved design to complete the L3 bridge.

After the technical infrastructure works are completed, temporary roads will be built for vehicles to circulate, serving the bridge construction work.

d
The L3 bridge over the Lu river has organized the construction of 20 bored piles, all bridge piers and cast all girders, and has been suspended since 2020. Photo: Song Huu
Cau L3 qua song Lu sap duoc tai thi cong tro lai sau nhieu nam dap chieu. Anh: Song Huu
The L3 bridge over the Lu River is about to be re-constructed after many years of being shelved. Photo: Song Huu

The representative of the project enterprise committed to ensuring safe and quality construction, and is expected to complete the Ring Road 2.5 project, Dam Hong - National Highway 1A section, in time for the opening of the Kim Dong - Giai Phong underpass.

The Ring Road 2.5 construction project is expected to play an important role in improving traffic infrastructure, reducing congestion and connecting urban areas. This is a key traffic project that creates momentum for socio-economic development in the southern area of the city.

SÓNG HỮU
RELATED NEWS

Bridge on the billion-dollar road in Hanoi re-constructed in September

|

Hanoi - L3 bridge over Lu river - a package of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, will resume construction in September after many years of suspension.

The 5-year-old billion-dollar road in Hanoi is under construction again from today

|

Hanoi - The Ring Road section worth over VND1,300 billion in Hoang Mai has been re-constructed after 5 years of stagnation due to land clearance problems and waiting for a BT contract extension.

Tomorrow, Hanoi will restart the billion-dollar road that has been stalled for many years

|

Hanoi - The Ring Road 2.5 project is preparing to re-construct after many years of being shelved due to land clearance problems, waiting for an extension of the BT contract.

Borderless connection, a new step forward in payment infrastructure

|

Cross-border payments are a step forward in digital infrastructure. Vietnam has connected Thailand, Cambodia, Laos, but expanding to many countries still has barriers.

Portrait of a person who has just surpassed Elon Musk, becoming the richest billionaire in the world

|

Larry Ellison became the world's richest billionaire after his fortune surged thanks to Oracle shares setting a record.

Receiving subsidy funds, cadres retire according to Decree 178 to start a business at the age of 53

|

Receiving 1.9 billion VND in retirement subsidies according to Decree 178, Mr. Ha Duc Lieu arranged his work and determined to start a business at the age of 53.

High tide exceeds alert level 3, causing flooding on many roads in Can Tho

|

Can Tho - On the morning of September 11, high tides caused local flooding on many roads, making it difficult for people to travel, live and do business.

Bridge on the billion-dollar road in Hanoi re-constructed in September

HỮU CHÁNH |

Hanoi - L3 bridge over Lu river - a package of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, will resume construction in September after many years of suspension.

The 5-year-old billion-dollar road in Hanoi is under construction again from today

HỮU CHÁNH |

Hanoi - The Ring Road section worth over VND1,300 billion in Hoang Mai has been re-constructed after 5 years of stagnation due to land clearance problems and waiting for a BT contract extension.

Tomorrow, Hanoi will restart the billion-dollar road that has been stalled for many years

HỮU CHÁNH |

Hanoi - The Ring Road 2.5 project is preparing to re-construct after many years of being shelved due to land clearance problems, waiting for an extension of the BT contract.