Tu Lien Bridge project has been constructed on site but is facing major obstacles

HỮU CHÁNH |

Hanoi - The Tu Lien bridge project has been implemented by the contractor in the field, but the site allocated is currently very limited, affecting the construction organization.

According to the report of the Pacific Group contractor consortium, the construction unit has begun to drill and fill piles for the underpass under National Highway 5, the main pillars P37 and P38 of the Tu Lien Bridge project and the road at both ends of the bridge.

The deposit drilling work is expected to be completed in October 2025.

On the South bank in Hong Ha ward, the drilling line has been operating since mid-July. The contractor is making efforts to soon pour the first piles of concrete for P37 tower in the next few weeks.

According to the plan, all bored piles will be completed by the end of 2025. In 2026, contractors will focus on the construction of the main tower, and in early 2027, the steel beams will be cast.

s
Construction site of Tu Lien bridge construction project, mid-July 2025. Photo: Huu Chanh
Nha thau dang trien khai thi cong khoan coc nhoi. Anh: Huu Chanh
The contractor is implementing the bored pile drilling construction. Each drill tip is 65m deep. Photo: Huu Chanh
s
The cluster piles are 2.5m in diameter. Photo: Huu Chanh

The investment project to build Tu Lien Bridge and the road at both ends of the bridge is one of the key traffic projects of Hanoi, however, the project is facing many challenges, especially in site clearance (GPMB) and natural environmental conditions.

The total land acquisition area for the project is 62.53 hectares, involving nearly 560 households and organizations in Hong Ha and Bo De wards.

Although some areas such as before the National Exhibition Center and public land at pillar P38 (about 3,000m2 within the GPMB boundary and 15,000m2 outside the boundary) have been handed over, many other areas have not yet been completed.

At the P37 pillar, only a part of public land (1 600/14,400m2 within the boundary and 1,400/34,000m2 outside the boundary) was handed over. Tay Ho, Hong Ha and Bo De wards are coordinating to speed up site clearance, especially in the P37 pillar area - the project's progress focus.

a
Due to the lack of road connection, the transportation of equipment and materials is all by waterway. Photo: Huu Chanh
s
A concrete station serving the project was built on the river. Photo: Huu Chanh

Engineer Mai Minh Thang - Deputy Commander of the Trung Chinh Company's construction site, said: "Currently, the site clearance is very limited. We hope to soon have an entrance from 310 Nghi Tam alley to the P37 pillar location to facilitate equipment transportation and synchronous deployment of items. Currently, transportation via the river is greatly affected by the water level of the Red River".

On the North bank, outside the P38 pillar area, the remaining areas still have no roads to the construction site. Contractors have to use riverways to transport machinery and materials, increasing costs and construction time.

Here, the construction site of the P38 pillar has been handed over, mainly public land for growing crops. The contractor has land, but the surrounding areas have not been cleared.

s
The lack of access roads makes project implementation difficult. Photo: Huu Chanh

Mr. Vu Trung Thang - Deputy Director of the Executive Board of Phuong Thanh Investment and Construction Joint Stock Company - shared: "Currently, only the P38 pillar area has been handed over. Meanwhile, the road leading to the construction site has not yet been formed, so the transportation of materials must mainly be done through the river, causing many obstacles".

Sharing the same view, Mr. Mai Minh Thang - Construction Commander of Trung Chinh Company said that accessing the project by road is currently very difficult. Contractors are forced to bring machinery and equipment across the waterway, relying heavily on natural factors.

"We hope to hand over the entire site soon to have space to gather equipment, materials and deploy construction teams simultaneously, thereby ensuring the project completion progress by 2027 as planned" - Mr. Thang emphasized.

HỮU CHÁNH
TIN LIÊN QUAN

The first construction phases of the over 20,000 billion VND bridge project in Hanoi

|

Hanoi - Contractors are currently implementing the construction of bored piles for the Tu Lien bridge project. This item is expected to be completed in 2025.

Hanoi informs about the progress of Tu Lien bridge, plan to start construction of 4 bridges across the Red River

|

Hanoi - In addition to focusing on the construction of Tu Lien Bridge, the city is also planning to start construction of 4 bridges across the Red River in 2025.

The Prime Minister requested contractors to make efforts to complete Tu Lien Bridge within 24 months

|

The Prime Minister requested the Project Management Board to promote the highest responsibility, contractors should strive to shorten the construction time of the Tu Lien Bridge project to 24 months.

The beautiful, talented sister of Hoa Minzy and Phuong My Chi

|

Hoa Minzy and Phuong My Chi both have beautiful and talented sisters.

Following the waterway traffic police to inspect ships and boats during the rainy and stormy season

|

Lao Cai - The waterway traffic police force increases patrols and controls owners of wharves, ferry terminals, owners of ships, boats... during the rainy season.

Passenger bus carrying students to give charity gifts overturned in Lam Dong, 5 people injured

|

Lam Dong - Upon receiving the news that the passenger bus carrying students overturned, the PTKV 3 - Bao Lam Command quickly mobilized people to respond in time.

Golden hour actress Lan Phuong separates from her husband Tay

|

Actress Lan Phuong said that she and her husband David Duffy have separated.

Legal support to bring the ashes of 2 Vietnamese twins who were hit by a car in Germany back home

|

The Consulate General of Vietnam in Germany will continue to support legal procedures to bring the ashes of the two Vietnamese twins back to the country according to the correct procedures.

The first construction phases of the over 20,000 billion VND bridge project in Hanoi

HỮU CHÁNH |

Hanoi - Contractors are currently implementing the construction of bored piles for the Tu Lien bridge project. This item is expected to be completed in 2025.

Hanoi informs about the progress of Tu Lien bridge, plan to start construction of 4 bridges across the Red River

HỮU CHÁNH |

Hanoi - In addition to focusing on the construction of Tu Lien Bridge, the city is also planning to start construction of 4 bridges across the Red River in 2025.

The Prime Minister requested contractors to make efforts to complete Tu Lien Bridge within 24 months

ANH HUY |

The Prime Minister requested the Project Management Board to promote the highest responsibility, contractors should strive to shorten the construction time of the Tu Lien Bridge project to 24 months.