The 5-year-old billion-dollar road in Hanoi is under construction again from today

HỮU CHÁNH |

Hanoi - The Ring Road section worth over VND1,300 billion in Hoang Mai has been re-constructed after 5 years of stagnation due to land clearance problems and waiting for a BT contract extension.

On May 27, Hoang Mai - Hanoi Construction Investment Company Limited held a restart ceremony for the investment project to build the Ring Road 2.5 (Dam Hong - National Highway 1A section) in Hoang Mai district, Hanoi.

Informing at the restart ceremony, Mr. Hoang Manh Hien - Deputy Director of Hoang Mai - Hanoi Construction Investment Company Limited (project enterprise) said that the project to build the Ring Road 2.5 section Dam Hong - National Highway 1A is invested in the form of a BT (build - transfer) contract with a length of 1.6km, with a total investment of more than 1,300 billion VND.

The project started in 2014 and was expected to be completed in 2017 but was behind schedule.

In 2020, the project was temporarily suspended when it had only reached about 40% of the workload. The reason is due to difficulties in site clearance and extension of BT contract appendices.

Diem dau du an tai Dam Hong. Anh: Huu Chanh
The starting point of the project is at Dam Hong. Photo: Huu Chanh
Mot so vi tri tren tuyen ngap rac thai. Anh: Huu Chanh
Some locations on the route were flooded with waste. Photo: Huu Chanh

According to the investor's report, up to now, package No. 1 (section 1, Km0+00 to Km1+381.7) has been organized with a volume of about 1,270m/1,381.7m. Since 2020, this package has been suspended due to the extension of the BT contract.

For package No. 2 (construction of L3 bridge across Lu river, route Km1+394) has organized the construction of 20 bored piles, the entire bridge piers and cast the entire girders. The bridge abutment and remaining items of the bridge cannot be constructed due to lack of land and the BT contract has not been extended.

As for package No. 3 (section 3, Km1+405.85 - Km1+600), although the site has been handed over, construction cannot be carried out because the site is still encroached by some households, the adjusted construction drawing design has not been approved, the BT contract has not been extended.

s
The unfinished road makes it difficult for people to travel. Photo: Huu Chanh
Diem cuoi du an ket noi voi ham chui Kim Dong - Giai Phong. Anh: Huu Chanh
The end point of the project connects with the Kim Dong - Giai Phong underpass. Photo: Huu Chanh

By the first quarter of 2025, the Hanoi People's Committee had chaired a meeting with relevant departments and branches to resolve the project's problems.

On 9.5.2025, under the authorization of the Chairman of Hanoi People's Committee, Director of the Management Board of the Investment Project Construction of the Hanoi Transport Project signed the Appendix of BT Contract No. 02/2025/PLHD Investment Project on construction of Ring Road 2.5 (section from pink lagoon to National Highway 1A), Hoang Mai District, Hanoi; Contract extension time of the first quarter/2026.

s
The L3 bridge over the Lu river has been under construction for many years. Photo: Huu Chanh

Regarding the project implementation, Mr. Hoang Manh Hien - Deputy Director of Hoang Mai - Hanoi Construction Investment Company Limited said that after the restart ceremony, the investor and project enterprise will mobilize maximum machinery and construction personnel, speeding up the project's progress.

However, according to Mr. Hien, the project will not be able to be completed in 2025 to synchronously connect with the underpass at the intersection of Ring Road 2.5 - Kim Dong - Giai Phong.

"In addition to construction work, we also have to carry out project adjustment procedures. Investors and project enterprises are committed to the fastest progress and completing the route in the first quarter of 2026" - Mr. Hien said.

When completed, the project will play an important role in transport infrastructure such as reducing congestion, connecting urban areas, and enhancing traffic capacity between inner-city districts, especially the Hoang Mai and Thanh Xuan areas.

HỮU CHÁNH
TIN LIÊN QUAN

Tomorrow, Hanoi will restart the billion-dollar road that has been stalled for many years

|

Hanoi - The Ring Road 2.5 project is preparing to re-construct after many years of being shelved due to land clearance problems, waiting for an extension of the BT contract.

Hanoi reclaims land from more than 700 households to build a bridge worth nearly 20,000 billion VND across 2 major rivers

|

Hanoi - More than 700 households in 3 districts will have their land reclaimed to implement the Tu Lien bridge project across the Red River and Duong River, with an investment capital of nearly 20,000 billion VND.

The bridge project worth nearly 20,000 billion VND is added to the land use plan of Tay Ho district

|

Hanoi - The Tu Lien bridge construction project across the Red River has just been added to the 2025 Land Use Plan of Tay Ho district.

Mr. Do Van Chien presented the Vietnam Science and Technology Innovation Award in 2024

|

On the evening of May 28, Mr. Do Van Chien, Politburo member, Secretary of the Party Central Committee, Secretary of the Party Committee of the Fatherland Front, Central organizations, Chairman of the Vietnam Fatherland Front Committee, Honorary Chairman of the VIFOTEC Foundation attended and presented the Vietnam Science and Technology Innovation Award in 2024.

"Death hole" in Bac Kan continues, experts warn of extreme risk

|

According to the Institute of Geological Sciences and Mineral Resources, to handle the sinkhole like in Bac Kan, careful surveys are needed to avoid possible extreme phenomena.

A woman died unexpectedly at a private clinic

|

Thanh Hoa - The police are investigating and clarifying the case of a woman who died unexpectedly at a private clinic.

National Assembly deputies must be banned from speaking personally and using sarcastic language

|

The National Assembly delegate said that it is necessary to prohibit personal attacks, use of sarcastic, insulting language or distort the content that has been discussed.

Man United lost to Southeast Asia

|

On the evening of May 28, Man United lost to the Southeast Asian All-Stars in an international friendly match.

Tomorrow, Hanoi will restart the billion-dollar road that has been stalled for many years

HỮU CHÁNH |

Hanoi - The Ring Road 2.5 project is preparing to re-construct after many years of being shelved due to land clearance problems, waiting for an extension of the BT contract.

Hanoi reclaims land from more than 700 households to build a bridge worth nearly 20,000 billion VND across 2 major rivers

HỮU CHÁNH |

Hanoi - More than 700 households in 3 districts will have their land reclaimed to implement the Tu Lien bridge project across the Red River and Duong River, with an investment capital of nearly 20,000 billion VND.

The bridge project worth nearly 20,000 billion VND is added to the land use plan of Tay Ho district

HỮU CHÁNH |

Hanoi - The Tu Lien bridge construction project across the Red River has just been added to the 2025 Land Use Plan of Tay Ho district.