Ho Chi Minh City will change the design of the 2km long bridge connecting Thu Duc and District 7

MINH QUÂN |

Ho Chi Minh City is adjusting the plan to build Thu Thiem 4 bridge connecting Thu Duc and District 7, more than 2km long, after Nha Rong - Khanh Hoi Port built an international passenger ship port.

According to the Ho Chi Minh City Department of Transport, this unit has studied 5 options for clearance for Thu Thiem 4 bridge.

Options include: fixed clearance of 10m, 15m, 45m, underpass, or bridge with flexible lifting span from 15m - 45m.

The Ho Chi Minh City Department of Transport proposed a plan to build a bridge with a clearance of 15m for normal operation, but the main span can be raised to 45m when large ships pass by.

In August 2024, the Ho Chi Minh City People's Committee consulted the Ministry of Transport and said it would choose the option of building a bridge with a fixed clearance of 15m, because it believed this option was suitable for the operations of restaurant boats on the Saigon River.

However, after Chairman of the Ho Chi Minh City People's Committee Phan Van Mai worked with relevant units, the city agreed to plan Nha Rong - Khanh Hoi port into an international passenger port.

This forced the city to reconsider the construction plans for Thu Thiem 4 Bridge, to ensure there is enough space for large cruise ships to enter and exit the port area.

Phoi canh du an cang tau khach quoc te Nha Rong - Khanh Hoi. Anh: Cang Sai Gon
Perspective of Nha Rong - Khanh Hoi international passenger port project. Photo: Saigon Port

The Nha Rong - Khanh Hoi international passenger port project is currently being researched and filed by Saigon Port Joint Stock Company to request investment policy from the Ministry of Transport and Ho Chi Minh City People's Committee.

The project area includes the entire area of ​​Zone 3 and part of the K10 bridge connecting to Nguyen Tat Thanh Street, with a total area of ​​over 68,000 m². The port will be developed into a multi-purpose complex, including an international passenger terminal, a marina, a square, a parking lot and logistics areas serving port operations.

The total investment of this port project is expected to be nearly 625 billion VND, and will be implemented from 2025 to 2027. Of which, the investor plans to allocate 30% of its own capital and the rest will be borrowed from banks or mobilized from other sources.

The location of Nha Rong - Khanh Hoi port is very favorable, located right in the city center and opposite the new urban area of ​​Thu Thiem. This is a place that regularly welcomes large international cruise ships with the number of passengers from 300 to nearly 1,100 people per trip.

Domestic passenger and restaurant boat activities on the Saigon River at night also create excitement for the area.

Vi tri xay cau Thu Thiem 4. Anh: Anh Tu
Construction site of Thu Thiem 4 Bridge (HCMC). Photo: Anh Tu

According to a representative of Saigon Port, the construction of Thu Thiem 4 bridge needs to be carefully calculated, because if the clearance of the fixed bridge is only 15m, large ships will not be able to dock, losing the great advantage of Ho Chi Minh City in developing river tourism.

Mr. Phan Xuan Anh - Director of Saigon Boat Tourism Company, emphasized that if Thu Thiem 4 bridge is built at a low height, the Nha Rong - Khanh Hoi port area will become a "dead river", with no large ships entering or leaving.

The Ho Chi Minh City Department of Transport said it has requested the Department of Planning and Architecture to urgently study and update the planning of Nha Rong - Khanh Hoi international passenger port into the dossier adjusting the general planning of Ho Chi Minh City.

This will be the basis for determining suitable clearance for Thu Thiem 4 bridge, both ensuring traffic development and preserving the city's river tourism potential.

Thu Thiem 4 Bridge is expected to have a total length of 2.16km, of which the main bridge is more than 1.6km long, with 6 lanes. The bridge starts from the intersection of Tan Thuan 2 Bridge - Nguyen Van Linh (District 7), connecting with Thu Thiem New Urban Area at the intersection of the North-South axis and Bui Thien Ngo Street.

Ho Chi Minh City aims to start construction of Thu Thiem 4 Bridge on April 30, 2025 and complete it in 2028.

MINH QUÂN
RELATED NEWS

aggressive crazy buffalo chases and attacks 7 people in Nghe An

|

Nghe An - In just 3 days, a wild buffalo appeared in Binh Chuan commune and chased and attacked 7 people.

20h News: More than 130 hectares of land recovered to widen the road connecting Long Thanh airport

|

20h News on November 1: Reclaim more than 130 hectares of land in 3 communes to widen road near Long Thanh airport; Search Truong Ngoc Anh villa, police seize iPad and 2 important documents;...

Teachers and soldiers busy cleaning schools in Da Nang after floods

|

Da Nang - Military forces, militia and teachers in Dai Loc commune urgently cleaned up and overcame the damage after a long period of deep flooding.

Hanoi shows another deep hole on Tran Hung Dao street

|

Hanoi - A deep hole appeared on Tran Hung Dao Street, causing many people to worry because this is an area with a lot of people and vehicles passing through.

The stock market is still under pressure from large-cap stocks

|

Financial sector stocks including banks and securities are being sold strongly by foreign investors.

The 20-year-old bottleneck at the Northwest gateway of Ho Chi Minh City waiting to widen the road and build an underpass

|

HCMC - For 20 years, the Truong Chinh - Tan Ky Tan Quy intersection has been a bottleneck that has caused traffic congestion at the Northwest gateway, but projects to expand roads and build underpasses have been delayed.

Ward union uses fishing baskets to transport food to people in flooded areas

|

Lam Dong - Ham Thang Ward Trade Union uses fishing baskets to bring food and drinking water to support people in the area along Cai River.

5 phương án xây cầu dài hơn 2km nối Thủ Đức với Quận 7

MINH QUÂN |

Trong 5 phương án xây cầu Thủ Thiêm 4 dài hơn 2km, bắc qua sông Sài Gòn (nối TP Thủ Đức và Quận 7), TPHCM chọn thiết kế tĩnh không cố định 15m.

TPHCM muốn xây cầu Thủ Thiêm 4 với tĩnh không cố định 15m

MINH QUÂN |

TPHCM - Cầu Thủ Thiêm 4 dài hơn 2km, 6 làn xe, tĩnh không cố định 15m, không thể nâng mở nhịp chính lên 45m như đề xuất trước đó.

Hình ảnh vị trí dự kiến xây cầu Thủ Thiêm 4 nối TP Thủ Đức và Quận 7

Anh Tú - Ngọc Ánh |

Theo Sở GTVT TPHCM, Cầu Thủ Thiêm 4 (bắc qua sông Sài Gòn, nối TP Thủ Đức và Quận 7) được xác định là một trong các công trình hạ tầng giao thông quan trọng, cần ưu tiên đầu tư để từng bước hoàn chỉnh đồng bộ hệ thống hạ tầng kỹ thuật chung toàn khu vực.