HCMC speeds up the completion of a series of traffic projects on the occasion of April 30

MINH QUÂN |

To celebrate the 50th anniversary of the Liberation of the South and National Reunification (April 30, 1975 - April 30, 2025), Ho Chi Minh City accelerates the completion of a series of key transport projects: Tan Son Nhat T3 Station, Tran Quoc Hoan - Cong Hoa connecting road, Hoang Hoa Tham expansion, Duong Quang Ham, An Phu underpass...

Completing a series of projects to reduce the load on Tan Son Nhat

In mid-March, the construction atmosphere at the T3 terminal at Tan Son Nhat airport became more urgent than ever. Workers worked day and night to complete the final items.

Mr. Mai Van Thanh (45 years old), a worker directly involved in the project, shared: "This is a key project of the city, everyone is trying their best to put it into operation on the occasion of April 30".

The T3 terminal project is invested by Vietnam Airports Corporation (ACV), with a total capital of more than VND 10,986 billion. The station is built on an area of 112,500m2, including 1 basement and 4 upper floors, with a capacity to serve 20 million passengers per year. Started in August 2023, the project's progress has reached about 95%.

According to the T3 Terminal Project Management Board, the architectural part will be completed in March, while technical systems such as electricity, air conditioning, fire prevention and fighting, elevators, luggage handling belts, etc. are in the completion stage.The overpass system, aircraft parking lot and external infrastructure are ready to be put into operation.To ensure the inauguration on April 30, Mr. Le Khac Hong - Head of the T3 Terminal Project Management Board - said that more than 2,500 engineers and workers along with hundreds of equipment and machines have been mobilized, working throughout the week to speed up the progress and complete the items according to plan.


Outside, the Tran Quoc Hoan - Cong Hoa connecting road project, an important traffic route that directly connects Terminal T3 and reduces traffic pressure in the airport area, will also be completed before April 20. The project is about 4 km long, with a total investment of more than VND 4,800 billion, including the main road, overpass and underpass.

Currently, the 1.25km section from the underpass of Phan Thuc Duyen Street to Hoang Hoa Tham Street has been completed and put into operation. In addition, the four-lane overpass in front of terminal T3 has been completed, ready to connect to the terminal. At the same time, Hoang Hoa Tham Street (783m long, with an investment capital of 403 billion VND) will also be open to traffic before April 30.

An Phu intersection underpass is about to open to traffic

In the eastern area of Ho Chi Minh City, the An Phu intersection project (Thu Duc City) with a total capital of more than VND 3,400 billion is entering the final stage.

According to Mr. Luong Minh Phuc - Director of the Ho Chi Minh City Traffic Construction Investment Project Management Board, after more than 2 years of construction, the project has reached about 65% of the progress. Of which, the HC1 underpass branch (from Ho Chi Minh City - Long Thanh - Dau Giay Expressway to Mai Chi Tho Avenue) has reached 80% of the volume. The remaining important items such as pumping stations and closed tunnels are being urgently deployed to ensure traffic opening before April 30. It is expected that the entire An Phu intersection project will be completed by the end of 2025.

Another important project is the expansion of Duong Quang Ham Street (Go Vap District), expected to open to traffic on April 30. Recently, construction has encountered obstacles due to land clearance and electric poles. However, according to Mr. Luong Minh Phuc, the electric poles along the route will be relocated and undergrounded before the end of March. When the site is clear, the construction unit will speed up the progress to complete the project in time.

In the southern area of Ho Chi Minh City, the parallel road of National Highway 50 (Binh Chanh District) is being accelerated to open to traffic on April 30. Previously, the project encountered difficulties in site clearance, causing delays in progress. This is a item of the National Highway 50 expansion project with a total investment of more than 1,500 billion VND. Currently, the parallel section has been basically completed, while the existing National Highway 50 expansion has reached about 30%. It is expected that the entire route will be completed by the end of 2025.

MINH QUÂN
TIN LIÊN QUAN

Traffic project stuck because natural forest has not been cleared

|

Quang Tri - The natural forest area that the road passes through has not been cleared, causing the road project to be stuck and behind schedule.

20h News: List of key traffic projects in Ho Chi Minh City that have been stalled

|

20:00 News on September 28: List of key traffic projects in Ho Chi Minh City that have been stalled; Hanoi to build a 45m wide road, to be completed in 2026;...

Land acquisition issues cause a series of key traffic projects in Ho Chi Minh City to stagnate

|

A series of key traffic projects in Ho Chi Minh City such as the Tran Quoc Hoan - Cong Hoa connecting road, An Phu intersection, My Thuy intersection, and Duong Quang Ham road expansion are facing great difficulties in site clearance, causing obstacles and prolonging construction progress.

Announcing the list of Secretaries of 126 communes and wards of Hanoi when implementing 2-level government

|

Hanoi - Below is a list of Secretaries of communes and wards of Hanoi when implementing 2-level government.

70 central-level cadres, Standing Committee of Khanh Hoa Provincial Party Committee, Ninh Thuan retire from the regime

|

There will be 70 comrades of the Central level and the Standing Committee of Khanh Hoa Provincial Party Committee, Ninh Thuan managing the regime leave from July 1, 2025.

Ninh Binh Provincial Police has 8 deputy directors after the merger

|

Ninh Binh - The new Ninh Binh Provincial Police after merging with Ha Nam and Nam Dinh provinces has 1 director and 8 deputy directors.

Bich Phuong's rumored boyfriend is the one behind the hit song that helped ACB president cause a storm

|

Tang Duy Tan is a young musician and singer who owns many hits, including the famous hit "Lonely on the sofa" that caused a storm when the Chairman of ACB Bank sang in the rain.

Israel declares to kill Hamas co-founder

|

The Israeli military has confirmed it has eliminated one of Hamas' remaining top military leaders in the Gaza Strip.

Traffic project stuck because natural forest has not been cleared

HƯNG THƠ |

Quang Tri - The natural forest area that the road passes through has not been cleared, causing the road project to be stuck and behind schedule.

20h News: List of key traffic projects in Ho Chi Minh City that have been stalled

NHÓM PV |

20:00 News on September 28: List of key traffic projects in Ho Chi Minh City that have been stalled; Hanoi to build a 45m wide road, to be completed in 2026;...

Land acquisition issues cause a series of key traffic projects in Ho Chi Minh City to stagnate

MINH QUÂN |

A series of key traffic projects in Ho Chi Minh City such as the Tran Quoc Hoan - Cong Hoa connecting road, An Phu intersection, My Thuy intersection, and Duong Quang Ham road expansion are facing great difficulties in site clearance, causing obstacles and prolonging construction progress.