Traffic project stuck because natural forest has not been cleared

HƯNG THƠ |

Quang Tri - The natural forest area that the road passes through has not been cleared, causing the road project to be stuck and behind schedule.

On November 18, the Department of Transport of Quang Tri province confirmed that the project connecting the East branch of Ho Chi Minh road with the West branch of Ho Chi Minh road still has 4.5km of land that has not been handed over, causing difficulties for the project.

This road project will be implemented from 2022, with a length of 15km. To date, more than 10.5km has been basically completed, the remaining 4.5km has not been handed over due to problems related to the auction and liquidation of natural forests.

According to the Ben Hai River Basin Protection Forest Management Board, the 4.5km section encountered problems passing through the natural forest area managed by the unit. To implement the project, the locality converted the natural forest area and was approved by the Prime Minister on November 24, 2023.

After that, the forest owner organized an auction for the converted forest area. However, during the first auction, there were no customers participating. On November 4, 2024, the forest owner asked for permission to re-auction and is currently completing the procedures to implement it.

Dien tich rung tu nhien chua thanh ly duoc vi chua co khach hang tham gia dau gia. Anh: H.Tho.
The area of ​​natural forest has not been liquidated because there are no customers participating in the auction. Photo: H. Tho.

“The forest area put up for auction is 4.5km long along the road through the forest, so units are not interested in participating in the auction. If the second auction is not successful, it will be reported to the People's Committee of Quang Tri province” – the leader of the Ben Hai River Basin Protection Forest Management Board informed.

While the auction of forest clearance is still unclear, the above mentioned road project is stuck, causing the project to be behind schedule.

Mr. Tran Huu Hung - Director of the Department of Transport of Quang Tri province said that the capital plan of the project has been arranged from 2020 to 2024 is more than 171 billion VND, of which in 2024 more than 20 billion VND is arranged and so far nearly 6 billion VND has been disbursed.

Due to difficulties in site clearance through natural forest areas, the Department of Transport proposed that the People's Committee of Quang Tri province consider transferring 5 billion VND that could not be disbursed in 2024 to another project or adjust it to be implemented in 2025. The project's capital plan for 2024 after adjustment is more than 15 billion VND. The remaining capital that needs to be arranged in 2025 is 63 billion VND to complete the remaining items of the project to ensure compliance with the approved investment target.

HƯNG THƠ
RELATED NEWS

Supporting two grandmothers and grandchildren in Lai Chau to cross forests and escape streams to safe places

|

Lai Chau - A grandmother and grandchild living 3km from the central area on a forest road have been taken to a safe place by functional forces.

A nearly 3-year-old boy in critical condition after studying at an intervention facility

|

Thanh Hoa - After a class at an intervention facility, a nearly 3-year-old boy was found to have many serious injuries and had to be hospitalized in critical condition.

2026 World Cup Final: The battle of wits begins with personnel choices

|

Before the 2026 World Cup final, Luis de la Fuente and Lionel Scaloni both faced difficult personnel problems.

After organizing the civil servant exam, Cao Bang Department of Education and Training received instructions to reduce 596 staff positions

|

Cao Bang - The Department of Education and Training has a document requesting to temporarily suspend the recruitment of public employees in the Education sector due to a reduction of nearly 600 staff positions.

Binh Duong MB is pointed out for many shortcomings from lending to bad debt handling

|

The State Bank Inspectorate pointed out many shortcomings at MB Binh Duong in lending, post-loan monitoring, bad debt handling and foreign exchange operations.

Cao Bằng chuyển đổi hơn 18ha rừng tự nhiên để làm thủy điện

Nhóm PV |

Cao Bằng - Theo kế hoạch, nhà máy thủy điện Bảo Lạc A dự kiến khởi công trong quý III.2024. Dự án này cần chuyển đổi 18,08ha rừng tự nhiên.

Không chuyển đổi 4.700ha rừng tự nhiên thành vùng tưới

THANH TUẤN |

Bộ Nông nghiệp và Phát triển nông thôn thống nhất với tỉnh Gia Lai giữ lại hơn 4.700 ha rừng tự nhiên ở Ia Mơr để phát triển, bảo vệ biên giới.

Xử phạt đơn vị thi công đường giao thông rồi san ủi luôn rừng tự nhiên

HƯNG THƠ |

Liên quan đến vụ việc đơn vị thi công đường giao thông rồi san ủi sang một diện tích đất rừng tự nhiên, cơ quan chức năng tỉnh Quảng Trị đã tiến hành xử phạt.