Land acquisition issues cause a series of key traffic projects in Ho Chi Minh City to stagnate

MINH QUÂN |

A series of key traffic projects in Ho Chi Minh City such as the Tran Quoc Hoan - Cong Hoa connecting road, An Phu intersection, My Thuy intersection, and Duong Quang Ham road expansion are facing great difficulties in site clearance, causing obstacles and prolonging construction progress.

Site obstructions hinder construction progress

Construction started at the end of 2022, the Tran Quoc Hoan - Cong Hoa connecting road project (Tan Binh district) is more than 4km long, with a total investment of more than 4,800 billion VND. Currently, the entire project has completed about 78% of the volume. Some important items such as the underpass and the road system from the beginning of the route to Thang Long Street, the overpass in front of T3 station and the road in the middle of the route have progressed from 65% to 98%. However, package No. 13 (the last section of the route adjacent to Truong Chinh Street) is still stalled due to the unresolved land issue.

According to the investor, Tan Binh District People's Committee needs to hand over land to 67 households soon, Military Region 7 needs to hand over the fence of Textile Factory 7. If not handled promptly, the possibility of completing the project by the end of 2024 will face many difficulties.

The An Phu intersection in Thu Duc City is also facing a similar situation. With a total investment of more than 3,400 billion VND, this project has only reached about 55% of its volume after nearly two years of construction.

The project was originally planned to be completed on April 30, 2025, but the investor announced a delay to the end of 2025. The biggest problem causing the project to be delayed is the Luong Dinh Cua starting area, where more than 22,000 square meters of land have not been cleared, belonging to the An Phu urban development project.

Also in Thu Duc City, the My Thuy intersection project started in 2016 with an initial total investment of VND1,998 billion, then increased to more than VND3,600 billion (due to increased land acquisition capital) in 2022. Thu Duc City is responsible for compensating 195 cases since 2016, but has not yet been processed, greatly affecting the project's progress.

Duong Quang Ham Street in Go Vap District, which started construction in April 2020, to widen the road from 6m to 32m for 6 lanes of traffic, was suspended after 4 months of construction due to land acquisition issues. There are still 45 unresolved cases, including 9 cases belonging to military units, making it difficult to complete the project by the end of this year.

Du an nut giao My Thuy (TP Thu Duc) dang do do vuong mat bang.  Anh: Minh Quan
My Thuy intersection project (Thu Duc City) is unfinished due to land acquisition problems. Photo: Minh Quan

Putting people at the center

Regarding the reason for the delay in handing over the site, a representative of the Thu Duc City People's Committee said that many projects were approved after 3-4 years when land prices had increased, causing the compensation level to no longer be suitable and forced to be adjusted.

In particular, land prices in Thu Duc City have increased sharply after the merger of three districts, making compensation more difficult. In addition, continuous changes to the Land Law have also prolonged the process of implementing projects, from determining land types, land prices, to implementation procedures.

Mr. Luong Minh Phuc - Director of the Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City - said that the delay in many projects in Ho Chi Minh City mainly comes from the issue of site clearance. Some projects have had to wait from 3-10 years after the first phase of construction, such as Long Kieng, Phuoc Long, Rach Dia, Vam Sat 2, Ong Nhieu and Tang Long bridges.

To overcome the delay, Ho Chi Minh City is implementing a series of synchronous solutions. The top priority is to listen to the people, put them at the center and adjust compensation prices to approach market prices. Ho Chi Minh City has established a Steering Committee for key projects and three specialized working groups to speed up the progress of major projects.

MINH QUÂN
RELATED NEWS

Promoting the strength of national great unity - the foundation and important driving force for successfully implementing the country's development goals in the new era

|

On the morning of January 21, the 14th National Congress of the Party continued with a discussion session in the hall on the Congress documents. On behalf of the Party Committee of the Fatherland Front, central mass organizations, Comrade Ha Thi Nga, Member of the Party Central Committee, Standing Deputy Secretary of the Party Committee of the Fatherland Front, central mass organizations, Vice Chairman - Secretary General of the Central Committee of the Vietnam Fatherland Front, presented a paper on the issue "Promoting the strength of national unity - an important foundation and driving force to successfully implement the country's development goals in the new era".

Eligible number of National Assembly deputies for the 16th term, top priority for quality

|

The Vice Chairman of the National Assembly emphasized the careful preparation to successfully organize the election of National Assembly deputies of the XVI term and People's Council deputies at all levels.

Dinh Bac U23 Vietnam and the sensational interaction with a "Hello Brother"

|

Striker Nguyen Dinh Bac was so excited that he lost sleep when a singer called an idol actively arranged to meet him on the occasion of the 2026 Lunar New Year.

Hanoi general rehearsal for fireworks display at My Dinh Stadium tonight

|

Hanoi - On the evening of January 21, at My Dinh National Stadium, a general rehearsal of the fireworks program to celebrate the success of the 14th Party Congress took place.

Finance industry: Consolidating the macro foundation, creating room for rapid and sustainable growth

|

On the occasion of the 14th National Party Congress, Member of the Party Central Committee, Secretary of the Party Committee, Minister of Finance Nguyen Van Thang had an exchange with the press about the achievements of the Finance sector in the past term and the tasks and solutions of the sector in the coming period.

Suspension and recall of On1 Huong Fresh Sakura hand sanitizer shipment for violation

|

Suspending circulation, recall and destruction nationwide of the batch of On1 Huong Fresh Sakura hand sanitizer due to containing ingredients not disclosed according to regulations.

Hon Vong Phu faces debate, functional sectors get involved

|

Thanh Hoa - After public opinion paid attention to reinforcing the Hon Vong Phu relic, functional agencies intervened to inspect and clarify information.

The 14th Party Congress enters its third working day

|

Today (January 21), at the National Convention Center, the 14th National Party Congress entered its third working day.

Solution for the last 0.15% of the highway area through Quang Binh

CÔNG SÁNG |

Quang Binh - Localities are developing plans to enforce the handover of the last meters of highway land to the Project Management Boards.

Dong Nai sets date for handing over Bien Hoa - Vung Tau expressway site

HÀ ANH CHIẾN |

On September 25, information from the People's Committee of Dong Nai province said that by October 15, the province will basically hand over the land for the Bien Hoa - Vung Tau expressway.

6-lane road at the gateway to Ho Chi Minh City is at risk of being delayed due to land congestion

MINH QUÂN |

HCMC – The project to upgrade and expand Duong Quang Ham Street (Go Vap District) is facing the risk of not being completed on schedule due to land acquisition problems.