Land acquisition issues cause a series of key traffic projects in Ho Chi Minh City to stagnate

MINH QUÂN |

A series of key traffic projects in Ho Chi Minh City such as the Tran Quoc Hoan - Cong Hoa connecting road, An Phu intersection, My Thuy intersection, and Duong Quang Ham road expansion are facing great difficulties in site clearance, causing obstacles and prolonging construction progress.

Site obstructions hinder construction progress

Construction started at the end of 2022, the Tran Quoc Hoan - Cong Hoa connecting road project (Tan Binh district) is more than 4km long, with a total investment of more than 4,800 billion VND. Currently, the entire project has completed about 78% of the volume. Some important items such as the underpass and the road system from the beginning of the route to Thang Long Street, the overpass in front of T3 station and the road in the middle of the route have progressed from 65% to 98%. However, package No. 13 (the last section of the route adjacent to Truong Chinh Street) is still stalled due to the unresolved land issue.

According to the investor, Tan Binh District People's Committee needs to hand over land to 67 households soon, Military Region 7 needs to hand over the fence of Textile Factory 7. If not handled promptly, the possibility of completing the project by the end of 2024 will face many difficulties.

The An Phu intersection in Thu Duc City is also facing a similar situation. With a total investment of more than 3,400 billion VND, this project has only reached about 55% of its volume after nearly two years of construction.

The project was originally planned to be completed on April 30, 2025, but the investor announced a delay to the end of 2025. The biggest problem causing the project to be delayed is the Luong Dinh Cua starting area, where more than 22,000 square meters of land have not been cleared, belonging to the An Phu urban development project.

Also in Thu Duc City, the My Thuy intersection project started in 2016 with an initial total investment of VND1,998 billion, then increased to more than VND3,600 billion (due to increased land acquisition capital) in 2022. Thu Duc City is responsible for compensating 195 cases since 2016, but has not yet been processed, greatly affecting the project's progress.

Duong Quang Ham Street in Go Vap District, which started construction in April 2020, to widen the road from 6m to 32m for 6 lanes of traffic, was suspended after 4 months of construction due to land acquisition issues. There are still 45 unresolved cases, including 9 cases belonging to military units, making it difficult to complete the project by the end of this year.

Du an nut giao My Thuy (TP Thu Duc) dang do do vuong mat bang.  Anh: Minh Quan
My Thuy intersection project (Thu Duc City) is unfinished due to land acquisition problems. Photo: Minh Quan

Putting people at the center

Regarding the reason for the delay in handing over the site, a representative of the Thu Duc City People's Committee said that many projects were approved after 3-4 years when land prices had increased, causing the compensation level to no longer be suitable and forced to be adjusted.

In particular, land prices in Thu Duc City have increased sharply after the merger of three districts, making compensation more difficult. In addition, continuous changes to the Land Law have also prolonged the process of implementing projects, from determining land types, land prices, to implementation procedures.

Mr. Luong Minh Phuc - Director of the Management Board of Investment and Construction of Traffic Works in Ho Chi Minh City - said that the delay in many projects in Ho Chi Minh City mainly comes from the issue of site clearance. Some projects have had to wait from 3-10 years after the first phase of construction, such as Long Kieng, Phuoc Long, Rach Dia, Vam Sat 2, Ong Nhieu and Tang Long bridges.

To overcome the delay, Ho Chi Minh City is implementing a series of synchronous solutions. The top priority is to listen to the people, put them at the center and adjust compensation prices to approach market prices. Ho Chi Minh City has established a Steering Committee for key projects and three specialized working groups to speed up the progress of major projects.

MINH QUÂN
RELATED NEWS

Chain collision in Hanoi kills one person

|

Hanoi - One person died, many vehicles were damaged after a chain traffic accident on Nga Tu Vong overpass, morning of January 10.

Hai Phong authorities intervene after reflecting strange odor in domestic water

|

Hai Phong - Many households in Kien Minh commune reflect on social networks about the situation of domestic water showing signs of not ensuring quality...

It's a bit of a bit of a bit of a bit of a bit of a bit.

Tao Quan stops production, costume designer sends wishes

|

Meritorious Artist, designer Duc Hung - who has been attached to the program's costumes for many years, shared a story about Tao Quan before the information of temporary suspension.

Personnel transfer and appointment in Lang Son, Lai Chau, Hung Yen, Ha Tinh

|

From January 5-9, in Lang Son, Lai Chau, Hung Yen, Ha Tinh, Hue... decisions on election, transfer, appointment, and appointment of personnel have been implemented.

12 outstanding highlights of Ho Chi Minh City in 2025

|

Ho Chi Minh City - Ho Chi Minh City People's Committee has just announced 12 outstanding milestones reflecting the comprehensive and breakthrough development picture of the city in 2025.

Bollywood film crew filming for 3 days in Ha Long Bay

|

Quang Ninh - The Bollywood film crew of India will film for 3 days in Ha Long Bay and Tuan Chau, Quang Ninh province for the movie "Silaa".

From today, January 10, end the first cold spell in winter

|

According to the meteorological agency, the widespread severe cold in the North will end from today, January 10. However, the temperature in the midlands and mountainous areas is still low.

Workers expect strict handling of profiteering from social housing

|

The prosecution of the case of profiteering from social housing policies in Thai Nguyen not only tightens management but also increases housing ownership opportunities for workers.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Solution for the last 0.15% of the highway area through Quang Binh

CÔNG SÁNG |

Quang Binh - Localities are developing plans to enforce the handover of the last meters of highway land to the Project Management Boards.

Dong Nai sets date for handing over Bien Hoa - Vung Tau expressway site

HÀ ANH CHIẾN |

On September 25, information from the People's Committee of Dong Nai province said that by October 15, the province will basically hand over the land for the Bien Hoa - Vung Tau expressway.

6-lane road at the gateway to Ho Chi Minh City is at risk of being delayed due to land congestion

MINH QUÂN |

HCMC – The project to upgrade and expand Duong Quang Ham Street (Go Vap District) is facing the risk of not being completed on schedule due to land acquisition problems.